Hundreds of personnel and machinery constructing the Long Thanh airport fuel supply package

HÀ ANH CHIẾN |

Dong Nai - Package 4.9, construction of the fuel supply system for Long Thanh airport, has a contract value of more than VND 2,880 billion.

On July 8, information from Vietnam Airports Corporation (ACV) said about the implementation of component project 3 - part of Long Thanh International Airport project phase 1 (abbreviated as Long Thanh airport).

In particular, for package 4.9, construction of the fuel supply system, up to now, the consortium of contractors has mobilized nearly 465 personnel and more than 80 construction machinery and equipment to speed up the progress.

To ensure the timely handover of the underground pipeline in the bean sprout area according to the plan, the contractor has organized 13/14 simultaneous construction teams, distributed throughout the bean sprout area.

At the same time, other items are also being actively implemented, including: construction of valve holes, excavation of pipeline soil, construction of fuel tank foundations, construction of fuel tank installation, construction of houses and auxiliary works, rainwater drainage systems and landscape roads. The total value of the volume to date has reached about 1,016 billion VND.

Package 4.9, the fuel supply system for the construction contractor is a consortium of Vietnam Oil and Gas Technical Services Corporation - BCA - Thang Long One Member Co., Ltd. (abbreviated as: PTSC - BCA TL consortium); Contract value is over VND 2,880 billion.

The Long Thanh airport component project 3 has a total investment of more than VND 99,000 billion, including 14 packages. Up to now, 3 packages have been completed, 9 packages are under construction, the remaining 2 packages are about to select contractors. At the current construction site, the units are still maintaining the construction progress with hundreds of deployment teams, mobilizing nearly 13,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment to speed up the progress with the goal of basically completing the project by the end of 2025, putting it into operation and commercial exploitation in the first half of 2026 in accordance with the Prime Minister's request.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

|

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Urgently expand the Ho Chi Minh City - Long Thanh expressway to shorten travel time to Long Thanh airport

|

The Government Office has just issued a document notifying the opinion of Deputy Prime Minister Tran Hong Ha on the implementation of the Ho Chi Minh City - Long Thanh Expressway expansion project.

Developing a $16 billion free trade zone project near Long Thanh airport

|

Dong Nai - The estimated cost to build a free trade zone near Long Thanh airport is about 16 billion USD with an area of nearly 8,300 hectares.

Consider handling organizations and individuals if there are violations in the bidding package proposed by Son Hai Group

|

The Ministry of Finance has just sent a document reporting to the Government on the bid package previously proposed by Son Hai Group.

Big fire at fabric warehouse in Da Nang, many assets and equipment burned down

|

Da Nang - As of 10:00 a.m. on July 8, the Da Nang Fire Police force was still trying to handle the fire at a fabric warehouse on Nguyen Dinh Tuu Street, An Khe Ward.

A major road in Hanoi is under repair, vehicles are banned from circulating from night to morning

|

Hanoi - From 10pm - 6am, vehicles are prohibited from traveling on Ring Road 3 from Nguyen Trai - Thang Long Avenue to repair the expansion joints and bridge deck.

Landslide on National Highway 15D, road to La Lay International Border Gate cut off

|

Quang Tri - The landslide occurred while the construction unit was expanding the curve on National Highway 15D to the La Lay international border gate, causing traffic disruption.

Russian general arrested on corruption charge

|

Russia arrested Senior Lieutenant General Viktor Strigunov, former Deputy Commander of the National Guard, on serious corruption charges.

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Urgently expand the Ho Chi Minh City - Long Thanh expressway to shorten travel time to Long Thanh airport

Lê Thanh Phong |

The Government Office has just issued a document notifying the opinion of Deputy Prime Minister Tran Hong Ha on the implementation of the Ho Chi Minh City - Long Thanh Expressway expansion project.

Developing a $16 billion free trade zone project near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The estimated cost to build a free trade zone near Long Thanh airport is about 16 billion USD with an area of nearly 8,300 hectares.