Land clearance bottlenecks threaten the goal of opening Huu Nghi - Chi Lang expressway

Khánh Linh |

Lang Son - 122 households have not been relocated, along with a series of other difficulties, causing the Huu Nghi - Chi Lang expressway to face the risk of being behind schedule.

The Huu Nghi - Chi Lang border gate expressway project - one of the key transport projects in the Northern border area - is facing many difficulties and obstacles in site clearance (GPMB), relocation of technical infrastructure, seriously affecting the construction progress.

If the problems are not resolved promptly, the goal of opening the entire route to traffic before December 19, 2025 according to the direction of the Government is at risk of not being completed.

According to Huu Nghi - Chi Lang Expressway Joint Stock Company, by July 7, the project had only reached more than 28% of the construction volume, while site clearance (GPMB) was still facing many difficulties.

The entire route has handed over 544.18 hectares of land, accounting for 97.6% of the FS step plan, but the arising part according to the technical design (TKKT) has only been completed more than 41%.

Currently, there are still 122 households that have not been relocated, 66 households and organizations have not handed over land, mainly due to not agreeing on a compensation unit price or land disputes.

In addition, the project still has 40 locations for un relocated technical infrastructure, including power lines, telecommunications, and railway signals. 8/44 dumping sites have not been cleared, seriously affecting the construction progress.

Nhung “ngoi nha giua duong” tren cao toc 11.000 ti dong vung bien xu Lang. Anh: Khanh Linh
"Houses in the middle of the road" on the 11,000 billion VND expressway in the border area of Lang Son. Photo: Khanh Linh

On the site that has been handed over, contractors have mobilized more than 2,500 workers, more than 1,100 pieces of machinery and deployed 141 construction teams on 4 packages.

However, the construction volume is still very slow compared to requirements. To date, the volume of newly dug ground has reached more than 47.7%, K95 filling has reached 56.3%, and the underpass for people has been completed about 42.3%.

In particular, important items such as asphalt concrete pavement have only reached about 0.5%, a very low rate compared to the requirements for traffic opening progress.

The total accumulated construction value has only reached about 1,859 billion VND, equivalent to 28.25% of the contract value. Meanwhile, the State budget capital to support the construction of new projects has been disbursed about 913 billion VND out of a total of more than 3,718 billion VND expected.

The reason for the delay is partly due to the recent merger and reorganization of administrative units in Lang Son, causing disruptions to the local government apparatus, affecting site clearance work.

Thi cong dem tren tuyen cao toc. Anh: Khanh Linh
Construction at night on the expressway. Photo: Khanh Linh

Speaking with reporters, Mr. Bui Quoc Khanh - Director of the Lang Son Provincial Construction Investment Project Management Board said that according to the assessment, the Huu Nghi - Chi Lang expressway project is behind schedule.

Explaining the reason, the leader of the Provincial Construction Investment Project Management Board said that partly due to the project site, however, the main reason is unfavorable weather conditions. For the past month, there have been consecutive heavy rains in the area, making construction difficult.

Currently, to meet the goal of opening the entire route on a layer of asphalt concrete before December 19, 2025 according to the Government's direction, Huu Nghi - Chi Lang Expressway Joint Stock Company has proposed that the People's Committee of Lang Son province resolutely direct the completion of site clearance, relocation of technical infrastructure, and handover of remaining dumping sites before July 20.

At the same time, it is recommended that localities speed up the approval of compensation, support and resettlement plans; increase propaganda and mobilize people to agree to receive compensation and hand over land.

The Huu Nghi - Chi Lang border gate expressway is nearly 60 km long, with a total investment of more than VND 11,000 billion in the phased phase. Of which, state capital accounts for about 49.85%. After completion, the route is expected to shorten the connection time from Huu Nghi border gate to Bac Giang - Lang Son expressway, increase transportation capacity, and promote trade in border areas.

Khánh Linh
TIN LIÊN QUAN

Meals to enjoy at the Can Tho - Ca Mau expressway construction site

|

Can Tho - At the Can Tho - Ca Mau expressway construction site, some workers have started their lunch break, while others continue their asphalt paving work.

Adding a car ban sign to the Van Ninh - Cam Lo expressway under construction

|

Quang Tri - Signs prohibiting and blocking entrances and exits to the Van Ninh - Cam Lo expressway to ensure traffic safety for people, vehicles and construction units.

Land along the Hoa Binh - Moc Chau Expressway heats up

|

Phu Tho - Northwest real estate heated up after the merger of provinces, land along the Hoa Binh - Moc Chau expressway attracted investors thanks to infrastructure and tourism potential.

Horsemen on the A80 parade training ground

|

In the midst of the hot weather, the Cavalry Mobile Police formation still practiced tirelessly, ready for the A80 parade mission.

Chairman of Khanh Hoa province directs inspection of the Quan Truong river leveling case

|

Khanh Hoa - Chairman of the Provincial People's Committee directs inspection and handling of violations if there is a case of leveling the Quan Truong River in Nha Trang that Lao Dong Newspaper has reported.

EU announces plan to impose US retaliatory tariffs

|

The EU has proposed retaliatory measures after President Donald Trump threatened to impose a 30% tariff on Europe.

Look up the fastest high school graduation exam scores in 2025 on Lao Dong

|

The 2025 high school graduation exam scores will be announced by the Ministry of Education and Training at 8:00 a.m. on July 16. Candidates can look up the fastest exam scores on Lao Dong.

Meals to enjoy at the Can Tho - Ca Mau expressway construction site

Tạ Quang |

Can Tho - At the Can Tho - Ca Mau expressway construction site, some workers have started their lunch break, while others continue their asphalt paving work.

Adding a car ban sign to the Van Ninh - Cam Lo expressway under construction

HƯNG THƠ |

Quang Tri - Signs prohibiting and blocking entrances and exits to the Van Ninh - Cam Lo expressway to ensure traffic safety for people, vehicles and construction units.

Land along the Hoa Binh - Moc Chau Expressway heats up

Yên San |

Phu Tho - Northwest real estate heated up after the merger of provinces, land along the Hoa Binh - Moc Chau expressway attracted investors thanks to infrastructure and tourism potential.