Overview of more than 5,000 personnel and machinery for the heart-shaped construction of the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - The Long Thanh airport component project 3 has 14 packages, of which package 5.10 for the construction of the passenger terminal is considered the heart of the project.

Reporters from Lao Dong Newspaper were present at the Long Thanh airport project site in Dong Nai province to record the urgent and serious construction atmosphere at the project.

According to Vietnam Airports Corporation (ACV), component project 3 - part of Long Thanh International Airport project phase 1 (abbreviated as Long Thanh airport) has a total investment of more than VND 99,000 billion, including 14 bidding packages. Up to now, 3 packages have been completed, 9 packages are under construction, the remaining 2 packages are about to select contractors.

According to ACV, for package 5.10, the construction of the passenger terminal (known as the heart of the project, as well as the gantt road for the progress of the entire Long Thanh airport project), the consortium of contractors mobilized to arrange 4,428 personnel and more than 1,000 machines and equipment to carry out the construction.

Currently, the rough construction work has reached about 80% and is being completed such as water painting, ceilings, installation of aluminum frame glass walls in the central area and the station wing...

Regarding station equipment such as: luggage handling system, checked baggage screening system, train parking system, escalator system, pedestrian elevator, elevator system... are also being urgently implemented...

An officer of the Long Thanh Airport Project Management Board shared that the appearance of the Long Thanh airport project is changing every day...

Overview of the construction of package 5.10 of Long Thanh airport passenger terminal, the heart of the project:

h1
The passenger terminal area and the parking lot of the Long Thanh airport project in Dong Nai province.
h2
Construction of the main roof of the Long Thanh airport passenger terminal.
h3
To ensure water supply before the rainy season, the entire roof (class 1-decking and skylight) will be completed by mid-July 2025.
h4
The construction is taking place urgently and seriously to ensure the progress and quality of the project.
h5
Inside the second floor of the Long Thanh airport passenger terminal, many modern machines were mobilized during the construction process to ensure labor safety for officers, engineers, experts and workers...
h6
Package 5.10 has completed the reinforced concrete structure of the underground part, floors 1, 2, 3, 4.
h7
Package 5.10 is constructed by the VIETUR consortium, and will start construction in mid-2023.
h8
Regarding station equipment such as: luggage handling system, checked baggage screening system, train parking system, escalator system, pedestrian elevator, elevator system... are also being urgently implemented...
h9
Irrigation work is carried out regularly, minimizing the impact of dust.
h10
Construction of airport cage pipes at Long Thanh airport passenger terminal.
h11
Overview of the heart of the Long Thanh airport project.

On the entire construction site at present, the units are still maintaining the construction progress with hundreds of deployment teams, mobilizing nearly 13,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment to speed up the progress of the packages with the goal of basically completing the project by the end of 2025, putting it into operation and commercial exploitation in the first half of 2026 in accordance with the Prime Minister's request.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Close-up of the headquarters of state management agencies at Long Thanh airport racing for progress

|

Dong Nai - The projects of port headquarters, customs, immigration, police... are gradually emerging to prepare for Long Thanh airport to be put into operation in 2026.

Mobilizing nearly 13,000 personnel to urgently construct Long Thanh airport

|

Despite unfavorable weather and a shortage of human resources, nearly 13,000 experts, engineers and workers are being urgently mobilized to complete the Long Thanh airport project on schedule by the end of 2025.

Hundreds of personnel and machinery constructing the Long Thanh airport fuel supply package

|

Dong Nai - Package 4.9, construction of the fuel supply system for Long Thanh airport, has a contract value of more than VND 2,880 billion.

20h News: Areas in Hanoi are about to ban gasoline vehicles from 2026

|

20h News: Where is Hanoi's Ring Road 1 about to ban gasoline vehicles, including which streets; The problem of printing shops in Lao Cai is worth billions of dong, some units have paid off debts...

1 year of the failed assassination of Mr. Trump, exposing the errors of the US Secret Service

|

A year after the failed assassination attempt on Mr Trump in Pennsylvania, the federal investigation report has just revealed a series of serious errors by the US Secret Service.

Current status of Hanoi Ring Road 1 will ban gasoline vehicles from July 2026

|

Hanoi is about to ban gasoline motorbikes from traveling on Ring Road 1, including the Hoang Cau - Voi Phuc section, the road considered "the most expensive on the planet".

A series of houses in the center of Ho Chi Minh City are still blocked by signs and billboards

|

HCMC - Many houses in the center, where there are many people, have signs and roofs covering all floors, posing a potential risk of obstructing rescue if there is a fire or explosion.

Close-up of the headquarters of state management agencies at Long Thanh airport racing for progress

HÀ ANH CHIẾN |

Dong Nai - The projects of port headquarters, customs, immigration, police... are gradually emerging to prepare for Long Thanh airport to be put into operation in 2026.

Mobilizing nearly 13,000 personnel to urgently construct Long Thanh airport

HÀ ANH CHIẾN |

Despite unfavorable weather and a shortage of human resources, nearly 13,000 experts, engineers and workers are being urgently mobilized to complete the Long Thanh airport project on schedule by the end of 2025.

Hundreds of personnel and machinery constructing the Long Thanh airport fuel supply package

HÀ ANH CHIẾN |

Dong Nai - Package 4.9, construction of the fuel supply system for Long Thanh airport, has a contract value of more than VND 2,880 billion.