Progress of the trillion-dong road connecting Thai Nguyen with Tuyen Quang

Việt Bắc |

Thai Nguyen - Hundreds of workers and machinery are being mobilized to accelerate the progress of the Ho Chi Minh road project.

The Ho Chi Minh road project section Cho Chu - Trung Son intersection is nearly 29km long. Construction started in June 2024 with a total investment of more than 1,600 billion VND.

In which, the section through Thai Nguyen province is 11.51km long; through Tuyen Quang province is about 17.1km. The starting point of the project is in Cho Chu town (Km 245+878), the ending point is at Trung Son intersection (Km 276+135.5).

The project is invested on a scale of a grade III mountain road, roadbed width of 9m, design speed of 60km/h.

Trang thiết bị máy móc được huy động để đẩy nhanh tiến độ dự án. Ảnh: Ngọc Quang
Equipment and machinery are mobilized to accelerate the project progress. Photo: Ngoc Quang

PV recorded that after nearly 2 years of implementation, the shape of the trillion-dong road connecting Thai Nguyen and Tuyen Quang has gradually emerged.

At the construction site section passing through Thai Nguyen province, more than 500 engineers, workers and machinery and equipment were mobilized, deploying items simultaneously.

Construction teams stretch across the entire route, deploying items from roadbed, bridges and culverts to road surface structure.

Mr. Le Chi Nghia - Ho Chi Minh Road Project Management Board, Cho Chu - Trung Son intersection, said that so far, the roadbed section of over 12km belonging to construction package No. 2 in Thai Nguyen has completed the entire volume.

Contractors are focusing on asphalt concrete paving. At the same time, increase manpower, equipment, and organize overtime construction to ensure progress.

Currently, bridge projects on the route are also being accelerated. Most have completed the main structure and moved to the completion phase.

According to the construction contractors, the asphalt concrete paving item at the project is being accelerated, with the goal of completion before April 30th. The completion of the asphalt paving layer on schedule is associated with quality requirements.

Many technical solutions to improve durability, extend road surface life, and limit damage during exploitation have been implemented.

Dự án đường Hồ Chí Minh đoạn Chợ Chu - ngã ba Trung Sơn. Ảnh: Việt Bắc
Ho Chi Minh Road project section Cho Chu - Trung Son intersection. Photo: Viet Bac

To date, the disbursement rate has reached over 60%. The Ho Chi Minh road project section Cho Chu - Trung Son intersection is expected to be completed in the third quarter of 2026.

When completed, the road will contribute to completing the inter-regional transportation network, connecting the midlands and mountainous areas of the North with the plains and major economic centers.

This will be an important vertical axis, helping to reduce pressure on national highways, especially National Highway 3.

According to the plan, the Ho Chi Minh road project section Cho Chu - Trung Son intersection will be completed and put into operation at the end of 2025.

However, encountering some obstacles forced the project to postpone the milestone to the finish line. The Ministry of Construction has issued a decision approving the project adjustment, postponing the completion time to the third quarter of 2026.

Việt Bắc
RELATED NEWS

Ring Road 1 project accelerates progress amidst material and site pressure

|

Despite facing many difficulties in terms of land, increased material costs and traffic organization, contractors are still making efforts to accelerate the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Focusing efforts to complete the Khanh Hoa - Buon Ma Thuot expressway on schedule

|

Khanh Hoa - The Khanh Hoa - Buon Ma Thuot expressway project is being accelerated, striving to complete the entire route by the end of 2026 as directed by the Government.

Ha Tinh urges progress of 2 inter-level boarding schools to start construction from 2025

|

Ha Tinh - The Provincial People's Committee has just urged to accelerate the construction progress of the inter-level boarding primary and secondary school in Son Kim 1 and Huong Khe communes.

The Strait of Hormuz divides the fate of Middle Eastern oil nations

|

The blockade of the Strait of Hormuz and the sharp increase in global oil prices are creating a clear divide between Middle Eastern oil nations.

Bayern Munich beat Real Madrid at the Bernabeu

|

On the morning of April 8 (Vietnam time), Bayern Munich defeated Real Madrid 2-1 in the first leg of the quarterfinals of the Champions League 2025-2026 season.

Progress of the trillion-dong road connecting Thai Nguyen with Tuyen Quang

|

Thai Nguyen - Hundreds of workers and machinery are being mobilized to accelerate the progress of the Ho Chi Minh road project.

Da Nang tightens permits for high-rise buildings, re-plans parking lots

|

Da Nang - Da Nang City People's Committee is focusing on reviewing the licensing of high-rise buildings and re-planning the parking system.

Live football U20 Vietnamese women vs U20 Bangladesh women at the 2026 Asian U20 women's tournament

|

Live football match between Vietnam U20 women's team and Bangladesh U20 women's team in the group stage of the 2026 AFC U20 Women's Championship at 8:00 PM tonight (April 7).

Ring Road 1 project accelerates progress amidst material and site pressure

Tùng Giang |

Despite facing many difficulties in terms of land, increased material costs and traffic organization, contractors are still making efforts to accelerate the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Focusing efforts to complete the Khanh Hoa - Buon Ma Thuot expressway on schedule

Hữu Long |

Khanh Hoa - The Khanh Hoa - Buon Ma Thuot expressway project is being accelerated, striving to complete the entire route by the end of 2026 as directed by the Government.

Ha Tinh urges progress of 2 inter-level boarding schools to start construction from 2025

TRẦN TUẤN |

Ha Tinh - The Provincial People's Committee has just urged to accelerate the construction progress of the inter-level boarding primary and secondary school in Son Kim 1 and Huong Khe communes.