Accelerate the progress of handing over the construction site for the Cho Moi - Bac Kan expressway

Việt Bắc |

Thai Nguyen - According to the plan, the entire site of the Cho Moi - Bac Kan expressway will be handed over before June 15.

Started in March 2025, the Cho Moi - Bac Kan Expressway Project is nearly 29km long. The project has a total investment of more than 5,750 billion VND, designed with a scale of 4 lanes, speed of 80km/h.

The Cho Moi - Bac Kan expressway passes through Thanh Thinh, Thanh Mai communes and Bac Kan ward, Thai Nguyen province with a total of 1,624 households and organizations affected.

Công trường dự án cao tốc Chợ Mới - Bắc Kạn. Ảnh: Công Luận
Construction site of Cho Moi - Bac Kan expressway project. Photo: Cong Luan

PV recorded that after a long period of construction, a highway stretching across hills and mountains has gradually emerged.

At the large construction site, hundreds of workers and machinery and equipment are mobilized to implement the project. A large amount of excavated soil is transported from high positions to low-lying areas.

In addition to the roadbed item, bridges and culverts, and resettlement areas serving the project are also being synchronously constructed.

According to the construction unit, on the entire route, dozens of construction fronts are stretched to deploy the project. Currently, contractors have mobilized over 600 personnel, more than 400 machines and equipment, deploying 42 construction fronts. The realized value reaches over 21.8% of the contract.

Vận động bàn giao mặt bằng để triển khai cao tốc Chợ Mới - Bắc Kạn. Ảnh: Việt Bắc
Mobilizing land handover to deploy the Cho Moi - Bac Kan expressway. Photo: Cong Luan

Up to now, site clearance work in Bac Kan ward and Thanh Mai commune has been basically completed.

In Thanh Thinh commune, the locality with the largest length of the route passing through with about 12.5km, affecting 773 households in 12 villages.

As of May 12, 753 households have received compensation and support money; the area handed over to the investor reached more than 104ha.

For households still facing difficulties, Thanh Thinh Commune People's Committee is coordinating with the Branch of the Land Fund Development Center Region VI to continue propaganda and dialogue. At the same time, develop a temporary housing support plan for households that need to relocate.

For households that need to arrange temporary accommodation and relocate old houses, the locality will mobilize forces to support the dismantling, transportation of houses and leveling ground.

Một dải công trường vắt ngang đồi núi dần hình thành. Ảnh: Công Luận
A construction site stretching across hills and mountains gradually forms. Photo: Cong Luan

Regarding the project, Vice Chairman of Thai Nguyen Provincial People's Committee Nong Quang Nhat requested relevant departments, branches, and localities to continue to closely coordinate, focus on removing difficulties, and accelerate the progress of compensation, support, and resettlement.

Vice Chairman of Thai Nguyen Provincial People's Committee emphasized the need to strengthen propaganda, mobilization, and promptly resolve legitimate petitions of the people. Strive to complete the handover of the entire route before June 15 according to the plan.

When completed, the Cho Moi - Bac Kan expressway will contribute to synchronizing transport infrastructure, shortening travel time to northern Thai Nguyen localities. At the same time, expanding development space, attracting investment, and promoting local socio-economic development.

Việt Bắc
RELATED NEWS

5 strategic highways open up new development space for Dak Lak

|

Dak Lak - In the future, 5 strategic expressways expected to be implemented will open up new development space for the locality.

More than 2 years, the Van Ninh - Cam Lo expressway resettlement area still does not have clean water

|

Quang Tri - People in the Van Ninh - Cam Lo expressway resettlement area hope that the promise of the clean water supply project investor will be completed by May 30th.

Hanoi diverts traffic at La Thanh - Nguyen Chi Thanh intersection from May 18

|

Hanoi adjusts traffic organization at La Thanh - Nguyen Chi Thanh intersection from May 18 to serve the construction of overpasses under the Ring Road 1 project.

Retired life of "golden hour artist" Tu Oanh, People's Artist Bui Bai Binh

|

Stage and film artists such as People's Artist Bui Bai Binh, People's Artist Lan Huong, Tu Oanh... after retiring become sought-after, continuously participating in projects.

Energy transition, develop green transportation to promote sustainable growth

|

Energy saving, energy transition and green transportation development are important solutions to promote sustainable growth.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

5 strategic highways open up new development space for Dak Lak

BẢO TRUNG |

Dak Lak - In the future, 5 strategic expressways expected to be implemented will open up new development space for the locality.

More than 2 years, the Van Ninh - Cam Lo expressway resettlement area still does not have clean water

HƯNG THƠ |

Quang Tri - People in the Van Ninh - Cam Lo expressway resettlement area hope that the promise of the clean water supply project investor will be completed by May 30th.

Rò rỉ thông tin mở đường nối cao tốc, hàng trăm cây thông ở Lâm Đồng bị đầu độc

Hải Đường |

Lâm Đồng – Thông tin đề xuất mở đường kết nối cao tốc Bảo Lộc – Liên Khương bị rò rỉ, hàng trăm cây thông tại xã Nam Ban Lâm Hà bị đầu độc để lấn chiếm đất.