Metro Line 2 project progress after 7 months of infrastructure relocation

Anh Tú |

HCMC - Metro Line 2 project (Ben Thanh - Tham Luong) is speeding up site clearance and infrastructure relocation to prepare for construction to start next year.

According to Project Management Board 2 - Ho Chi Minh City Urban Railway Management Board, up to now, the districts have completed land acquisition procedures, reaching 100% (585/585 cases), with the site handover rate reaching 98.3% (575/585 cases) to serve the construction of Metro Line 2.

According to records, over the past few days, at the construction site of Metro Line 2 (Ben Thanh - Tham Luong), workers and machinery have been working continuously day and night to relocate technical infrastructure. From Tan Binh District to District 1, construction materials, sewer pipes, and construction equipment have been gathered on many sidewalks; many sections have been fenced off with corrugated iron and dug deep to relocate technical infrastructure at 10 station locations.

 Cong truong thi cong du an metro so 2 tai vong xoay Dan Chu. Ảnh: Anh Tu
Construction site for technical infrastructure relocation at Metro Line 2 project in the Democracy Roundabout area. Photo: Anh Tu

At stations S10 (Pham Van Bach, Tan Binh district), S8 (Nguyen Hong Dao), S4 (Hoa Hung), S5 (Le Thi Rieng), S6 (Pham Van Hai), construction work is taking place urgently, ensuring progress thanks to the completed site and uncomplicated technical infrastructure.

At the S2 station area (Tao Dan), the construction encountered many difficulties such as the complex technical infrastructure system with many overlapping water supply and drainage pipes, power lines and telecommunications. At the S9 station (Ba Queo), the project encountered difficulties in traffic flow and the water supply system did not match the original design, forcing adjustments, slowing down the construction progress.

Ha tang ky thuat tai nhieu nha ga metro so 2 phuc tap, cac nha thau ton nhieu thoi gian xu ly. Ảnh: Anh Tu
The technical infrastructure at many Metro No. 2 stations is complicated, and contractors spend a lot of time processing it. Photo: Anh Tu

According to Mr. Vu Van Vinh, Director of Project Management Board 2 - Ho Chi Minh City Urban Railway Management Board: "To speed up the progress, the contractor has mobilized machinery and workers to work in 3 shifts, continuously day and night, and at the same time divided the construction teams to promote the project progress. The goal is to complete the main water supply and drainage items of Metro Line 2 by the end of the year.

As for Democracy Station, due to the city's large water supply system, the construction time will be longer and is expected to be completed in mid-2025. The entire technical infrastructure will also be completed in mid-2025, so that at the end of the year, construction of the underground station, tunnel and elevated section can begin.

Nguoi dan tren duong Cach Mang Thang 8 (Quan 3) sua lai nha sau khi giao mat bang lam Metro so 2. Ảnh: Minh Quan
Households on Cach Mang Thang 8 Street (District 3) renovate their houses after the land was handed over for Metro Line 2. Photo: Anh Tu

According to plan, Metro Line 2 will be constructed in 5 years and is expected to be completed by the end of 2030.

Metro Line 2 was approved in 2010, with an initial investment of 1.3 billion USD (26,000 billion VND). By 2019, the total investment had been adjusted to 2.1 billion USD (nearly 47,900 billion VND).

This Metro line is more than 11 km long, of which 9.2 km is underground and the rest is an elevated section leading to Tham Luong depot (District 12). The project includes 9 underground stations and 1 elevated station.

When put into operation, Metro Line 2 will connect with Metro Line 1 (Ben Thanh - Suoi Tien) at Ben Thanh Station (District 1), and connect with many other Metro lines in the future. This will help people move conveniently along the East - West axis of Ho Chi Minh City, contributing to reducing traffic congestion in the city center.

Anh Tú
TIN LIÊN QUAN

Nhan Dan Newspaper launches National Brands page

|

On the afternoon of October 22, Nhan Dan Newspaper in collaboration with the Ministry of Industry and Trade launched the National Brand page, providing comprehensive data on leading enterprises.

Import and export exceed 600 billion USD, forecast to have many more records

|

As of mid-October, the country's total import-export turnover reached 610.56 billion USD, with a trade surplus of 21.24 billion USD. It is forecasted that it could reach 800 billion USD by the end of the year.

Forecast of dangerous areas affected by storm Tra Mi

|

A representative of the meteorological agency said that after entering the East Sea, storm Tra Mi is likely to strengthen and head towards the coast of the Central provinces.

Secretly recording the handling of the "chaotic" passenger bus at Thang Long bridge

|

Hanoi Traffic Police will increase patrols, disguise themselves, and secretly record and handle passenger vehicles stopping and parking at the Thang Long Bridge.

Proposing China to properly handle the issue of fishing boats and fishermen

|

Vietnam requests that China properly handle the issue of fishing vessels and fishermen; respect each other's legitimate and legal rights and interests.

Awarding the decision to appoint Deputy Minister of Planning and Investment Nguyen Duc Tam

|

On the afternoon of October 22, the Ministry of Planning and Investment held an announcement of the Prime Minister's Decision on appointing Deputy Minister for comrade Nguyen Duc Tam.

New land price list narrows gap with market price

|

Land prices for calculating financial obligations and land taxes will be based on the time of application submission after the land price list of Ho Chi Minh City takes effect.

Nóng Sài Gòn: Mạnh tay cưỡng chế thu hồi đất làm Metro số 2

Thanh Chân - Chân Phúc |

Tin tức Nóng Sài Gòn ngày 24.9: Mạnh tay cưỡng chế thu hồi đất làm Metro số 2; Nam Bộ sắp đón đợt mưa lớn mới;...

TPHCM mạnh tay cưỡng chế thu hồi đất làm Metro số 2

MINH QUÂN |

TPHCM - Metro số 2 vẫn còn vướng 10 mặt bằng chưa được giải tỏa, trong đó một số trường hợp sẽ bị cưỡng chế thu hồi đất nhằm đẩy nhanh tiến độ dự án.

Gói thầu 63 triệu USD quyết định tiến độ Metro số 2 ở TPHCM

MINH QUÂN |

TPHCM - Metro số 2 (Bến Thành - Tham Lương) dự kiến khởi công vào năm 2025, nhưng đến nay gói thầu tư vấn trị giá 63 triệu USD vẫn chưa đấu thầu xong.