Ring Road 1 project accelerates progress amidst material and site pressure

Tùng Giang |

Despite facing many difficulties in terms of land, increased material costs and traffic organization, contractors are still making efforts to accelerate the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Many pressures from costs and traffic organization

These days, at the Ring Road 1 project site, Hoang Cau - Voi Phuc section, the construction atmosphere is always maintained urgently. Construction teams are organized flexibly, divided into shifts continuously, taking advantage of each hour to closely follow the set schedule. The immediate goal is to technically open the left-sided route by the end of June and aim to complete the entire route in 2026.

Talking to Lao Dong Newspaper, Mr. Le Ba Luong - Deputy Construction Site Commander of Ring Road 1 package, Hoang Cau - Voi Phuc section (Construction & Trading Joint Stock Company 68) - said that the unit is making maximum efforts to meet the general progress of the project.

According to Mr. Luong, the plan is to technically open each section on the left side of the route by June, then organize the construction of the right lane, on the De La Thanh side. This is to take advantage of the ground and maintain continuous construction of the next items.

Although progress is being accelerated, the construction process still faces many difficulties. Mr. Luong said that one of the major challenges comes from market price fluctuations when the cost of materials and supplies escalates. "Proviners continuously propose price adjustments, forcing contractors to review and adjust contract appendices to suit reality" - Mr. Luong said.

In addition, the specific nature of construction in the inner city area makes the transportation of materials, materials and waste soil very limited. The De La Thanh line is currently organized for one-way traffic, so vehicles serving construction can mainly operate only at night.

However, even during this time frame, traffic conditions are not favorable. At many times, transport vehicles have to go in long circles, prolonging travel time, directly affecting work progress. Faced with that reality, contractors are forced to adjust construction plans, increase shifts, increase crews, and arrange many parallel construction teams to compensate for the affected time.

Accelerate the construction of overpasses, limiting the impact on the progress of the entire route

Not only the Hoang Cau - Voi Phuc section, on the entire Ring Road 1, overpass items at Lang Ha and Nguyen Chi Thanh intersections are also being implemented simultaneously.

At these construction sites, the lower structures such as foundation pits and drilled piles are being urgently deployed. On average, about 50 workers work every day, organizing continuous 3 shifts of construction. For items requiring high progress, the contractor arranges construction day and night.

According to the construction unit, the overpass at the Lang Ha - Giang Vo intersection was started in mid-June 2020. However, in the process of implementation, a situation of overlapping ground between the bridge and road construction units has arisen. Currently, relevant parties are actively coordinating to remove obstacles, in order to minimize the impact on the overall progress of the project.

Mr. Tieu Van Huy - Commander of Lang Ha - Giang Vo overpass project - informed that the unit is closely following the set plan. Initially, the construction time was expected to be 17 months, but after the direction of the Hanoi Party Committee and the Project Management Board, the progress has been shortened to 12 months. "The progress of both the bridge and the road sections is currently being accelerated. However, due to the narrow construction area, the units are deploying simultaneously, so it is easy to overlap the ground. We are closely coordinating to organize reasonable construction, ensuring the overall progress" - Mr. Huy said.

The Ring Road 1 project, Hoang Cau - Voi Phuc section, is more than 2.2km long, with a cross-section of 50m, connecting Hoang Cau intersection (Cat Linh - La Thanh - Yen Lang) with Voi Phuc intersection. This is one of the vital traffic axes of the Capital.

The project has a total investment of more than 7,200 billion VND from the city budget, approved from December 2017, expected to be completed in 2020. However, due to many problems, the project has been delayed for many years. Recently, the construction progress has been accelerated again, igniting the expectation of soon completing the road, thereby contributing to reducing the pressure of prolonged capital congestion in the inner city of Hanoi.

Tùng Giang
RELATED NEWS

Hanoi Secretary points out experience in site clearance from Ring Road 1 project

|

Hanoi - Mr. Nguyen Duy Ngoc pointed out the experiences in site clearance for Ring Road 1, which need to be replicated for other projects.

The government propagates that households still deliberately do not hand over the land for the Ring Road 1 project

|

Hanoi - Giang Vo Ward has basically completed site clearance for the Ring Road 1 project, and is mobilizing the remaining cases to be handed over before December 15.

Enforced site clearance for Ring Road 1 project

|

Hanoi - Despite propaganda and mobilization, households in Giang Vo ward still do not hand over the land for the Ring Road 1 project, and the authorities have to force it.

Mr. Nguyen Huy Tien re-elected as Chief Procurator of the Supreme People's Procuracy

|

The National Assembly has passed a Resolution electing Mr. Nguyen Huy Tien as Chief Procurator of the Supreme People's Procuracy for the term 2026-2031.

Ms. Vo Thi Anh Xuan re-elected as Vice President

|

At the First Session, the 16th National Assembly elected Ms. Vo Thi Anh Xuan to hold the position of Vice President of the Socialist Republic of Vietnam for the term 2026-2031.

Mr. Nguyen Van Quang re-elected Chief Justice of the Supreme People's Court

|

Mr. Nguyen Van Quang - Secretary of the Party Central Committee was elected by the National Assembly to hold the position of Chief Justice of the Supreme People's Court.

Proposal to supplement measures to temporarily suspend vehicle registration when enforcing administrative sanctions

|

According to the new draft related to administrative sanction coercion, functional agencies add measures to temporarily suspend vehicle registration.

US prioritizes sending troops home instead of taking over Iranian oil

|

President Trump acknowledged his desire to take over the Iranian oil industry to generate profits, but affirmed the desire of the American people to end the war soon.

Hanoi Secretary points out experience in site clearance from Ring Road 1 project

SÓNG HỮU |

Hanoi - Mr. Nguyen Duy Ngoc pointed out the experiences in site clearance for Ring Road 1, which need to be replicated for other projects.

The government propagates that households still deliberately do not hand over the land for the Ring Road 1 project

HỮU CHÁNH - HẢI NGUYỄN |

Hanoi - Giang Vo Ward has basically completed site clearance for the Ring Road 1 project, and is mobilizing the remaining cases to be handed over before December 15.

Enforced site clearance for Ring Road 1 project

HỮU CHÁNH - HẢI NGUYỄN |

Hanoi - Despite propaganda and mobilization, households in Giang Vo ward still do not hand over the land for the Ring Road 1 project, and the authorities have to force it.