Inspectorate of the 291 billion VND project started construction and then left it there in Quang Nam

Hoàng Bin |

The Chairman of the People's Committee of Quang Nam province has directed a comprehensive inspection of the Loc Dai Reservoir project worth more than 291 billion VND.

Key project, in disarray after 6 years of construction

The Loc Dai Reservoir Project (in Que Son District) started construction in 2018 with a total investment of more than 291 billion VND, expected to provide irrigation water for 500 hectares of agricultural land, contributing to reducing flooding in downstream areas.

Initially, the project was expected to be completed in 2020, but due to delays, the People's Committee of Quang Nam province extended the progress to the end of 2025.

Ho chua nuoc Loc Dai la cong trinh trong diem trong Chuong trinh muc tieu ung pho voi bien doi khi haudu kien hoan thanh sau 2 nam, nay da 6 nam van ngon ngang. Anh: Nguyen Hoang
Loc Dai reservoir in Quang Nam worth over VND291 billion is still in disarray after 6 years. Photo: Nguyen Hoang

Previously, during the project implementation, Quang Nam province granted a license to Quang Nam Agricultural and Forestry Development Investment Company Limited to exploit crushed stone and fill soil in the project area. Meanwhile, the construction of the reservoir is still "stuck at the site", due to land clearance problems and lack of fill soil.

Current status of the project instead of a reservoir for agricultural production, there is only mineral exploitation at the construction site.

On March 24, the Office of the Quang Nam Provincial People's Committee said that the Chairman of the Provincial People's Committee had requested the Provincial Inspectorate to intervene and clarify compliance with legal regulations on land, environment, investment and construction at the project. At the same time, the province also requested to determine the responsibilities of each relevant collective and individual and propose handling measures.

Hoat dong khai thac khoang san trong long du an ho thuy loi Loc Dai. Anh: Nguyen Hoang
Mineral exploitation activities in the inner of Loc Dai irrigation lake project. Photo: Nguyen Hoang

In addition, the Provincial People's Committee assigned the Provincial Construction Investment Project Management Board to review all legal documents, investment scale, implementation progress, disbursement capital... to report and propose adjustments to the investment policy. The People's Committee of Que Son district is also required to speed up compensation and site clearance to hand over the remaining area to the investor.

Slow progress, paying more than 36 billion VND in central capital

Notably, the sluggish site clearance of this project has made it impossible for Quang Nam province to carry out construction, leading to the return of more than VND 36.5 billion from the central budget due to failure to disburse on time.

The Chairman of the People's Committee of Quang Nam province has also requested the People's Committee of Que Son district to review the collective and individual responsibilities related to this delay. At the same time, the Provincial Construction Investment Project Management Board must also organize a review of responsibilities for individuals and project management units.

According to local people, previously at the location where the reservoir was being built, people blocked the stream to bring water to serve 50 hectares of rice, but the old ditch was affected by the construction project, so there was a lot of erosion, unable to bring water to the fields. The fact that the soil here is barren makes farming in the dry season very difficult.

Muc tieu du an ban dau la xay ho chua nuoc de cap nuoc cho dan nhung bay gio lai lam thieu nuoc tram trong hon khien nguoi dan dia phuong buc xuc. Anh: Nguyen Hoang
The project's initial goal was to build a reservoir to supply water to the people, but now the water shortage is getting worse, making the local people angry. Photo: Nguyen Hoang

The Loc Dai Reservoir Project is considered a key project of Quang Nam, playing an important role in developing sustainable agriculture and preventing natural disasters. However, without a drastic solution, this project is at risk of becoming a long-term "suspended" project, causing waste of the state budget and affecting people's lives.

Not only the delay, the Loc Dai lake project was also involved in a scandal when at the end of 2022, the state Audit requested Quang Nam province to recover and pay the state budget more than 927 million VND and reduce the payment acceptance of more than 533 million VND for the project.

The reason pointed out by the State Audit is that the investor has conducted acceptance and payment to determine incorrect costs for survey consulting, construction drawing design - estimate, and site clearance stake-ups.

Hoàng Bin
TIN LIÊN QUAN

Quang Nam has no more ferries thanks to 2 bridges worth nearly a thousand billion VND

|

Quang Nam officially inaugurated 2 key bridges with a total investment of nearly 1,000 billion VND.

Identifying the identities of 5 victims of the boat sinking in Quang Nam

|

The Quang Nam Border Guard Command has identified 1 fisherman who died and 4 fishermen who went missing due to a sunken boat at noon on March 21.

New developments in land dispute lawsuits in Quang Nam

|

Positive moves from the Quang Nam government and businesses have opened up prospects for resolving the largest land dispute in the Central region, causing nearly 1,000 customers to be spread.

Deadline for cutting 100% of unnecessary business conditions

|

In 2026, 100% of unnecessary or conflictive, overlapping business conditions or general regulations will be cut and simplified.

Urgently build a smoke barrier, equipped with adequate fire prevention and fighting before March 30

|

After March 30, the rental house that has not completed implementing fire prevention and fighting safety (PCCC) solutions will have to stop operating.

Proposal on documents after merging provinces and communes

|

It is expected that documents issued by competent authorities to individuals and organizations before the merger of provinces and communes will still be used if they have not expired.

In Hanoi, anyone who travels can have their alcohol concentration checked

|

Hanoi - Traffic police are strengthening control and handling of alcohol concentration violations, especially at key routes and areas.

VTV Binh Dien Long An maintains its winning streak in the National Championship

|

On the afternoon of March 26, VTV Binh Dien Long An defeated Vietinbank with a score of 3-1 at the 2025 National Volleyball Championship.

Quang Nam has no more ferries thanks to 2 bridges worth nearly a thousand billion VND

Hoàng Bin |

Quang Nam officially inaugurated 2 key bridges with a total investment of nearly 1,000 billion VND.

Identifying the identities of 5 victims of the boat sinking in Quang Nam

Hoàng Bin |

The Quang Nam Border Guard Command has identified 1 fisherman who died and 4 fishermen who went missing due to a sunken boat at noon on March 21.

New developments in land dispute lawsuits in Quang Nam

Nguyễn Hoàng |

Positive moves from the Quang Nam government and businesses have opened up prospects for resolving the largest land dispute in the Central region, causing nearly 1,000 customers to be spread.