Accelerating 180 days and nights to complete and operate Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - ACV organizes a launching ceremony for 180 days and nights to accelerate the completion of the project and put Long Thanh airport into operation.

On June 1, at the Long Thanh International Airport construction site (abbreviated as Long Thanh airport), Vietnam Airports Corporation (abbreviated as ACV) organized the "180-day and night launching ceremony to accelerate the completion of the project and put Long Thanh airport into operation", officially launching a peak emulation period throughout the construction site.

Lễ ra quân 180 ngày đêm tăng tốc hoàn thành dự án và đưa sân bay Long Thành vào khai thác. Ảnh: ACV
180-day and night launching ceremony to accelerate the completion of the project and put Long Thanh airport into operation. Photo: ACV

To date, the project has reached 75.97% of the total value of signed contracts; many key items have reached high progress, in which runway No. 1 has been completed and put into technical operation.

Long Thanh airport passenger terminal (the heart of the project) has completed the entire main structure and is entering the completion and equipment installation phase, ready for the sprint towards the finish line.

At the ceremony, ACV presented gifts of encouragement to representatives of contractors, engineers and workers who are directly constructing at the construction site.

HÀ ANH CHIẾN
RELATED NEWS

Dong Nai reclaimed more than 1,164 hectares of land near Long Thanh airport

|

Dong Nai - The project has a total recovered land area of about 1,164.5 ha, with a total project investment of more than 983 billion VND.

Close-up of the "heart" construction site of Long Thanh airport passenger terminal

|

Dong Nai - Long Thanh Airport aims to put into commercial operation in the fourth quarter of 2026.

Leasing more than 1,900ha of land in 2 industrial parks near Long Thanh airport

|

Dong Nai - Bau Can - Tan Hiep Industrial Park and Xuan Que - Song Nhan Industrial Park have prime locations near Long Thanh airport.

Close-up of 6 aircraft fuel tanks of 6,000 m3/tank at Long Thanh airport

|

Dong Nai - Each floating tank of the fuel supply system at Long Thanh airport has a capacity of 6,000 m3.

Commune chairman may be allowed to decide on the rental price of surplus public land and houses

|

The Ministry of Finance proposes stronger decentralization in the management of redundant public land and houses, the Chairman of the commune can decide the rental price for assets under management.

Hanoi's first specialized school announces benchmark scores for 10th grade in 2026

|

On June 1st, the High School for Gifted Students in Science announced the benchmark scores for 10th grade in 2026.

Pregnant woman dies in Ho Chi Minh City: Establishing a professional council to determine the cause

|

Ho Chi Minh City - A pregnant woman died during a cesarean section at a hospital in Thu Dau Mot ward.

Stock market liquidity declines

|

The stock market is in a period of lack of supporting information, causing many investors to choose to stand aside, and liquidity accordingly decreased sharply.

Dong Nai reclaimed more than 1,164 hectares of land near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project has a total recovered land area of about 1,164.5 ha, with a total project investment of more than 983 billion VND.

Close-up of the "heart" construction site of Long Thanh airport passenger terminal

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport aims to put into commercial operation in the fourth quarter of 2026.

Leasing more than 1,900ha of land in 2 industrial parks near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Bau Can - Tan Hiep Industrial Park and Xuan Que - Song Nhan Industrial Park have prime locations near Long Thanh airport.

Close-up of 6 aircraft fuel tanks of 6,000 m3/tank at Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Each floating tank of the fuel supply system at Long Thanh airport has a capacity of 6,000 m3.