Even though the construction started, the 500 billion VND stadium project still struggles to relocate the grave

Khánh Linh |

Lang Son - After more than 3 years of the investment policy approval, the 500 billion VND stadium complex project is still in the process of site clearance and contractor selection.

The Lang Son Provincial Sports Complex Project is one of the key projects, aiming to turn Lang Son city into a Class I urban area, expected to be an architectural highlight and a regional-scale sports center.

The project includes 11 main items with an area of 29 hectares, including a 4,000-seat multi-purpose gymnasium, a central stadium, an athlete housing area, a training ground system and synchronous technical infrastructure.

The total investment of the project is up to more than 500 billion VND, mainly from the central budget.

According to the plan, this project will be implemented in the period of 2021-2027, with the goal of starting the main items in June 2025 to celebrate the 18th Provincial Party Congress.

On June 9, informing reporters, Mr. Nguyen Manh Duc - Head of the Project Management Department (Lang Son Provincial Construction Investment Project Management Board) - said that site clearance is being carried out to ensure the groundbreaking on June 30, 2025.

As of the morning of the same day, since 1997, 4,164 affected households have had their land counted, of which 41 households have had their assets measured and counted in the field.

However, the selection of contractors has only completed 8/16 packages.

Also according to the leader of the Lang Son Provincial Construction Investment Project Management Board, as of early June 2025, the total disbursed capital had only reached about 1.19% compared to this year's capital plan, an worrying figure in the context of the approaching construction time.

Along with that, the biggest difficulty and obstacle in the project, according to Lang Son province, is the slow movement of graves due to family background.

Some plots of land have not yet been identified. The progress of building specific land prices is also slow; many households have not coordinated to count according to the plan.

San van dong Dong Kinh dang xuong cap nghiem trong. Anh: Khanh Linh
Dong Kinh Stadium is seriously degraded. Photo: Khanh Linh

Regarding the site clearance progress, Mr. Duong Xuan Huyen - Vice Chairman of Lang Son Provincial People's Committee - said that the Provincial People's Committee has requested the investor to urgently complete legal procedures, coordinate with Lang Son City People's Committee and Mai Pha Commune to carry out site clearance work to start the project in June 2025.

Faced with this situation, the Project Management Board has recommended that the People's Committees of Lang Son province and city direct more drastically. It is necessary to increase human resources for the counting work, speed up the progress of compensation, resettlement support and mobilize coordination from the grassroots government to mobilize people to agree.

According to the reporter's research, the Lang Son Provincial Sports Complex Project was invested to replace Dong Kinh Stadium (Lang Son City) - a long-standing sports symbol of the city, currently in a state of serious degradation.

Khánh Linh
TIN LIÊN QUAN

Zeon grass seen at the largest 500 billion VND stadium in the Northern mountainous region

|

Thai Nguyen - Thai Nguyen Provincial Stadium has a total investment of more than 500 billion VND, a scale of 22,000 seats, using standard Zeon Zoysia grass variety.

Agree to repair and upgrade Ha Tinh Provincial Stadium

|

Ha Tinh - The Provincial People's Committee has just agreed in principle to repair and upgrade the provincial stadium according to the proposal of the Department of Culture, Sports and Tourism.

Image of the deterioration of Dong Kinh Stadium before Lang Son spent 500 billion VND to build a new one

|

Lang Son - Dong Kinh Stadium is seriously degraded, the new Sports Complex is about to be implemented.

Leaders of the Vietnam General Confederation of Labor visit workers in difficult circumstances in Hai Phong

|

Hai Phong - On the afternoon of June 9, the working delegation of the Vietnam General Confederation of Labor visited and presented gifts to a number of union members who had work-related accidents and were in difficult circumstances.

New developments on the Metro line worth over 2 billion USD through 6 districts of Ho Chi Minh City

|

HCMC - Metro Line No. 2 (Ben Thanh - Tham Luong) passing through 6 districts 1, 3, 10, 12, Tan Binh and Tan Phu will pilot bid designation, first of all consulting packages.

Hanoi Chairman talks about reducing motorbikes in 4 inner-city districts

|

Hanoi - Chairman of the City People's Committee Tran Sy Thanh said that the city will continue to implement a plan to reduce motorbikes in 4 inner-city districts according to the roadmap.

Multiple accidents on Ho Chi Minh Road leave 6 people dead or injured

|

Thanh Hoa - A series of accidents involving 3 vehicles on the Ho Chi Minh trail left 1 person dead and 5 others injured.

Candidates confidently get high scores in the 10th grade multiple-choice test in Hanoi

|

Hanoi - Many candidates taking the 10th grade high school exam said that this year's exam is suitable, some students are confident of achieving high scores.

Zeon grass seen at the largest 500 billion VND stadium in the Northern mountainous region

Lam Thanh |

Thai Nguyen - Thai Nguyen Provincial Stadium has a total investment of more than 500 billion VND, a scale of 22,000 seats, using standard Zeon Zoysia grass variety.

Agree to repair and upgrade Ha Tinh Provincial Stadium

TRẦN TUẤN |

Ha Tinh - The Provincial People's Committee has just agreed in principle to repair and upgrade the provincial stadium according to the proposal of the Department of Culture, Sports and Tourism.

Image of the deterioration of Dong Kinh Stadium before Lang Son spent 500 billion VND to build a new one

Khánh Linh |

Lang Son - Dong Kinh Stadium is seriously degraded, the new Sports Complex is about to be implemented.