Quang Binh province requests handover of land for National Highway 12A project

CÔNG SÁNG |

The Chairman of the People's Committee of Quang Binh province requested Quang Trach district and Ba Don town to hand over the site for the National Highway 12A project before September 15.

Stuck in land for many years

The project to renovate and upgrade National Highway 12A, Ba Don bypass section and Song Gianh Cement Factory bypass section, has a total length of 10.83km, invested by the Department of Transport of Quang Binh province.

The project was approved by the Ministry of Transport for investment policy and investment policy adjustment in the decision dated December 30, 2022, with a total investment of VND 511,154 billion, and completion date of December 31, 2024.

The project consists of 2 independent component projects. Of which, component project 1 invests in the construction of National Highway 12A, avoiding Ba Don town, with a total investment of 447,177 billion VND.

Component project 2 invests in completing National Highway 12A, avoiding Song Gianh Cement Factory, with a total investment of 63 billion VND.

Mr. Ngo Duc Thinh - Deputy Director of the Traffic Construction Investment Project Management Board, Quang Binh Department of Transport said that up to now, the project component 1 has completed the handover of accessible sections for construction of about 4.70km/5.76km (80% of the route length), the remaining problems are mainly concentrated at 2 bottlenecks in Quang Trach district and Ba Don town.

Many locations cannot be built due to land issues. Photo: H. Van
Many locations cannot be built due to land issues. Photo: H. Van

“In component project 2, the construction and acceptance of the 4.65km/5.07km section has been completed since December 2023. Currently, the remaining 0.42km section through Canh Hoa commune is stuck with site clearance and resettlement that has lasted from 2022 until now and has not been completed yet,” said Mr. Thinh.

According to Mr. Thinh, the unit has made many recommendations to the People's Committees of localities to speed up the site clearance process. This helps the project to finish on schedule.

Hand over the site before September 15

Recently, Mr. Tran Thang - Chairman of Quang Binh Provincial People's Committee sent a document to units and 2 localities, Quang Trach District People's Committee and Ba Don Town People's Committee, regarding the site clearance work of the above project.

Mr. Thang pointed out that the implementation of site clearance and resettlement work is too slow, with no significant changes since the beginning of 2024.

Mr. Thang requested the two localities to urge their departments and affiliated units to complete the entire site clearance work before September 15.

“Quang Trach district and Ba Don town direct the district police to grasp the situation, have plans to protect security and order; strictly handle those who cause trouble and obstruct construction, especially those cadres and party members who incite and entice households around the construction site to intentionally obstruct and threaten the contractor within the cleared area,” Mr. Thang emphasized.

Land acquisition issues have stalled the project. Photo: Cong Sang
Land acquisition issues have stalled the project. Photo: Cong Sang

At the same time, quickly approve detailed planning, establish, appraise and approve technical economic reports for resettlement area construction.

The province requires the completion of related procedures and the construction of technical infrastructure for resettlement areas no later than October 30. Along with the construction of resettlement areas, it is possible to carry out procedures for land measurement, change of land use purpose, and drawing lots to allocate land to 10 resettled households on plots of land adjacent to existing traffic routes.

CÔNG SÁNG
TIN LIÊN QUAN

Quảng Bình cưỡng chế để hoàn trả mặt bằng cho cao tốc Bắc - Nam

CÔNG SÁNG |

UBND huyện Lệ Thủy (Quảng Bình) đã ban hành 5 quyết định, 12 trường hợp đang hoàn thiện hồ sơ để cưỡng chế nhằm hoàn trả mặt bằng cho cao tốc Bắc - Nam.

Giải quyết điểm đen tai nạn trên Quốc lộ 12A trong tháng 9

CÔNG SÁNG |

Các ngành chức năng tỉnh Quảng Bình sẽ hoàn thành nâng cấp, sửa chữa "điểm đen" tai nạn trên Quốc lộ 12A trong tháng 9.

Tai nạn liên hoàn trên Quốc lộ 12A, một tài xế tử vong

CÔNG SÁNG |

Xe đầu kéo mang BKS Lào khi đang lưu thông đến xã Dân Hóa (huyện Minh Hóa, tỉnh Quảng Bình) thì va chạm với xe lu và xe đầu kéo khác khiến một tài xế tử vong.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Nguyên chủ tịch xã ở Thái Bình bị tố lạm quyền để trục lợi

TRUNG DU |

Thái Bình - Nguyên Chủ tịch UBND xã Quỳnh Hải, huyện Quỳnh Phụ bị tố lợi dụng chức vụ quyền hạn để tư lợi, trục lợi cho bản thân, gia đình.