Construction throughout Tet brings Bien Hoa - Vung Tau expressway project to completion soon

HÀ ANH CHIẾN |

Dong Nai - Component project 1 of the Bien Hoa - Vung Tau expressway, dozens of officials, engineers, and workers are constructing throughout Tet.

Maintain construction throughout Tet to catch up with work immediately after the holiday

On February 17, representatives of the Dong Nai Provincial Construction Investment Project Management Board said that Construction Corporation No. 1 - JSC (CC1) is accelerating the construction pace throughout Tet at component project 1 of the Bien Hoa - Vung Tau expressway, determined to bring the project to completion soon.

Mr. Bui Ngoc Lam - Project Director of CC1 - said: To speed up the progress and construction momentum of component project 1 of the Bien Hoa - Vung Tau expressway, we have planned to maintain operations throughout Tet. The construction site operates continuously from December 27th to the end of January 7th (including peak days such as the 29th and the 1st day of Tet).

Nhiều máy móc thiết bị được duy trì, đẩy nhanh nhịp độ thi công đưa dự án sớm về đích. Ảnh: HAC
Many machinery and equipment are maintained, accelerating the construction pace to bring the project to completion soon. Photo: HAC

Regarding the technical plan, the contractor simultaneously deployed 3 main construction teams including: No. 1: Focusing on completing the items of railings and heat joints in the Quan Thu Bridge area; No. 2: Construction of expansion joints, continuous heat joints and median strips at Bridge 769; No. 3: Construction of the road section processing the foundation, focusing on compacting the K98 top soil layer and spreading crushed stone grade.

Regarding management personnel, the Executive Board of CC1 arranges 24/7 on-duty forces including: 1 Project Director, 1 Commander and 2 Technical staff to closely supervise the quality of the project.

Regarding construction capacity, the contractor mobilized 16 units of machinery and equipment and a standing workforce of 22 to 25 people. All preparations have been completed to ensure smooth operation of the machinery throughout the holiday.

Also according to Mr. Lam, the main goal of the unit is to proactively accelerate progress beyond the plan. More importantly, maintaining the working pace throughout Tet aims to create positive momentum, helping the construction site immediately catch up and return to normal construction immediately after the holiday ends, avoiding sluggishness after Tet.

Caring for workers constructing throughout Tet

Understanding the silent sacrifice of engineers and workers when they have to be away from their families, the Board of Directors and the Executive Board have had special policies to encourage and support both materially and spiritually. We are committed to ensuring that all forces stick to the construction site of Component Project 1 both complete their tasks well and have a warm and complete Tet right at work," Mr. Lam added.

Lãnh đạo UBND tỉnh Đồng Nai thăm, chúc Tết, động viên cán bộ, kỹ sư, công nhân đang thi công xuyên Tết tại công trường Dự án thành phần 1 cao tốc Biên Hòa - Vũng Tàu. Ảnh: HAC
Leaders of Dong Nai Provincial People's Committee visit, wish Tet, and encourage officials, engineers, and workers who are working during Tet at the construction site of component project 1 of the Bien Hoa - Vung Tau expressway. Photo: HAC

Previously, on the afternoon of February 16, leaders of Dong Nai Provincial People's Committee visited, wished Tet, and encouraged the team of officials, engineers, and workers who are working during Tet at the construction site of component project 1 of the Bien Hoa - Vung Tau expressway. At the construction site, Chairman of the Provincial People's Committee Nguyen Van Ut acknowledged the responsible working spirit of the construction force during the Tet holidays, and emphasized the important significance of the Bien Hoa - Vung Tau Expressway Project in regional linkage and promoting the province's socio-economy.

For the construction contractor unit, the Chairman of the Provincial People's Committee requested to pay attention to caring for the material and spiritual lives of workers, ensuring Tet working regime for workers...

Một gói thầu tại dự án thành phần 1, cao tốc Biên Hòa - Vũng Tàu. Ảnh: HAC
A bidding package at component project 1, Bien Hoa - Vung Tau expressway. Photo: HAC

The Bien Hoa - Vung Tau expressway project is a key project with a total length of nearly 54 km, passing through Dong Nai province and Ho Chi Minh City. In which, the section through Dong Nai province is more than 34 km long, and the section through Ho Chi Minh City is more than 19 km long.

When completed and put into operation, the project will contribute to reducing congestion on National Highway 51, while completing the transportation network of the Southern region, creating more favorable connection conditions between Dong Nai and Ho Chi Minh City. In particular, this expressway also plays an important role in effectively supporting the operation of Long Thanh airport in the coming time.

HÀ ANH CHIẾN
RELATED NEWS

Construction throughout Tet at the bridge construction site connecting Hanoi with Hung Yen

|

Ngoc Hoi bridge across the Red River connecting Hanoi with Hung Yen is being constructed throughout the Lunar New Year, ensuring project progress.

Mentioning 2 projects under construction throughout Tet, Ho Chi Minh City Department of Construction issues urgent document

|

Ho Chi Minh City requests that ring road, expressway, and bridge and road projects follow the example of Ring Road 3 and Rach Xuyen Tam, organize construction throughout Tet, and not interrupt progress.

Bridge on Ring Road 4 receives sufficient land, construction throughout the New Year

|

Hanoi - Leaving the New Year holiday, many engineers and workers stick to the construction site, accelerating the progress of Hong Ha bridge belonging to the Ring Road 4 project in the Capital region.

Villages in the core area of Phong Nha - Ke Bang welcome the first Tet in bright electric lights

|

Quang Tri - Lunar New Year 2026, Rao Con village in the core area of Phong Nha - Ke Bang brightens up the national power grid, opening a new step for people's lives.

Spring on the continental shelf, steadfast steel fortresses DK1

|

Naval Region 2 - In the middle of the ocean on the southern continental shelf, officers and soldiers of DK1 platform welcome Spring in combat readiness, keeping the peace of the mainland.

People ask for fire to pray for good luck when a dragon catches fire on New Year's Eve

|

Thanh Hoa - Every year, on New Year's Eve, people in Dong Bong village, Tong Son commune gather at the village communal house to participate in the fire procession ritual and ask for New Year's fortune.

New Year's Eve in the sky - Reunion when touching the ground

|

Welcoming New Year's Eve in the sky, touching the ground in the first moments of the new year, the special flight becomes a reunion journey with many passengers.

When civil servants serve in the digital space: The transformation from thinking to action

|

The implementation of administrative procedures in the digital space has helped Ho Chi Minh City residents save time, while effectively eliminating unofficial costs, creating a transparent and modern administration. There, the concept of "civil servants" is no longer associated with paperwork, but becomes dedicated "servants" on the data flow.

Construction throughout Tet at the bridge construction site connecting Hanoi with Hung Yen

SÓNG HỮU |

Ngoc Hoi bridge across the Red River connecting Hanoi with Hung Yen is being constructed throughout the Lunar New Year, ensuring project progress.

Mentioning 2 projects under construction throughout Tet, Ho Chi Minh City Department of Construction issues urgent document

MINH QUÂN |

Ho Chi Minh City requests that ring road, expressway, and bridge and road projects follow the example of Ring Road 3 and Rach Xuyen Tam, organize construction throughout Tet, and not interrupt progress.

Bridge on Ring Road 4 receives sufficient land, construction throughout the New Year

SÓNG HỮU |

Hanoi - Leaving the New Year holiday, many engineers and workers stick to the construction site, accelerating the progress of Hong Ha bridge belonging to the Ring Road 4 project in the Capital region.