On the morning of August 11, according to reporters of Lao Dong Newspaper, the Dong Nai bridge toll station on National Highway 1A (through Tran Bien ward, Long Hung district, Dong Nai city) has begun to dismantle in the direction from Dong Nai to Ho Chi Minh City.
Accordingly, the construction unit will dismantle toll stations T1, T2, T3 and T4, kiosks, and restore the road surface to complete the traffic safety system.

According to the schedule, the project will be completed in 90 days. However, according to Road Management Office IV. 2 (Road Management Zone IV, Vietnam Road Administration), during the construction of toll station dismantling, the contractor will increase manpower, machinery, and equipment to speed up progress, striving to complete the dismantling and restoration of the road surface before September 2.
After that, continue to complete work such as drawing road paint lines, installing signs...
In addition, during the dismantling process, ensure a minimum of 4 lanes of traffic (3 car lanes, 1 lane for 2-3 wheels).
Images of the demolition of Dong Nai bridge toll station on August 11:





Dong Nai bridge toll station is located on National Highway 1A in Tran Bien and Long Hung wards, Dong Nai city, serving the project to invest in the construction of the new Dong Nai bridge and the two ends of the bridge in the form of a BOT contract.
After many years, the Dong Nai bridge toll station temporarily stopped collecting tolls at 1:30 PM on August 24, 2020, and it has been nearly 6 years now. The project was established for all-people ownership by the Ministry of Transport (now the Ministry of Construction) on December 29, 2023.