Barriers, traffic organization to build a bridge on Hanoi Ring Road 2.5

SÓNG HỮU |

Hanoi - Trinh Dinh Cuu and Ha Ke Tan streets are partially fenced off to build an L3 bridge, vehicles will be guided through the temporary road.

On October 28, the Hanoi Department of Construction announced that it had granted a construction permit to Hoang Mai - Hanoi Construction Investment Company Limited to construct the L3 bridge across the Lu River (under the Ring Road 2.5 project, Dam Hong - National Highway 1A section).

The license is valid from October 28, 2025 to March 31, 2026.

Accordingly, Hoang Mai - Hanoi Construction Investment Company Limited is allowed to fence off and separate traffic lanes on Trinh Dinh Cuu and Ha Ke Tan streets to construct the L3 bridge construction item (Km1+394 program) within the scope of road infrastructure protection according to the approved design documents and construction organization, including the following main contents:

Barricading and organizing lane division on Trinh Dinh Cuu Street in status quo to construct the L3 bridge construction item

- Phase 1

Construct temporary road on the left side of the road on the cleared site, temporary road 7m wide (equal to the existing Trinh Dinh Cuu road surface), temporary road length about 48m; vehicles traveling along the existing Trinh Dinh Cuu road through the temporary road construction area.

- Phase 2

Organize a fixed barrier on Trinh Dinh Cuu Street on the right side of the road (frame of the L3 bridge construction area), the barrier length = 48m to serve the construction of the L3 bridge construction item; vehicles traveling according to the temporary road system through the construction barrier area.

Barricading and organizing lane division on Ha Ke Tan Street to construct the L3 bridge construction item

- Phase 1

Construct temporary road on the right side of the road on the cleared site, temporary road 6m wide (equal to the existing Ha Ke Tan road), temporary road length about 47m; vehicles traveling along Ha Ke Tan road through the temporary road construction area.

- Phase 2

Organize a fixed barrier on Ha Ke Tan Street on the left side of the road (frame of the L3 bridge construction area), the barrier length = 47m to serve the construction of the L3 bridge over the Lu River; vehicles traveling according to the temporary road system through the construction barrier area.

At the construction area on Ha Ke Tan Street and Trinh Dinh Cuu Street, the Department of Construction requested investors and contractors to arrange barriers, stretch reflective ropes, install a system of warning signs and night warning lights, and arrange 3 layers of warning in advance to guide people and vehicles participating in traffic.

The investor is responsible for implementing measures to ensure environmental sanitation and measures to ensure labor safety during the construction process, construction machinery is only allowed to circulate within the construction area from 10:00 p.m. to 5:00 a.m.

Outside of the permitted construction hours, construction machinery, vehicles, and electricity must gather within the barrier at the construction site.

SÓNG HỮU
RELATED NEWS

Ready to re-construct the bridge on the billion-dong road that has been unfinished for many years in Hanoi

|

Hanoi - L3 bridge over Lu river - an important item of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, will resume construction from October 2025.

The billion-dollar road in Hanoi is being constructed day and night, the investor is committed to completing it on schedule

|

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being urgently constructed by the contractor, the investor is committed to bringing the project to the finish line in the first quarter of 2026.

The progress of the billion-dollar road in Hanoi is being accelerated, to be completed in 2026

|

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being accelerated by the contractor, the entire route is expected to be completed in 2026.

US Senate blocks Trump's retaliatory tax blow to Brazil

|

The Republican-controlled US Senate has passed a bill to end the emergency that Trump cited to impose tariffs on Brazil.

Cao Bang Steel gang continues to suffer losses when needing capital to expand mining areas

|

Cao Bang - requiring large capital for site clearance and expansion of Na Lua iron mine, Cao Bang Steel Gang Joint Stock Company is facing continuous losses.

Liquidity of the stock market has not improved

|

The declining liquidity of the stock market shows that investor sentiment is still cautious.

Mr. Trump declares reasons for not being able to meet Mr. Kim Jong-un

|

US President Donald Trump said that meeting Mr. Kim Jong-un during his visit to South Korea is unlikely.

Adjusting traffic on 2 routes in the center of Ho Chi Minh City

|

Ho Chi Minh City adjusts the traffic organization of Le Loi and Nam Ky Khoi Nghia streets (Saigon ward) to serve the organization of a fire fighting drill.

Ready to re-construct the bridge on the billion-dong road that has been unfinished for many years in Hanoi

SÓNG HỮU |

Hanoi - L3 bridge over Lu river - an important item of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, will resume construction from October 2025.

The billion-dollar road in Hanoi is being constructed day and night, the investor is committed to completing it on schedule

SÓNG HỮU |

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being urgently constructed by the contractor, the investor is committed to bringing the project to the finish line in the first quarter of 2026.

The progress of the billion-dollar road in Hanoi is being accelerated, to be completed in 2026

SÓNG HỮU |

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being accelerated by the contractor, the entire route is expected to be completed in 2026.