More underpasses and overpasses to be opened to traffic at the largest intersection in Ho Chi Minh City

MINH QUÂN |

Ho Chi Minh City - An Phu intersection is about to complete HC1-02 underpass connecting the Ho Chi Minh City - Long Thanh expressway with Mai Chi Tho and overpass N3 connecting the Mai Chi Tho - Dong Van Cong axis.

Recorded on January 5, at the An Phu intersection construction site, dozens of workers and machinery are urgently constructing the closed tunnel sections of the HC1-02 underpass.

This underpass is 760 m long, including 4 two-way lanes, directly connecting the Ho Chi Minh City - Long Thanh - Dau Giay expressway with Mai Chi Tho street in the direction of the Saigon River tunnel. The total private investment for underpass HC1-02 is more than 340 billion VND.

To date, the HC1-02 underpass has completed about 90% of the volume and is expected to be opened to traffic before January 15, 2026.

Thi cong ham chui HC1-02. Anh: Anh Tu
Construction of HC1-02. underpass. Photo: Anh Tu
Toan canh ham chui, cau vuot tai nut giao An Phu.  Anh: Anh Tu
Overview of the underpass and overpass at An Phu intersection. Photo: Anh Tu

Previously, underpass HC1-01 at the Mai Chi Tho - Dong Van Cong intersection was put into operation from the end of June 2025.

When both underpasses are open to traffic, vehicles from the highway can turn left smoothly towards Mai Chi Tho street, towards the Saigon River tunnel, instead of having to wait for the traffic lights as before.

Ham chui HC1-02 se noi lien voi ham chui HC1-01 da thong xe truoc do.  Anh: Anh Tu
The HC1-02 underpass will connect with the HC1-01 underpass that was previously opened to traffic. Photo: Anh Tu
Phoi canh ham chui HC1-02 khi hoan thanh.  Anh: Ban Giao thong TPHCM
Perspective of HC1-02 underpass when completed. Photo: Ho Chi Minh City Traffic Management Board

A few dozen meters from the underpass, the branch of overpass N3 (from Mai Chi Tho turning left to Dong Van Cong) is also gradually forming, expected to be opened to traffic in the first quarter of 2026.

Cau vuot N3 - tu Mai Chi Tho re trai di Dong Van Cong.  Anh: Anh Tu
N3 overpass - turn left from Mai Chi Tho to Dong Van Cong. Photo: Anh Tu

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Management Board - investor), An Phu intersection often experiences congestion in 5 main directions, including: Traffic flow from the Ho Chi Minh City - Long Thanh - Dau Giay expressway to the intersection; direction from Dong Van Cong street going straight up Mai Chi Tho; traffic flow from Luong Dinh Cua street crossing the intersection to the expressway; branches from Nguyen Thi Dinh street and parallel roads entering the intersection; Mai Chi Tho - Dong Van Cong intersection area.

Thong xe nhanh cau N2 nut giao An Phu. Anh: Anh Tu
Branch N2 of An Phu intersection bridge opens to traffic at the end of 2025. Photo: Anh Tu

Previously, the project had completed the HC1-01 underpass and the N2 bridge branch (turning right from the expressway to Mai Chi Tho street).

In the first quarter of 2026, the commissioning of the HC1-02 underpass and the N3 bridge branch is expected to help reduce congestion by about 80% in the An Phu intersection area.

At the same time, the Traffic Management Board is directing contractors to accelerate the construction progress of bridge branch N4 (from Dong Van Cong turning right to Mai Chi Tho) and bridges N1.1, N1.3 (turning left from Mai Chi Tho to Ho Chi Minh City - Long Thanh - Dau Giay expressway).

These items are expected to be opened to traffic before June 30, 2026, thereby fundamentally solving the congestion situation at An Phu intersection.

To ensure the overall progress, the Traffic Management Board requests construction units to increase shifts, mobilize more manpower and equipment, and resolutely handle contractors who are slow or violate contracts.

Cau N3 Anh: Anh Tu
Bridge N3 from Mai Chi Tho turning left to Dong Van Cong will be opened to traffic in the first quarter of 2026. Photo: Anh Tu

An Phu intersection is a key traffic project at the eastern gateway of Ho Chi Minh City, started at the end of 2022, with a total investment of more than 3,400 billion VND.

According to Decision No. 869/QD-UBND dated March 28, 2022, the project is implemented in the period 2021 - 2025. However, due to project delays, the Ho Chi Minh City People's Committee has allowed adjusting the implementation time to the second quarter of 2026.

According to the Traffic Management Board, the An Phu intersection project plays a strategic role as a direct connecting point between Mai Chi Tho street and the Ho Chi Minh City - Long Thanh - Dau Giay expressway, and is also an important gateway to the East of the city.

The completion of the entire project in 2026 not only helps traffic in the area become more smooth, but also creates a foundation for a sharp increase in vehicle volume when the expressway is completed and expanded at the end of 2026 and Long Thanh International Airport officially operates from mid-2026.

MINH QUÂN
RELATED NEWS

Opening of the N2 overpass branch at An Phu intersection on the last night of the year

|

Ho Chi Minh City - Branch N2 overpass belonging to the An Phu traffic junction construction project (Ho Chi Minh City) officially opened to traffic on the evening of December 31st.

The largest intersection in Ho Chi Minh City has postponed completion until the second quarter of 2026

|

HCMC - An Phu intersection has postponed the completion of the completion date to the second quarter of 2026, with the underpass and a branch of the bridge to be completed before the Lunar New Year 2026.

The An Phu intersection must be completed immediately, it is already too congested!

|

After the press's reflection on the delay of the An Phu intersection project (HCMC), in mid-November, the construction site became bustling again.

Home loan interest rates increase sharply, buyers worried

|

Interest rates on home loans after the preferential period expires increase sharply, causing borrowers to bear great financial pressure.

U23 Asian Championship 2026 standings: U23 Vietnam leads Group A

|

Updated rankings of Group A of the 2026 AFC U23 Championship finals, in which U23 Vietnam is leading.

Venezuela transfers 113 tons of gold to Switzerland under Maduro

|

Venezuela has transferred a huge amount of gold worth 5.2 billion USD to Switzerland under President Nicolas Maduro.

Preventing recurrence of landslides on National Highway 49

|

HUE - Functional agencies are building a system of stone jars to reinforce the negative taluy along National Highway 49, in order to prevent landslides from recurring and ensure traffic safety.

Binh Ngo Tet bonus 2026 in Lam Dong highest 180 million VND

|

Lam Dong - A business offers Tet Nguyen Dan Binh Ngo 2026 bonuses to employees at the highest level of up to 180 million VND/person.

Opening of the N2 overpass branch at An Phu intersection on the last night of the year

Tâm Tú |

Ho Chi Minh City - Branch N2 overpass belonging to the An Phu traffic junction construction project (Ho Chi Minh City) officially opened to traffic on the evening of December 31st.

The largest intersection in Ho Chi Minh City has postponed completion until the second quarter of 2026

MINH QUÂN |

HCMC - An Phu intersection has postponed the completion of the completion date to the second quarter of 2026, with the underpass and a branch of the bridge to be completed before the Lunar New Year 2026.