Long Thanh airport is under construction through the September 2 ceremony, racing against the schedule of December 19, 2025

HÀ ANH CHIẾN |

Dong Nai - The Long Thanh airport project will basically be completed on December 19, 2025, put into operation and commercial exploitation in the first half of 2026.

On August 30, according to Vietnam Airports Corporation (ACV), Long Thanh airport is simultaneously implementing construction packages, units mobilizing nearly 14,000 human resources and about 3,000 machines to organize hundreds of construction teams.

Goi thau 5.10 thi cong nha ga hanh khach san bay Long Thanh. Anh: HAC
Package 5.10 for construction of Long Thanh airport passenger terminal. Photo: HAC

In particular, package 5.10 for the construction of the passenger terminal - an item considered a priority gasoline (gantt) of the entire Long Thanh airport project, a consortium of contractors mobilized nearly 6,000 human resources and construction machinery to ensure progress.

Up to now, the passenger terminal has completed the underground reinforced concrete structure and 4 floors; basically completed the installation of steel structure, installed glass wall support, rough construction and is implementing the work of completing the foundation, ceiling, and brick embankment.

The terminal equipment system such as: luggage handling (BHS), aircraft handling (VDGS), escalators, and pedestrian elevators (ES/MW), the contractor has transported materials and equipment to the project and is installing them.

Regarding the items of inland traffic and technical infrastructure, the consortium of contractors mobilized more than 3,300 human resources, machinery to construct the technical tuynel system, regulating lake drainage lines, power supply systems, roads and overpasses.

For packages such as: Fuel supply system; connecting transportation; aircraft parking lot; 2nd runway; cargo terminal, contractor consortium mobilizes thousands of human resources and machinery to speed up construction.

The Long Thanh airport project is targeted to be determined to basically complete the project by December 19, 2025, inaugurate it according to regulations, and move towards commercial exploitation in early 2026.

HÀ ANH CHIẾN
RELATED NEWS

Approving the proposal for the project to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport

|

Dong Nai - The Provincial People's Committee approved the investor's proposal to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport under the form of public-private partnership (PPP).

Prioritizing the recruitment of local workers to work at Long Thanh airport

|

More than 3,000 job opportunities for students and people when the Long Thanh Airport Project comes into operation in 2026, in which, priority will be given to recruiting local workers.

Thousands of jobs at Long Thanh airport, requiring TOEIC English proficiency of 300 or higher

|

Dong Nai - Long Thanh Airport for commercial operation in 2026 is needing more than 4,000 workers, the recruiting unit requires TOEIC English proficiency of 300 or higher.

Warning about the anti-scientific detox trend on social networks

|

Fasting, drinking high-dose lemonade or coffee beans are being praised as detoxifying "panaceas", but they pose many health risks.

Pay attention to building social housing for workers to rent

|

The Chairman of the Trade Union of Saitex International Dong Nai Co., Ltd. hopes that the 14th Congress of the Vietnam Trade Union will pay more attention to housing for workers.

The owner of the hit "Walking in the Brilliant Sky" promises to explode at Green Transformation Day 2026

|

In addition to free experience activities, Green Transformation Day 2026 also has the participation of many famous singers to spread meaningful messages.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Approving the proposal for the project to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The Provincial People's Committee approved the investor's proposal to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport under the form of public-private partnership (PPP).

Prioritizing the recruitment of local workers to work at Long Thanh airport

HÀ ANH CHIẾN |

More than 3,000 job opportunities for students and people when the Long Thanh Airport Project comes into operation in 2026, in which, priority will be given to recruiting local workers.

Thousands of jobs at Long Thanh airport, requiring TOEIC English proficiency of 300 or higher

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport for commercial operation in 2026 is needing more than 4,000 workers, the recruiting unit requires TOEIC English proficiency of 300 or higher.