The most polluted canal in Ho Chi Minh City is about to be renovated with 17,000 billion VND

MINH QUÂN |

HCMC - After many years of waiting, the Xuyen Tam canal renovation project, the most polluted canal in the city, with a total capital of more than VND17,000 billion, will start construction in April 2025.

On February 22, Mr. Dau An Phuc - Director of the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board ( urban Infrastructure Board - investor) said that the Xuyen Tam canal renovation project is completing procedures to start construction in April 2025, on the occasion of the 50th anniversary of the Liberation of the South and National Reunification.

The project initially had a total investment of more than VND9,600 billion, but was later adjusted to increase to more than VND17,000 billion, most of which was compensation and site clearance costs.

In particular, compensation funds have increased from nearly VND6,600 billion to nearly VND14,000 billion due to the application of new compensation prices under the 2024 Land Law.

Nguoi dan ven rach Xuyen Tam nhieu nam song chung voi o nhiem.  Anh: Anh Tu
People along Xuyen Tam canal have lived with pollution for many years. Photo: Anh Tu

According to Mr. Dau An Phuc, the project is divided into three packages. Package XL-03 from Luong Ngoc Quyen Street to Vam Thuat River in Go Vap District is expected to complete contractor selection before March 15 to start construction before April 30, 2025.

The remaining two packages, XL-01, from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy bridge and XL-02, from Bui Dinh Tuy bridge to Luong Ngoc Quyen street, including Binh Loi, Binh Trieu and Cau Son canals, are expected to complete the contractor selection in the first quarter of 2025.

Du an cai tai rach Xuyen Tam can thu hoi dat hon 2.000 ho dan.  Anh: Anh Tu
The Xuyen Tam canal renovation project needs to reclaim land from more than 2,000 households. Photo: Anh Tu

Although the plan to start the Xuyen Tam canal renovation project is clear, the site clearance work still has many problems.

In Go Vap district, the project needs to reclaim 2.5 hectares of land, affecting 138 households, of which 40 households were cleared.

Currently, only 35 cases have been handed over, Go Vap district needs to complete the remaining site in April to ensure the progress of construction.

In Binh Thanh District, the project needs to reclaim 17.3 hectares of land, affecting 2,077 cases, including 1,230 households and 23 organizations that were completely cleared.

At the end of 2024, the People's Committee of Binh Thanh District approved the compensation, support and resettlement plan for the Xuyen Tam canal renovation project.

Currently, Binh Thanh District has also developed a detailed plan for compensation, support, and resettlement for 1,660 cases.

The remaining 417 cases will be handled after the conclusion of the Ho Chi Minh City People's Committee, including 382 cases related to the purchase and sale of handwritten documents and land division after July 1, 2014 and 35 cases within the scope of the two projects of Xuyen Tam canal and Binh Hoa Residential Area in Ward 13.

The Urban Infrastructure Board recommends that Binh Thanh District coordinate with relevant units to promptly complete procedures, ensuring the handover of the construction site for the XL-03 package in Ward 13, and at the same time complete the handover of the XL-01 and XL-02 packages before April 30, 2025.

Rach Xuyen tam hien nay. Anh: Minh Quan
Xuyen Tam Canal today. Photo: Minh Quan
Phoi canh rach Xuyen Tam sau khi cai tao.  Anh: Ban ha tang do thi
Perspective of Xuyen Tam canal after renovation. Photo: Urban Infrastructure Board

Xuyen Tam Canal is nearly 9km long, flowing through Binh Thanh and Go Vap districts, considered the most polluted canal in Ho Chi Minh City.

The main canal is 6.7km long from Nhieu Loc - Thi Nghe canal to Vam Thuat river and three branches are more than 2.2km long (Son, Binh Trieu, Binh Loi bridge branch).

The Xuyen Tam canal renovation project includes dredging the canal bed to a depth of 3.5m and widening the canal bed from 20 - 30m. The wastewater and rainwater collection system will be built synchronously, helping to improve environmental quality and prevent pollution.

On both sides of the canal, a 6m wide road will be built with two lanes on each side, along with 3 - 4m wide sidewalks and a system of parks and trees.

The entire project is expected to be completed in 2028, not only helping to reduce pollution and prevent flooding but also contributing to the socio-economic development of the area.

MINH QUÂN
TIN LIÊN QUAN

Evacuation of 1,270 households in Binh Thanh and Go Vap, where will they be resettled?

|

HCMC - 1,270 households completely cleared in Binh Thanh and Go Vap districts to renovate Xuyen Tam canal will be resettled in many different locations.

Binh Thanh reclaims 53.7 hectares of land, clears 1,230 households

|

HCMC - Binh Thanh District reclaimed 53.7 hectares of land, affecting 2,077 cases, including 1,230 households that were completely cleared to implement the Xuyen Tam canal renovation project.

Ho Chi Minh City clears 1,230 households in Binh Thanh, when will compensation be paid?

|

HCMC – The Xuyen Tam canal renovation project through Binh Thanh district will reclaim land from 2,077 cases (clearing 1,230 households), and pay compensation from December.

Hour 9: I am the third person - Part 2

|

Hour 9 - The husband in the story has developed feelings for his wife's best friend. Where will this marriage go?

Mobilizing resources to treat accident victims on National Highway 6

|

The accident on National Highway 6, Sup Vat commune, Yen Chau district, Son La province caused many casualties and heavy casualties were transferred to the upper level.

Ho Chi Minh City University of Education has many violations in the 17.42 billion VND project

|

The Inspectorate of the Ministry of Education and Training concluded that Ho Chi Minh City University of Education has limitations, shortcomings, and violations related to the project with an investment of 17.42 billion VND.

Man United escaped defeat against Everton

|

Everton drew 2-2 with Man United in the match of round 26 of the Premier League on the evening of February 22 (Vietnam time).

making a living on landfills

|

Soc Trang - The landfill is a home, the only source of life for dozens of households.

Evacuation of 1,270 households in Binh Thanh and Go Vap, where will they be resettled?

MINH QUÂN |

HCMC - 1,270 households completely cleared in Binh Thanh and Go Vap districts to renovate Xuyen Tam canal will be resettled in many different locations.

Binh Thanh reclaims 53.7 hectares of land, clears 1,230 households

MINH QUÂN |

HCMC - Binh Thanh District reclaimed 53.7 hectares of land, affecting 2,077 cases, including 1,230 households that were completely cleared to implement the Xuyen Tam canal renovation project.

Ho Chi Minh City clears 1,230 households in Binh Thanh, when will compensation be paid?

MINH QUÂN |

HCMC – The Xuyen Tam canal renovation project through Binh Thanh district will reclaim land from 2,077 cases (clearing 1,230 households), and pay compensation from December.