Long Thanh airport is under construction through the September 2 ceremony, racing against the schedule of December 19, 2025

HÀ ANH CHIẾN |

Dong Nai - The Long Thanh airport project will basically be completed on December 19, 2025, put into operation and commercial exploitation in the first half of 2026.

On August 30, according to Vietnam Airports Corporation (ACV), Long Thanh airport is simultaneously implementing construction packages, units mobilizing nearly 14,000 human resources and about 3,000 machines to organize hundreds of construction teams.

Goi thau 5.10 thi cong nha ga hanh khach san bay Long Thanh. Anh: HAC
Package 5.10 for construction of Long Thanh airport passenger terminal. Photo: HAC

In particular, package 5.10 for the construction of the passenger terminal - an item considered a priority gasoline (gantt) of the entire Long Thanh airport project, a consortium of contractors mobilized nearly 6,000 human resources and construction machinery to ensure progress.

Up to now, the passenger terminal has completed the underground reinforced concrete structure and 4 floors; basically completed the installation of steel structure, installed glass wall support, rough construction and is implementing the work of completing the foundation, ceiling, and brick embankment.

The terminal equipment system such as: luggage handling (BHS), aircraft handling (VDGS), escalators, and pedestrian elevators (ES/MW), the contractor has transported materials and equipment to the project and is installing them.

Regarding the items of inland traffic and technical infrastructure, the consortium of contractors mobilized more than 3,300 human resources, machinery to construct the technical tuynel system, regulating lake drainage lines, power supply systems, roads and overpasses.

For packages such as: Fuel supply system; connecting transportation; aircraft parking lot; 2nd runway; cargo terminal, contractor consortium mobilizes thousands of human resources and machinery to speed up construction.

The Long Thanh airport project is targeted to be determined to basically complete the project by December 19, 2025, inaugurate it according to regulations, and move towards commercial exploitation in early 2026.

HÀ ANH CHIẾN
RELATED NEWS

Approving the proposal for the project to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport

|

Dong Nai - The Provincial People's Committee approved the investor's proposal to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport under the form of public-private partnership (PPP).

Prioritizing the recruitment of local workers to work at Long Thanh airport

|

More than 3,000 job opportunities for students and people when the Long Thanh Airport Project comes into operation in 2026, in which, priority will be given to recruiting local workers.

Thousands of jobs at Long Thanh airport, requiring TOEIC English proficiency of 300 or higher

|

Dong Nai - Long Thanh Airport for commercial operation in 2026 is needing more than 4,000 workers, the recruiting unit requires TOEIC English proficiency of 300 or higher.

The journey to escape the risk of death of victims of online scams in Cambodia

|

Three victims of an online scam in Cambodia recount their journey to risk their lives to escape the " slavery hell" in a human land.

The army of 4 countries China, Russia, Laos, and Cambodia held a rehearsal of the National Day parade

|

The State-level rehearsal of the commemoration, parade, and National Day parade on September 2 was attended by the army of the four countries of China, Russia, Laos, and Cambodia.

75 candidates applying for admission to the University of Finance - Marketing were unjustly accepted and passed the virtual exam

|

HCMC - 75 candidates who registered to apply to the University of Finance - Marketing from failing or vice versa have been resolved.

Heroic moments of the A80 parade and march team

|

The general parade and parade to celebrate the 80th anniversary of the August Revolution and National Day on September 2 attracted the attention of the entire population.

"The Man with the God" Su30-MK2 fires jamming bullets, the air force general inspects the A80 parade

|

The Su-30MK2 squadron dropped powerful bullet in the sky with air Forces flying in a general parade and parade to celebrate the 80th anniversary of National Day.

Approving the proposal for the project to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The Provincial People's Committee approved the investor's proposal to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport under the form of public-private partnership (PPP).

Prioritizing the recruitment of local workers to work at Long Thanh airport

HÀ ANH CHIẾN |

More than 3,000 job opportunities for students and people when the Long Thanh Airport Project comes into operation in 2026, in which, priority will be given to recruiting local workers.

Thousands of jobs at Long Thanh airport, requiring TOEIC English proficiency of 300 or higher

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport for commercial operation in 2026 is needing more than 4,000 workers, the recruiting unit requires TOEIC English proficiency of 300 or higher.