Xuyen Tam canal in Ho Chi Minh City: Busy construction sites, struggling places waiting for site clearance

Bảo Tú |

Ho Chi Minh City - The progress of Xuyen Tam canal reveals a contradiction between the bustling construction area and the difficult sections waiting for site clearance.

Recorded at construction package XL03, the section from Vam Thuat river to Luong Ngoc Quyen bridge, especially in the area near Van Lang University, is currently the place with the most urgent working atmosphere throughout the project. Started on May 15, 2025 with a construction time of 450 days, the contractor is focusing maximum manpower and equipment to accelerate progress.

 Nhìn từ trên cao, công trường gói thầu XL03 đoạn qua Trường Đại học Văn Lang hoạt động nhộn nhịp với máy xúc, xe cẩu bám sát mép rạch. Ảnh: Anh Tú
Looking from above, the construction site of package XL03, the section passing through Van Lang University, is bustling with excavators and construction cranes. Photo: Anh Tu
 Gói thầu XL03 đang được đẩy nhanh tiến độ thi công kể từ khi khởi công vào tháng 5/2025.
The contractor is implementing important items such as pouring concrete for dyke walls and installing drainage systems. Some sections have completed dyke pile driving. Photo: Anh Tu
 Dự kiến XL3 sẽ thông xe kỹ thuật vào tháng 4 tới. Ảnh: Anh Tú
It is expected that the 500m section in front of Van Lang University will be technically opened to traffic in April. Photo: Anh Tu

According to the plan, the section in front of Van Lang University is expected to be technically opened to traffic in April and basically complete the items in June 2026. The investor and contractors are aiming to complete and hand over the entire XL03 package in November 2026.

As for the remaining two bidding packages, XL01 and XL02, they are facing many difficulties, mainly due to incomplete site clearance. At bidding package XL02, the section from Bui Dinh Tuy street to Luong Ngoc Quyen street, including Binh Loi and Binh Trieu canal branches, although construction started on December 5, 2025, this area is still mainly in the process of site clearance.

 Tại gói XL02, mặt bằng hai bên rạch vẫn đang được dọn dẹp, việc triển khai thi công chỉ mới bắt đầu ở một vài vị trí. Ảnh: Anh Tú
At package XL02, the ground on both sides of the canal is still being cleaned up, and construction has only just started in a few locations. Photo: Anh Tu
Hình ảnh ghi nhận tại đoạn gần cầu Phan Chu Trinh thuộc gói XL02. Một vài máy ép cọc đang hoạt động trên phần diện tích nhỏ hẹp vừa được giải tỏa. Ảnh: Thái Bảo
Images recorded at the section near Phan Chu Trinh bridge belonging to package XL02. A few pile pressing machines are operating on a small area that has just been cleared. Photo: Thai Bao

The delay is most clearly shown at package XL01, the section from Bui Dinh Tuy bridge to Nhieu Loc - Thi Nghe canal. Here, almost no clear changes in construction have been recorded. The presence of dilapidated houses extending out into the canal shows that the volume of clearance here is still very large.

Nhìn từ trên cao khu vực rạch Xuyên Tâm giao với kênh Nhiêu Lộc - Thị Nghè thuộc gói XL01. Dòng rạch bị che khuất bởi nhà cửa san sát và cây xanh, chưa có dấu hiệu thi công
Looking from above, the Xuyen Tam canal area intersecting with the Nhieu Loc - Thi Nghe canal belonging to package XL01. The canal is obscured by houses close together and green trees, with no signs of construction. Photo: Anh Tu

In fact, the Xuyen Tam canal renovation project has a total investment of more than 17,200 billion VND, of which compensation, support and resettlement costs account for the majority with nearly 14,000 billion VND. The project affects nearly 2,200 households and organizations, creating huge pressure on site clearance work in Binh Thanh and Go Vap districts before.

