Technical traffic opening of the more than 1,100 billion VND route connecting Long An with Ho Chi Minh City

Duy Minh |

Long An - On April 19, the Provincial People's Committee organized the opening of provincial road 823D. This is a key transport project connecting Long An with Ho Chi Minh City and neighboring provinces.

Provincial Road 823D has a total length of more than 14km, starting from Duc Hoa District (Long An Province) to Ho Chi Minh City, ending at Hau Nghia roundabout intersection, Duc Hoa District. This is a completely new traffic axis in the Northwest direction, expected to create a breakthrough in regional linkage and socio-economic development of the region.

The project started on December 26, 2021, with the Long An Provincial Investment and Construction Project Management Board as the investor. Currently, the road surface has been completed, and auxiliary items such as sidewalks, trees, lighting systems, and traffic safety are under construction. It is expected that the entire project will be completed and put into operation in December 2025.

Quang canh buoi le thong xe ky thuat tuyen duong tinh 823D. Anh: Duy Minh
Scene of the technical opening ceremony of provincial road 823D. Photo: Duy Minh

Speaking at the ceremony, Mr. Nguyen Van Hung - Director of the Project Management Board - said: Route 823D plays a strategic role, connecting a series of key traffic routes such as Ho Chi Minh Road, National Highway N2, Ring Roads 2, 3, 4 of Ho Chi Minh City, creating favorable conditions for connecting the Eastern, Western provinces and Ho Chi Minh City.

The route still passes through many industrial and urban development areas with great potential but has not yet invested in infrastructure. The construction of route 823D not only contributes to completing the regional transportation system but also opens up great opportunities in industrial and urban development, creating a clean land fund, strongly attracting investors to Long An.

Duong tinh 823D ket noi Long An voi TPHCM chinh thuc thong xe ky thuat. Anh: Duy Minh
Provincial Road 823D connecting Long An with Ho Chi Minh City has officially opened to technical traffic. Photo: Duy Minh

The total investment for the road construction is more than 1,106 billion VND, of which the central budget supports 1,000 billion VND, the rest is from the provincial budget and other legally mobilized capital sources.

In particular, compensation, support and resettlement work was assigned to Duc Hoa District People's Committee as the investor, with a total capital of more than VND 3,745 billion from the provincial budget, district budget and other legal sources.

Duy Minh
TIN LIÊN QUAN

5 key projects in Long An will start, groundbreaking, inauguration on April 19

|

Long An - On April 19, he will start, inaugurated and groundbreaked at the same time 5 key projects to celebrate the 50th anniversary of the liberation of the South.

Long An restartes HCMC connecting road project

|

Long An - After a period of suspension, the project to upgrade and renovate Provincial Road 830C connecting to Ho Chi Minh City has been restarted with a total investment of nearly double.

Long An proposes to support more than VND 5,400 billion to build DT.827E road

|

Long An - The province proposed that the central government support more than VND 5,400 billion to invest in the construction of DT.827E road connecting from Ho Chi Minh City to Tien Giang.

Big fire at night in Ba Vi National Park

|

Hanoi - A large fire suddenly broke out in the Chang Re mountain area - Ba Vi National Park.

Binh Thuan celebrates 50 years of construction, innovation and development

|

Binh Thuan - On the evening of April 19, in Phan Thiet city, Binh Thuan province held a ceremony to celebrate the 50th anniversary of the Liberation of the province.

For the first time, Con Dao has a sea turtle conservation tour worth more than 20 million VND

|

Ba Ria - Vung Tau - Tourists will experience eating, staying and doing work related to sea turtle rescue with the forest rangers in Con Dao.

Nghe An has 3,530 surplus cadres after administrative unit arrangement

|

Nghe An - The whole province will have a surplus of about 3,530 cadres and civil servants after the arrangement of commune-level administrative units.

Reasons for choosing Bac Giang City as the administrative center of Bac Ninh province after the merger

|

Bac Ninh - The project to reorganize Bac Ninh and Bac Giang provinces clearly states the reasons for choosing Bac Giang city as the administrative center after the merger.

5 key projects in Long An will start, groundbreaking, inauguration on April 19

Duy Minh |

Long An - On April 19, he will start, inaugurated and groundbreaked at the same time 5 key projects to celebrate the 50th anniversary of the liberation of the South.

Long An restartes HCMC connecting road project

Duy Minh |

Long An - After a period of suspension, the project to upgrade and renovate Provincial Road 830C connecting to Ho Chi Minh City has been restarted with a total investment of nearly double.

Long An proposes to support more than VND 5,400 billion to build DT.827E road

Duy Minh |

Long An - The province proposed that the central government support more than VND 5,400 billion to invest in the construction of DT.827E road connecting from Ho Chi Minh City to Tien Giang.