Urgent progress of the 600 billion VND flood prevention and control dike project along the Da River

Minh Nguyễn |

Phu Tho - The urgent project of flood prevention and control of Pheo - Che flooded area, in Ky Son ward with a total investment of nearly 600 billion VND is at risk of being behind schedule.

The Pheo - Che urgent flood prevention project has a total investment of more than 597 billion VND, invested by the Project Management Board of Agricultural Works of Hoa Binh province (old), now the Project Management Board of Hoa Binh area.

The project will renovate and upgrade the dike combined with a 15.8km long traffic road, from Pheo area (Ky Son ward) to Che area (Thinh Minh commune, bordering Hanoi). The goal is to ensure safety for flood prevention and control, flood control in the downstream area of the Da River, while connecting inter-regional traffic between Hoa Binh - Phu Tho - Hanoi.

In March 2024, the project started construction, and is scheduled to be completed by the end of 2025. However, up to now, the construction progress is sluggish.

According to Lao Dong Newspaper's reporter in late October, after days of prolonged rain due to the impact of the weather, the weather is now dry, and the project has resumed construction. At this time, the contractor is focusing on the construction of the final section of the project, in Nha hamlet, Thinh Minh commune.

According to Mr. Dinh Van Hoan, project technical officer of My Phong Company (construction unit), the enterprise mobilized dozens of machines and vehicles to gather at the project for implementation to speed up the progress. However, the current lack of land is the biggest bottleneck of the project.

According to the Hoa Binh Regional Project Management Board, by mid-October 2025, 4 main packages are being implemented, reaching about 30% of the contract volume.

Of which, Ngoi Mai Bridge has been completed; the first 6.2km dike is under construction, culverts, retaining walls, and concrete pouring of the road surface of more than 500m long; the downstream reinforcement of Ngoi Mai Bridge has reached 33%; Ngoi Tom Bridge is in the beam casting phase, preparing to demolish the old bridge.

The project has disbursed 141 billion VND, while the capital plan assigned to 2025 is 216 billion VND. The capital is still lacking more than 384 billion VND, causing many items, especially the remaining 9.6km section of the dike, to not be implemented.

Site clearance is a major bottleneck. The 6.2km section at the beginning of the route had to reclaim more than 17 hectares of land from 344 households, but only could pay 131 households, 12 households had not received money, and the remaining 3.8km of the route had no land.

In addition, on the route, there are many households with land use right certificates, many plots of land overlapping, disputed or of production forest origin, causing the counting and determination of land types to take a long time. Some power and telecommunications projects that have not been relocated have also affected their progress.

Pho Chu tich UBND tinh Phu Tho Dinh Cong Su kiem tra tien do thuc hien Du an cap bach de ngan lu chong ngap ung Pheo - Che. Anh: Hong Trung
Vice Chairman of Phu Tho Provincial People's Committee Dinh Cong Su inspected the progress of the Pheo - Che flood prevention and control dike project. Photo: Hong Trung

At the project progress inspection in mid-October, Vice Chairman of Phu Tho Provincial People's Committee Dinh Cong Su pointed out that the construction progress of the project is currently slower than planned.

The Vice Chairman of Phu Tho Provincial People's Committee requested the People's Committees of communes and wards to speed up the review of documents, procedures, and resettlement land plots for projects.

Investors need to implement projects on schedule, pay attention to the implementation process so as not to affect people; coordinate with relevant units to closely monitor the construction progress, while speeding up the implementation of compensation, support and resettlement.

Construction units arrange equipment, machinery, and human resources to focus on speeding up progress; continue to deploy ongoing work, overcome difficulties, and ensure the completion of projects.

Minh Nguyễn
RELATED NEWS

Hai Phong approves 2 resolutions related to Gia Binh International Airport Project

|

Hai Phong - The 16th City People's Council, term 2021 - 2026, has just passed 21 Resolutions at the 30th session (special session).

Phu Tho approves investment in a technology brick and pottery factory worth over 130 billion VND

|

Phu Tho - The Provincial People's Committee has just approved the investment policy for the high-tech bored brick and pottery factory project in Lac Thuy commune.

The hillside is cracked, people in the highlands of Phu Tho are worried about landslides

|

Phu Tho - Dozens of households in Thoi Ba hamlet, Muong Thang commune are worried that cracks will appear when living on the hillside, posing a serious risk of landslides.

Request not to re-elect Mr. Phan Tat Phuong as Chairman of the Commune People's Council

|

Gia Lai - The Provincial Party Committee's Organization Committee proposed not to recommend Mr. Phuong to be re-elected as Chairman of the Commune People's Council after he was suspected of skipping a training class to play pickleball.

Investor says reason why National Highway 19 is damaged before handover date

|

Gia Lai - National Highway 19 through An Khe Pass damaged before handover, investor explains the cause due to natural disaster impact and sudden increase in vehicle traffic.

Ministry of Public Security informs about ensuring security and order to serve the 14th Party Congress

|

On the morning of January 10, the Ministry of Public Security will organize a launching ceremony and drills of security and order assurance plans to serve the 14th Party Congress.

Stock market adjusts after strong rally

|

Strong selling pressure suddenly appeared, causing the stock market not to maintain an impressive streak of gains.

Central Mass Mobilization Associations continue to streamline their apparatus

|

Mass organizations continue to implement the arrangement of organizational structure at the central level in the direction of streamlining and operating effectively.

Hai Phong approves 2 resolutions related to Gia Binh International Airport Project

Mai Dung |

Hai Phong - The 16th City People's Council, term 2021 - 2026, has just passed 21 Resolutions at the 30th session (special session).

Phu Tho approves investment in a technology brick and pottery factory worth over 130 billion VND

Minh Nguyễn |

Phu Tho - The Provincial People's Committee has just approved the investment policy for the high-tech bored brick and pottery factory project in Lac Thuy commune.

The hillside is cracked, people in the highlands of Phu Tho are worried about landslides

Minh Nguyễn - Yên San |

Phu Tho - Dozens of households in Thoi Ba hamlet, Muong Thang commune are worried that cracks will appear when living on the hillside, posing a serious risk of landslides.