New information on the progress of the elevated section of metro Nhon - Hanoi station

Tô Thế |

Hanoi - On July 31, relevant parties are completing final procedures to put the elevated section of the Nhon - Hanoi station metro project into operation.

At noon on July 31, information from the Hanoi Urban Railway Project Management Board (MRB) said that the same morning, the unit worked with the State Inspection Council on the acceptance of construction works to see Review and approve the results of acceptance of completed works. MRB will continue its efforts to ensure that every final step is completed safely, efficiently, and in accordance with regulations.

Previously, on July 30, the elevated section of the Hanoi City Pilot Urban Railway Project, the Nhon - Hanoi Station section (Nhon - Hanoi Station) was officially granted a system safety certificate, Certification confirming that the urban railway line is designed and built in accordance with safety management standards and meets safe operating conditions.

Vietnam Railways Administration - Ministry of Transport issued the Certificate of appraisal of urban railway system safety records (ATHT) No. 356/2024/GCN-CĐSVN dated July 30, 2024.

A road safety certificate is a mandatory requirement, a prerequisite for putting an urban railway project into commercial operation.

The Nhon - Hanoi station metro project is completing the final procedures to put the elevated section into operation. Photo: To The
The Nhon - Hanoi station metro project is completing the final procedures to put the elevated section into operation. Photo: To The

On July 29, the Ministry of Natural Resources and Environment also issued Environmental License No. 276/GPMT-BTNMT to MRB (Investor) and Hanoi Railway Company Limited (Operator) to carry out the following activities: Environmental protection activities of the elevated section of the Project "Hanoi City Pilot Urban Railway, Nhon - Hanoi Station section" in districts: Nam Tu Liem, Bac Tu Liem, Cau Giay, Dong Da and Ba Dinh, Hanoi city.

The project has the same criteria as group A projects (classified according to criteria prescribed by the law on public investment) and has environmental criteria like group I projects according to the provisions of the Law on Environmental Protection. The term of the License is 7 years.

Achieving the Environmental Permit and System Safety Certification is an important milestone, marking the completion of the highest technical requirements and safety standards during the construction and operation of the urban railway. Pilot urban area of ​​Hanoi city, section Nhon - Hanoi station.

This is considered a big step towards officially putting the elevated section of the route into commercial operation.

MRB will soon announce the time of official commercial operation of the elevated section of the Nhon - Hanoi station metro project.

On July 30, Hanoi Urban Railway Management Board (MRB) together with consultants and contractors started tunnel drilling with a TBM (Tunnel Boring Machine) for the underground section of the urban railway project. pilot in Hanoi city, section Nhon - Hanoi station.

The groundbreaking was held at the bottom floor of terminal S9 - Kim Ma.

Tô Thế
TIN LIÊN QUAN

Cận cảnh máy đào hầm metro Nhổn - ga Hà Nội dưới lòng đất

Tô Thế |

Hà Nội - Bộ đôi máy đào hầm của tuyến metro Nhổn - ga Hà Nội có chiều dài hơn 100m, nặng khoảng 850 tấn, tốc độ tiêu chuẩn khoảng 10m/ngày.

"Quái vật" đào hầm metro Nhổn - ga Hà Nội được "đánh thức"

Tô Thế |

Hà Nội - Bộ đôi máy đào TBM của dự án metro Nhổn - ga Hà Nội đã được khởi động vào sáng nay (30.7).

Vỏ hầm metro Nhổn - ga Hà Nội nặng 4 tấn/vòng

Tô Thế |

Với chiều dài đường hầm hơn 4km, metro Nhổn - ga Hà Nội cần 3.488 vòng vỏ hầm. Mỗi vỏ hầm nặng 4 tấn.

Người bạn từ Mỹ muốn giúp Trương Mỹ Lan khắc phục thiệt hại

Tâm Tú |

TPHCM - Trong phiên tòa, theo lời luật sư thì một người bạn của Trương Mỹ Lan tại Mỹ có nhã ý sẽ đứng ra trả nợ cho bị cáo.

Những thương vụ M&A nghìn tỉ của KIDO Group

Lục Giang |

Nutifood mua lại 51% vốn của KIDO Group, đem lại cho KIDO hàng nghìn tỉ đồng. Ở chiều ngược lại, KIDO cũng chi hàng nghìn tỉ để chi phối nhiều thương hiệu lớn.

Bắt Chánh Văn phòng Sở Tài nguyên và Môi trường Lâm Đồng

HOÀI THANH |

Chánh Văn phòng Sở Tài Nguyên và Môi trường tỉnh Lâm Đồng bị bắt giữ để điều tra về việc bị tố nhận 1 tỉ đồng của người dân.

Ủng hộ trên 100.000 đồng được nhận giấy khen, dưới chỉ nhận thư khen

Chân Phúc |

TPHCM - Học sinh ủng hộ trên 100.000 đồng thì nhận được giấy khen còn ủng hộ dưới 100.000 đồng thì chỉ được nhận thư khen.

Bắt khẩn cấp TBT Tạp chí Môi trường và Đô thị cùng một số phóng viên

NHÓM PV |

Cơ quan Cảnh sát điều tra - Công an tỉnh Thái Bình phối hợp với các đơn vị nghiệp vụ Bộ Công an vừa phá thành công chuyên án, bắt giữ khẩn cấp Tổng Biên tập Tạp chí Môi trường và Đô thị Việt Nam cùng một số phóng viên, cán bộ về tội cưỡng đoạt tài sản.

Close-up of the Nhon - Hanoi Station metro tunnel boring machine underground

Tô Thế |

Hanoi - The pair of tunnel boring machines for the metro line Nhổn - Hanoi Station are over 100m long, weigh about 850 tons, and have a standard speed of about 10m/day.

Monster tunnel boring machine for Nhon - Hanoi station metro project "awakened"

Tô Thế |

Hanoi - The TBM duo of the metro project Nhổn - Hanoi Station was launched this morning (July 30).

Nhon metro tunnel shell - Hanoi station weighs 4 tons/round

Tô Thế |

With a tunnel length of more than 4km, metro Nhon - Hanoi station needs 3,488 tunnel shells. Each tunnel shell weighs 4 tons.