Accelerating the Construction of the Fishing Port Project Behind Schedule for Many Years

TRẦN TUẤN |

After many years of slow implementation, the Investment Project for the expansion of the Fish Port of Thạch Kim (Lộc Hà, Hà Tĩnh Province) is currently being accelerated by the contractor.

Date 10.8, a reporter from Lao Động Newspaper was present at the construction site of the Thạch Kim Port Expansion Project (Thạch Kim Commune, Lộc Hà District) to record many officials, workers, and machinery concentrated on the construction site.

Although the weather was extremely hot, workers were still working hard until nearly noon.

“We must focus on working to accelerate the progress as per the instructions because the rainy season will make it very difficult to work”, a worker shared.

The Thạch Kim Port Expansion Project, with an investment of 60 billion VND, was inaugurated on May 15, 2024, and is being implemented by two contractors, Company No. 3 of Hà Tĩnh and Vietnam Construction Corporation - Joint Stock Company.

As Lao Động reported, on May 1, 2019, the Prime Minister issued Decision No. 476, assigning the People's Committees of Hà Tĩnh, Quảng Bình, Quảng Trị, and Thừa Thiên Huế to direct the implementation of the investment of the projects "Construction and upgrading of service infrastructure for the fishing industry" and the project "Restoration and regeneration of aquatic ecosystems and aquatic resources", using the compensation money for the environmental pollution of Hà Tĩnh Formosa Steel Corporation.

Implementing the above decision, Hà Tĩnh Province has launched 4 projects, including: The Thạch Kim Port Expansion Project; The project to invest in the construction of service infrastructure for the fishing industry at the Cửa Khẩu Anchorage in Kỳ Hà Commune; The project to dredge and renovate the channel and entrance to the Cửa Hội - Xuân Phổ Anchorage; and The Cửa Nhượng Port Project in Cẩm Nhượng Commune.

However, the above-mentioned projects have been delayed, and the Prime Minister has subsequently extended the deadline.

Up to now, Hà Tĩnh Province has only completed the project to invest in the construction of service infrastructure for the fishing industry at the Cửa Khẩu Anchorage in Kỳ Hà Commune, which was put into operation in June 2023.

The Cửa Nhượng Port Project, with a total investment of 280 billion VND, was inaugurated on January 20, 2024, and has achieved approximately 70% of the construction work.

The Thạch Kim Port Expansion Project, with a total investment of 60 billion VND, is currently focusing on accelerating the progress.

The project to dredge and renovate the channel and entrance to the Cửa Hội - Xuân Phổ Anchorage, with a total investment of 20 billion VND, has not yet been implemented as it is still requesting an increase in the source of funds.

Some images of the concentrated construction of the Thạch Kim Port Expansion Project:

The Thạch Kim Port Expansion Project is accelerating construction. Photo: Trần Tuấn.
The Thạch Kim Port Expansion Project is accelerating construction. Photo: Trần Tuấn.
Taking advantage of favorable weather to work if not in the rainy season, it will be difficult to work. Photo: Trần Tuấn.
Taking advantage of favorable weather to work if not in the rainy season, it will be difficult to work. Photo: Trần Tuấn.
The project's fence has been completed. Photo: Trần Tuấn.
The project's fence has been completed. Photo: Trần Tuấn.
The excavator is concentrating on construction. Photo: Trần Tuấn.
The excavator is concentrating on construction. Photo: Trần Tuấn.
The construction of the port will be difficult during the rainy season. Photo: Trần Tuấn.
The construction of the port will be difficult during the rainy season. Photo: Trần Tuấn.
According to the schedule, the project must be completed by the end of 2024. Photo: Trần Tuấn.
According to the schedule, the project must be completed by the end of 2024. Photo: Trần Tuấn.

TRẦN TUẤN
TIN LIÊN QUAN

Chạy đua tiến độ tại dự án cảng cá 280 tỉ đồng ở Hà Tĩnh

TRẦN TUẤN |

Hà Tĩnh - Tranh thủ thời tiết thuận lợi, nhà thầu đang chạy đua tiến độ thi công Dự án cảng cá Cửa Nhượng với tổng vốn đầu tư 280 tỉ đồng.

Dự án nâng cấp cảng cá 460 tỉ đồng ở Quảng Ngãi đình trệ vì vướng mặt bằng

VIÊN NGUYỄN |

Vướng mặt bằng khiến dự án Nâng cấp, mở rộng khu neo đậu tránh trú bão kết hợp cảng cá Tịnh Hòa, TP Quảng Ngãi giậm chân tại chỗ.

Hối hả thi công Dự án cảng cá từ nguồn bồi thường của Formosa Hà Tĩnh

TRẦN TUẤN |

Hà Tĩnh - Sau nhiều năm chậm triển khai, Dự án đầu tư xây dựng mở rộng Cảng cá Thạch Kim (huyện Lộc Hà) đang được tập trung thi công để kịp hoàn thành theo tiến độ giao vào cuối năm 2024 này.

Nợ chế độ giáo viên Bình Định: Trách nhiệm "chảy" về trường

Hoài Phương |

Bình Định - Về việc giáo viên huyện miền núi Vân Canh bị nợ lương, chế độ kéo dài, các cơ quan, đơn vị liên quan đều cho rằng trách nhiệm chính thuộc về trường.

Chơi dưới chung cư, bé gái bị vật cứng rơi trúng, lõm sọ não

Hoàng Xuyến - Việt Anh |

Mới đây, tại một chung cư trên địa bàn Hà Nội xảy ra trường hợp bé gái bị một vật cứng như bát, đĩa sứ rơi trúng vào đầu, gây lõm sọ não.

Kỷ luật nguyên Thứ trưởng Bộ Tài chính Vũ Thị Mai

PHẠM ĐÔNG |

Bà Vũ Thị Mai - nguyên Thứ trưởng Bộ Tài chính - bị kỷ luật bằng hình thức Khiển trách do đã có những vi phạm, khuyết điểm trong công tác.

Trực tiếp bóng chuyền U23 VTV Bình Điền Long An 0-0 U23 Thái Nguyên: Set 1

Nhóm PV |

Trận đấu giữa đội VTV Bình Điền Long An và Thái Nguyên tại chung kết giải bóng chuyền U23 Quốc gia, diễn ra lúc 18h00 hôm nay (19.9).

Lý do hàng loạt "ông lớn" xin giảm nhập xăng dầu

Anh Tuấn |

Một số thương nhân đầu mối kinh doanh xăng dầu đề xuất điều chỉnh giảm mức tổng nguồn được phân giao cho cả năm 2024 do bị lỗ những tháng gần đây.