The National Assembly opens a knot, waiting for Ho Chi Minh City to rescue a 10,000 billion VND flood prevention project

MINH QUÂN |

HCMC - The nearly VND10,000 billion flood prevention project has been on hold for 5 years, with the opportunity to re-construct when the National Assembly allows HCMC to use land to pay investors.

Near the end of 2025, the project "Solving flooding caused by tides in the Ho Chi Minh City area taking into account climate change factors (phase 1)" with a total investment of nearly 10,000 billion VND has not been able to be restarted, although the project has been 94% complete.

Started in 2016 under the BT (build - transfer) form, the project had to be temporarily suspended from November 2020 due to legal problems, especially procedures for paying land funds to investors.

Although the Government has issued two resolutions (Resolution 40/NQ-CP and Resolution 212/NQ-CP) to resolve the issue, the project continues to "stand firm".

Adding a payment land fund is a prerequisite for the project to resume construction. According to Resolution 212/NQ-CP, Ho Chi Minh City is paid to investors with land funds.

In case the value of the land fund is lower than the value of the BT project (after reviewing and excluding unreasonable costs), the difference will be paid with public investment capital of Ho Chi Minh City.

The project working group has proposed 5 land areas to include in the BT contract appendix, including: 257 Tran Hung Dao (2,374 m2, provisional value of more than VND 597 billion); 420 No Trang Long (66,800 m2, about VND 5,385 billion); Lot C8A - Area A, New Urban Area of South Ho Chi Minh City (5,500 m2, more than VND 1,113 billion); 232 Do Xuan Hop (14,000 m2, more than VND 930 billion); 762 Binh Quoi (3,100 m2, about VND 72.3 billion).

The total value of the 5 plots of land is more than VND 8,099 billion, equivalent to 81.1% of the value of the BT contract. However, the payment of land funds has not yet been finalized, making it impossible to sign a contract appendix for the investor to re-construct.

Duong Tran Xuan Soan ngap nang khi trieu cuong dang, trong khi cong ngan trieu Tan Thuan ben canh da hoan thanh hon 90% phai tam dung. Anh: Nhu Quynh
Tran Xuan Soan Street was heavily flooded due to high tides, while the Tan Thuan tidal sluice nearby, which was more than 90% complete, had to be temporarily suspended. Photo: Nhu Quynh

On December 11, the National Assembly passed a Resolution amending and supplementing Resolution 98 on piloting a number of specific mechanisms and policies for the development of Ho Chi Minh City, creating a clear legal basis for handling BT contracts signed before the PPP Law took effect but have not been paid.

According to the resolution, investors are paid by land fund or public assets according to the Law on Management and Use of Public Assets; land fund recovered or managed by the State under the Land Law; or combining these land funds. If the land fund is partly managed by a State agency, the Ho Chi Minh City People's Committee will reclaim the entire land to allocate or lease, without auction and without bidding to select investors.

The Ho Chi Minh City People's Committee decides on land used for payment, negotiation and signing of BT contract appendices with investors and project enterprises.

If the BT contract has not been allocated or leased, the Ho Chi Minh City People's Committee will allocate or lease the land based on the value of the accepted and audited volume. Land prices for calculating land use fees or land rents are determined according to the law on land and the law on investment under the PPP method.

Dr. Tran Quang Thang - Director of the Ho Chi Minh City Institute of Economics and Management - assessed the National Assembly's permission to pay land funds for BT projects as a "legal turning point" to remove the biggest bottleneck of the nearly 10,000 billion VND flood prevention project.

The Resolution to adjust and supplement Resolution 98 creates a clear and transparent legal corridor, removing concerns that have existed for many years. Accordingly, the Ho Chi Minh City People's Committee has the right to sign a contract appendix and add a payment land fund without having to go through an auction" - Mr. Thang said.

Mr. Tran Quang Thang said that the project's completion of 94% but stagnation for the past 5 years is a "very great waste", every day of delay increases interest rates and puts pressure on both the city and investors.

Although the mechanism has been approved, according to Mr. Thang, Ho Chi Minh City must immediately shift from "waiting" to "acting", determining the land fund for payment, land valuation, completing the contract appendix and clearly defining responsibilities between departments and branches. "If there is no drastic action, the project can still be delayed even though the mechanism has been opened".

Mr. Thang also warned that the delay will directly affect Ho Chi Minh City's ability to prevent flooding and adapt to climate change.

MINH QUÂN
RELATED NEWS

Resolutely answer voters when the 10,000 billion VND flood prevention project will be completed

|

At the meeting on September 27, many voters in Ho Chi Minh City expressed special interest in the progress of the 10,000 billion VND tidal prevention project.

The Government issues a resolution to remove obstacles for the 10,000 billion VND flood prevention project in Ho Chi Minh City

|

HCMC - The nearly VND10,000 billion flood prevention project and the Ring Road 2 section with a capital of more than VND2,700 billion have just been resolved by the Government to remove difficulties and obstacles.

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

|

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.

Plan to invest in surgical robots with the ability to perform precise surgery at Viet Duc Hospital, Facility 2

|

Viet Duc Hospital accelerates investment in modern equipment, preparing high-quality human resources to ensure similar treatment quality between the two facilities.

Struggling to handle an abandoned VND17 billion center in Thanh Hoa

|

Thanh Hoa - An agricultural center with an investment of more than 17 billion VND has been abandoned for many years, and up to now, the handling and exploitation are still struggling to find a solution.

Love for ex-lover: How to deal with it to keep your father from getting hurt

|

Loveing an ex-lover of a best friend is something that confuses many people. So how can you not hurt others and not deny your own feelings?

Live Vietnam vs Laos men's volleyball at SEA Games 33

|

Live match between the Vietnamese and Lao men's volleyball teams at the 33rd SEA Games, taking place at 15:00 on December 13.

Forecast of bad weather in the next 2 days due to the strengthening of cold air

|

The weather forecast for the Gulf of Tonkin continues to be affected by cold air; from the night of December 14, the wind will gradually decrease.

Resolutely answer voters when the 10,000 billion VND flood prevention project will be completed

Lê Thanh Phong |

At the meeting on September 27, many voters in Ho Chi Minh City expressed special interest in the progress of the 10,000 billion VND tidal prevention project.

The Government issues a resolution to remove obstacles for the 10,000 billion VND flood prevention project in Ho Chi Minh City

MINH QUÂN |

HCMC - The nearly VND10,000 billion flood prevention project and the Ring Road 2 section with a capital of more than VND2,700 billion have just been resolved by the Government to remove difficulties and obstacles.

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

MINH QUÂN |

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.