Vice Chairman of Ho Chi Minh City People's Committee inspects the progress of Nhon Trach bridge and Long Thanh expressway intersection

Anh Tú |

Ho Chi Minh City speeds up the progress of the XL1 Ring Road 3 package to open the Nhon Trach bridge connection with the Ho Chi Minh City - Long Thanh - Dau Giay expressway in time.

On July 7, Vice Chairman of the Ho Chi Minh City People's Committee Bui Xuan Cuong directly inspected the XL1 package - the section of the Ho Chi Minh City Ring Road 3 project, directly connecting Nhon Trach Bridge and the Ho Chi Minh City - Long Thanh - Dau Giay Expressway.

 Pho Chu tich UBND TPHCM Bui Xuan Cuong (o giua) tai buoi kiem tra thuc dia. Anh: Anh Tu
Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong (middle) at the field inspection. Photo: Anh Tu

According to the Traffic Construction Investment Project Management Board, the XL1 package has a total investment of VND 2,123 billion, constructing a nearly 2.75km section through the old Thu Duc City. Although the contract term is extended to November 2026, the units are speeding up the progress to complete and open the main route connecting the expressway in December 2025 and the parallel road in June 2026.

 Hang muc cau Nhon Trach da hoan thanh dang cho ket noi. Ảnh: Anh Tu
The Nhon Trach bridge project has been completed and is waiting for connection. Photo: Anh Tu

As of the end of June 2025, package XL1 has reached 53.7% of the total construction output, leading among 6 packages starting the second phase of the Ho Chi Minh City Ring Road 3 project.

To synchronize with the progress of Nhon Trach Bridge, units are focusing on constructing items at the intersection with the Ho Chi Minh City - Long Thanh - Dau Giay Expressway. Currently, the entire concrete section of branch A has been completed, branches D and E and about 400m of the main route have reached 50% of the crushed stone layer. The asphalt concrete paving is expected to be completed before August 15.

  Toan canh doan goi thau XL1 thi cong ket noi cau Nhon Trach voi cao toc TP.HCM - Long Thanh - Dau Giay. Anh: My Quynh
Overview of the XL1 package connecting Nhon Trach Bridge with the Ho Chi Minh City - Long Thanh - Dau Giay Expressway. Photo: My Quynh

In addition, for completed items such as traffic safety systems, lighting, and technical designs that are being appraised, it is expected to be completed in July. The contractor selection will be completed in August 2025, construction will be implemented and completed by the end of September 2025, a shortening of 9 months compared to the original progress.

 Phuong an mo duong tam de ket noi cau Nhon Trach voi cao toc. Ảnh: Anh Tu
Plan to open a temporary road to connect Nhon Trach bridge with the expressway. Photo: Anh Tu

In addition, the remaining branches of the Ho Chi Minh City - Long Thanh - Dau Giay expressway intersection, which are branches B and C, are also being focused on by the contractor, aiming to complete the opening of the main overpass in December 2025.

To facilitate people's travel during the September 2 holiday and promptly connect traffic between Nhon Trach Bridge and the expressway, the investor and contractor have agreed to deploy a temporary traffic organization plan - phase 1.

According to the plan, the main route of about 400m long under the XL1 package will be completed before August 19 to allow vehicles to circulate first. The remaining items such as branch road D, branch E, branch bridge A and lighting system, traffic safety will continue to be constructed, completed before September 30.

At the same time, at the intersection, an additional two-way section will be opened about 200m long. Thanks to that, vehicles from Dong Nai after crossing Nhon Trach Bridge can go straight 900m through the road on the Ho Chi Minh City side, then turn right into the toll station to get onto the Ho Chi Minh City - Long Thanh - Dau Giay Expressway. The reverse is also organized similarly, ensuring temporary traffic during the completion of the entire project.

At the inspection, Vice Chairman of the Ho Chi Minh City People's Committee Bui Xuan Cuong acknowledged the efforts of investors and contractors, especially in unfavorable weather conditions and scarce material sources. He requested units to continue to increase human resources, equipment, and work in three shifts continuously to ensure the set progress.

"The project is on schedule, with a clear plan to open phase 1 on August 19 and complete the entire project by the end of September. This is a key project, not only serving the connection of Nhon Trach Bridge but also ensuring the opening of the 15km section of Ring Road 3 this year, Mr. Cuong emphasized.

The city's leaders also requested the Traffic Department to review and summarize difficulties beyond its authority in all bidding packages so that the Ho Chi Minh City People's Committee can promptly resolve them, creating maximum conditions for the project to complete as committed.

Anh Tú
RELATED NEWS

HCMC speeds up the progress of Ring Road 3, aiming to connect Nhon Trach bridge by September

|

Ho Chi Minh City speeds up the construction of package XL1, striving to connect with Nhon Trach Bridge in September 2025.

Under the Ring Road 3 bridge on Nguyen Xien street, a giant landfill has been turned into

|

Hanoi Despite the prohibition signs, the area under the Ring Road 3 bridge (through Nguyen Xien Street, Hanoi) has turned into a giant garbage collection point.

Selecting the investment option to complete 15.3km of road coinciding with the Ho Chi Minh City Ring Road 3 project

|

HCMC - 6 overpasses or underpasses will be invested in construction at the intersection with My Phuoc Tan Van road, a 15.3km section coinciding with the Ho Chi Minh City Ring Road 3 project.

Hanoi accelerates 10 drainage projects, handles 220 flooded points before the 2026 rainy season

|

Hanoi accelerates 10 urgent drainage projects, handles 220 flooded points, ensuring completion before the 2026 rainy season.

Russian military transport plane crashes in Crimea, all 29 people killed

|

The Russian Ministry of Defense said 6 crew members and 23 passengers were killed in the crash of a Russian military transport plane in Crimea.

Italy national team absent for the third consecutive World Cup

|

In the early morning of April 1st (Vietnam time), Italy lost to Bosnia Herzegovina in a penalty shootout in the 2026 World Cup play-off final.

Canal pollution through two wards in Ho Chi Minh City

|

Ho Chi Minh City - The situation of waste and black water pollution in the canal through Tan Son Nhi and Tay Thanh wards is affecting the lives of Ho Chi Minh City residents.

Base salary expected to increase, preschool teachers are both excited and worried about prices

|

The proposal to increase the base salary from July 1, 2026 makes many kindergarten teachers excited, but also worried that living costs may increase accordingly.

HCMC speeds up the progress of Ring Road 3, aiming to connect Nhon Trach bridge by September

Anh Tú |

Ho Chi Minh City speeds up the construction of package XL1, striving to connect with Nhon Trach Bridge in September 2025.

Under the Ring Road 3 bridge on Nguyen Xien street, a giant landfill has been turned into

Cao thơm - Nguyễn Linh |

Hanoi Despite the prohibition signs, the area under the Ring Road 3 bridge (through Nguyen Xien Street, Hanoi) has turned into a giant garbage collection point.

Selecting the investment option to complete 15.3km of road coinciding with the Ho Chi Minh City Ring Road 3 project

ĐÌNH TRỌNG |

HCMC - 6 overpasses or underpasses will be invested in construction at the intersection with My Phuoc Tan Van road, a 15.3km section coinciding with the Ho Chi Minh City Ring Road 3 project.