Long Thanh Airport maintains more than 7,300 direct workers, an increase of 4.54%

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport maintains an average of more than 7,300 direct workers, an increase of 4.54% compared to the beginning of the 180-day and night emulation campaign to accelerate project completion.

On June 22, according to Vietnam Airports Corporation - JSC (ACV), after nearly 3 weeks of implementing the emulation movement "180 days and nights to accelerate the completion of Long Thanh International Airport Project", Component Project 3 has a total production value of about 65,602 billion VND, equivalent to 75.97% of the total value of signed contracts.

Specifically for the main construction packages, the accumulated realized value reached more than 56.341 billion VND, equivalent to 67.93% of the contract value. This index increased by 3.35 percentage points compared to the beginning of June 2026, showing that the construction pace is continuing to be pushed up after the peak emulation campaign was launched.

Toàn cảnh sân bay Long Thành. Ảnh: HAC
Overview of Long Thanh airport. Photo: HAC

Regarding construction resources, the construction site currently maintains an average of more than 7,300 direct workers, an increase of about 4.54% compared to the beginning of the campaign.

One of the important results in the past time is the power supply for the project. On June 9, ACV coordinated with Dong Nai Power Company to successfully energize from the 110kV substation to the PWR-ACV power source receiving station through 6 medium-voltage 22kV lines. The completion of energizing contributes to ensuring electricity supply conditions for project loads, serving construction, installation, testing and technical operation.

According to ACV, the current focus is on controlling the roadmap, prioritizing items that are connected, technically synchronized and directly serve the goal of completing the project in 2026.

Bên trong nhà ga hành khách sân bay Long Thành. Ảnh: HAC
Inside the passenger terminal of Long Thanh airport. Photo: HAC

Also according to ACV, in the near future, the project area will enter the peak rainy season in the Southeast region, which is forecast to affect some outdoor construction activities, technical infrastructure, transportation of materials, equipment and construction organization at the site.

Faced with that situation, ACV, together with the Project Management Board, contractors, supervision consultants and related units, proactively developed response plans and adjusted construction plans according to actual weather conditions. In addition to arranging manpower, equipment and materials, units also strengthened labor safety control, maintained continuous construction conditions and minimized adverse impacts caused by weather.

Previously, on June 1, ACV organized the "180-day and night launching ceremony to accelerate the completion of the project and put Long Thanh airport into operation".

HÀ ANH CHIẾN
RELATED NEWS

Land acquisition for Metro extension project from Ho Chi Minh City to Dong Nai and Long Thanh airport

|

Dong Nai - The project to extend the Ben Thanh - Suoi Tien Metro line to the City Administrative Center and Long Thanh airport is about to announce land acquisition.

Long Thanh airport passenger terminal technical operation in September

|

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Long Thanh Airport extends labor recruitment for aviation fuel branch

|

Dong Nai - Long Thanh Airport (Long Thanh ward) extends labor recruitment for Long Thanh Aviation Fuel Services Branch.

Accelerating 180 days and nights to complete and operate Long Thanh airport

|

Dong Nai - ACV organizes a launching ceremony for 180 days and nights to accelerate the completion of the project and put Long Thanh airport into operation.

Victims recount the case of a passenger car crashing into the rear of a truck, causing 9 casualties

|

Ha Tinh - The injured victim who is being treated at the hospital recounted the horrific moment of the collision between the passenger car and the truck.

Prodigy Yamal scores a "quickie" goal to help Spain defeat Saudi Arabia

|

Lamine Yamal shone brightly with the opening goal in the 10th minute, contributing to Spain's 4-0 victory over Saudi Arabia in Group H of the 2026 World Cup.

Proposing to handle and remove difficulties for a series of slow-progress projects in Song Doc, Ca Mau

|

Ca Mau - Many housing projects and urban areas in Song Doc are behind schedule for a long time, with some projects almost stalled after being approved.

Gold price update morning of June 22: Facing the risk of plummeting

|

Gold price update morning of June 22: Gold prices are receiving negative forecasts from many Wall Street experts, the market is likely to prolong its decline.

Land acquisition for Metro extension project from Ho Chi Minh City to Dong Nai and Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to extend the Ben Thanh - Suoi Tien Metro line to the City Administrative Center and Long Thanh airport is about to announce land acquisition.

Long Thanh airport passenger terminal technical operation in September

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Long Thanh Airport extends labor recruitment for aviation fuel branch

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport (Long Thanh ward) extends labor recruitment for Long Thanh Aviation Fuel Services Branch.

Accelerating 180 days and nights to complete and operate Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - ACV organizes a launching ceremony for 180 days and nights to accelerate the completion of the project and put Long Thanh airport into operation.