Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

On July 7, Vietnam Airports Corporation (ACV) informed about the implementation of component project 3 - part of Long Thanh International Airport project phase 1 (abbreviated as Long Thanh airport)

The Long Thanh airport component project 3 has a total investment of more than VND 99,000 billion, including 14 packages. Up to now, 3 packages have been completed, 9 packages are under construction, the remaining 2 packages are about to select contractors.

According to ACV, from the beginning of May 2025 to now, the weather at the construction site (Dong Nai province) has changed unfavorably when the rainy season arrived about a month earlier than expected. Continuous heavy rain with heavy rain has seriously affected the entire construction work, disrupting many items, especially underground works such as technical pilotons, drainage systems, roadbeds, etc.

In addition, the work of mobilizing workers for the project has encountered many difficulties...

Despite many challenges, at the current construction site, the units still maintain the construction progress with hundreds of deployment teams, mobilizing nearly 13,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment to speed up the progress with the goal of basically completing the project by the end of 2025, putting it into operation and commercial exploitation in the first half of 2026 in accordance with the Prime Minister's request.

For package 5.10, construction of the passenger terminal (considered the gantt road for the progress of the entire Long Thanh airport project), the consortium of contractors mobilized to arrange 4,428 personnel and more than 1,000 machines and equipment to carry out the construction.

Currently, the rough construction work has reached nearly 79.5% and is being completed such as water painting, ceilings, installation of aluminum frame glass walls in the central area and the station wings...

Regarding station equipment such as: luggage handling system, checked baggage screening system, train parking system, escalator system, pedestrian elevator, elevator system... are also being urgently implemented...

Some images recorded by reporters at the Long Thanh airport project overcoming construction difficulties during the rainy season:

Gan 13.000 chuyen gia, ky su, nguoi lao dong va gan 3.000 thiet bi thi cong dang duoc huy dong day nhanh tien do du an san bay Long Thanh. Anh: HAC
Nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress of the Long Thanh airport project. Photo: HAC
HÀ ANH CHIẾN
TIN LIÊN QUAN

Developing a $16 billion free trade zone project near Long Thanh airport

|

Dong Nai - The estimated cost to build a free trade zone near Long Thanh airport is about 16 billion USD with an area of nearly 8,300 hectares.

Starting construction of 2 aviation service projects at Long Thanh airport, investing nearly 1,800 billion VND

|

Dong Nai - Vietnam Airlines has started two projects on food supply and aircraft maintenance at Long Thanh airport.

Install fire prevention and fighting systems at Long Thanh airport passenger terminal

|

Dong Nai - Fire prevention and fighting system is an important item at the passenger terminal at Long Thanh airport project.

Plan to help people save costs when metro tickets increase from 1.8

|

Hanoi - Tickets for the two metro lines will increase from August 1, 2025, the highest at 40%.

Expanding conditions, more cases are considered for amnesty on September 2

|

The amnesty on the occasion of the 80th anniversary of National Day on September 2 has many new points, including expanding the subjects and conditions for amnesty consideration.

Hanoi leaders talk about taking water from the Red River to supplement West Lake and To Lich River

|

According to Hanoi leaders, taking the additional water from the Red River to West Lake and To Lich River is a major policy, requiring strict control of total investment, costs and operations.

Motorbikes still overflow into the car lane on Pham Van Dong Street, traffic police on duty to remind

|

Hanoi - The situation of motorbikes entering the lane reserved for cars on Pham Van Dong Street is still happening.

Put 6 cases and incidents under the monitoring of the Steering Committee for Anti-Corruption and Wastefulness

|

The Central Steering Committee on preventing and combating corruption, waste and negativity agreed to include 6 cases and incidents under the monitoring and direction of the Steering Committee.

Developing a $16 billion free trade zone project near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The estimated cost to build a free trade zone near Long Thanh airport is about 16 billion USD with an area of nearly 8,300 hectares.

Starting construction of 2 aviation service projects at Long Thanh airport, investing nearly 1,800 billion VND

HÀ ANH CHIẾN |

Dong Nai - Vietnam Airlines has started two projects on food supply and aircraft maintenance at Long Thanh airport.

Install fire prevention and fighting systems at Long Thanh airport passenger terminal

HÀ ANH CHIẾN |

Dong Nai - Fire prevention and fighting system is an important item at the passenger terminal at Long Thanh airport project.