  Gói thầu XL01 vẫn còn nhiều vướng mắc về mặt bằng. Ảnh: Anh Tú
Package XL01 still has many problems with land. Photo: Anh Tu
Các hộ dân gói XL1 đã bắt đầu tháo dỡ nhà cửa bàn giao mặt bằng. Ảnh: Thái Bảo
Some households in package XL1 have started dismantling houses and handing over land. Photo: Thai Bao

To solve the resettlement problem, Ho Chi Minh City is urgently implementing the Social Housing project at No. 4 Phan Chu Trinh, Binh Thanh ward. The project includes 3 20-story apartment blocks, developed according to the model of housing combined with commerce and services. This place will serve resettlement for households affected by the Xuyen Tam canal project, contributing to ensuring social security for people who give up land for the project.

Toàn cảnh dự án nhà ở xã hội tại số 4 Phan Chu Trinh với 3 khối chung cư B1, B2, B3 cao 20 tầng
Overview of the social housing project at No. 4 Phan Chu Trinh with 3 apartment blocks B1, B2, B3, 20 stories high, is being accelerated. Photo: Anh Tu

Recently, Chairman of Ho Chi Minh City People's Committee Nguyen Van Duoc inspected the project progress. Faced with the reality of differentiated progress, city leaders requested departments, branches and localities to flexibly receive and hand over land in parts, accelerate infrastructure relocation and completely remove obstacles. Up to now, 3 wards under the project have paid money to 2,011 households and 787 households have handed over land. Ho Chi Minh City is determined to complete the entire site clearance stage before June 2026 to bring the project to the finish line on schedule in 2028.

Bảo Tú
RELATED NEWS

Ho Chi Minh City clears 1,077 households in the center to revive polluted canals

|

Ho Chi Minh City approved the component project to renovate Van Thanh canal with a total capital of more than 1,743 billion VND, about 1,077 households will be cleared to implement the project.

Renovating the most polluted canal in Ho Chi Minh City, many people dismantle houses to hand over land

|

Ho Chi Minh City - Many households along Xuyen Tam canal voluntarily dismantled houses, handed over land, and joined hands to renovate the canal considered the most polluted in the city.

Ho Chi Minh City misses the land handover deadline for the Xuyen Tam canal renovation project

|

Ho Chi Minh City cannot hand over the entire site of the Xuyen Tam canal renovation project in November 2025 according to the direction of Ho Chi Minh City Party Secretary Tran Luu Quang.

Deputy Director of Quang Ninh Provincial Police becomes Deputy Head of the Provincial Party Committee's Internal Affairs Commission

|

Quang Ninh - On the morning of March 23, the Standing Committee of the Quang Ninh Provincial Party Committee held a conference to announce decisions on personnel work of the Provincial Party Committee's Internal Affairs Committee.

High interest rates are cyclical, real estate is still a long-term accumulation channel

|

According to experts, the general level of home loan interest rates is currently high in the short term, but this is a cyclical development of the economy.

Kim Jong Un re-elected Chairman of North Korea

|

Mr. Kim Jong Un was re-elected Chairman of the North Korean State Council Committee in the first session of the 15th Supreme People's Assembly.

Hanoi plans to build a 2,000 billion VND theater, 9,000m2 wide

|

Hanoi - In the period 2026-2030, the city will build a theater of about 9,000 m2 on Vo Thi Sau street with an investment of about 2,000 billion VND.

Iranian nuclear power plant at risk of attack

|

US President Donald Trump declares he will eradicate the Iranian nuclear power plant unless Tehran reopens the Strait of Hormuz.

Ho Chi Minh City clears 1,077 households in the center to revive polluted canals

MINH QUÂN |

Ho Chi Minh City approved the component project to renovate Van Thanh canal with a total capital of more than 1,743 billion VND, about 1,077 households will be cleared to implement the project.

Renovating the most polluted canal in Ho Chi Minh City, many people dismantle houses to hand over land

NHƯ QUỲNH - ANH TÚ |

Ho Chi Minh City - Many households along Xuyen Tam canal voluntarily dismantled houses, handed over land, and joined hands to renovate the canal considered the most polluted in the city.

Ho Chi Minh City misses the land handover deadline for the Xuyen Tam canal renovation project

MINH QUÂN |

Ho Chi Minh City cannot hand over the entire site of the Xuyen Tam canal renovation project in November 2025 according to the direction of Ho Chi Minh City Party Secretary Tran Luu Quang.