Review of compensation for the extended Ly Thai To road project

Khánh Linh |

Lang Son - The province requests to review land records at the Ly Thai To extended road project, to prevent overlapping compensation or omission of people's rights.

On August 26, the Office of Lang Son Provincial People's Committee said that the leaders of the Provincial People's Committee had just assigned the Department of Agriculture and Environment to take the lead in handling obstacles in site clearance for the Ly Thai To extended road project and the residential and resettlement area of Lang Son City.

The decision was made after Dong Kinh Ward People's Committee reported difficulties in the process of reviewing and resolving petitions related to project boundaries at the beginning of the route.

The Department of Agriculture and Environment will coordinate with the Provincial Construction Investment Project Management Board, the Provincial Land Fund Development Center and related units to inspect cadastral records through each period.

Land acquisition dossiers, compensation, site handover and related documents must also be compared.

From the review results, specialized agencies determine the legal basis and solutions for each case. The Provincial People's Committee requests that the handling must be in accordance with regulations, not allowing overlapping compensation or omission of legitimate rights of land users.

The results of handling and contents beyond authority, if any, must be reported to the Provincial People's Committee before September 10.

The Ly Thai To extended road project and residential and resettlement area of Lang Son City, now belonging to Dong Kinh ward, is invested by the Lang Son Provincial Construction Investment Project Management Board.

The project has a total area of 24.51 ha, affecting 543 households, individuals, organizations and residential communities.

The project is expected to contribute to completing infrastructure and changing the urban appearance, but the site clearance process is still entangled in compensation dossiers that have existed for more than 30 years.

Mr. Hoang Van Duc - Head of the Economic, Infrastructure and Urban Department of Dong Kinh ward - said that previously, compensation had not been resolved definitively due to prolonged time, and some related documents were lost.

In addition, the project has undergone many adjustments, bearing different names, making it difficult to verify the subjects and pay compensation.

According to Mr. Duc, related documents have recently been found. The Land Fund Development Center is verifying and reviewing affected cases, and at the same time comparing them with old documents to serve as a basis for paying people.

Khánh Linh
RELATED NEWS

After the flood, Lang Son people join forces to rebuild their lives

|

Lang Son is urgently overcoming the consequences of floods. People and forces are clearing mud, cleaning houses, schools, and people's markets to soon stabilize their lives.

Floodwaters recede, schools in Lang Son are busy cleaning up before the opening ceremony

|

Lang Son - Floodwaters passing through leave mud and garbage, making the work of overcoming and cleaning up even more difficult, especially at schools.

Rushing to untie the knot to save the 700 billion VND project from a prolonged deadlock

|

Lang Son - With a total investment of nearly 700 billion VND, the Ly Thai To extended road project has only received handover of only 1.52% of the site.

Grab drivers call for turning off apps, concerned about fees on each trip

|

Many Grab drivers reflect that they are not clear about the fee calculation method and the actual amount received per trip, while on social networks, a call to turn off the app on December 12-13 appeared. 9.

Risk of tropical depression coming soon in the East Sea, forecast of heavy rain in the area

|

Forecast that the low pressure area in the East Sea is likely to strengthen into a tropical depression; the situation of heavy rain in the Central region is likely to become complicated.

Many roads in Ho Chi Minh City quickly flooded in the rain on the evening of September 10th

|

Heavy rain in the late afternoon of September 10 caused water to rise rapidly, causing flooding on many roads in Ho Chi Minh City, causing difficulties for people on the way to work.

Successfully rescuing people in the fast-flowing floodwaters in Dak Lak

|

Dak Lak - Functional forces have successfully rescued a resident swept away in the floodwaters.

After the flood, Lang Son people join forces to rebuild their lives

Khánh Linh - Phùng Minh |

Lang Son is urgently overcoming the consequences of floods. People and forces are clearing mud, cleaning houses, schools, and people's markets to soon stabilize their lives.

Floodwaters recede, schools in Lang Son are busy cleaning up before the opening ceremony

Việt Bắc - Khánh Linh |

Lang Son - Floodwaters passing through leave mud and garbage, making the work of overcoming and cleaning up even more difficult, especially at schools.

Rushing to untie the knot to save the 700 billion VND project from a prolonged deadlock

Khánh Linh |

Lang Son - With a total investment of nearly 700 billion VND, the Ly Thai To extended road project has only received handover of only 1.52% of the site.