Hundreds of personnel and machinery constructing the Long Thanh airport fuel supply package

HÀ ANH CHIẾN |

Dong Nai - Package 4.9, construction of the fuel supply system for Long Thanh airport, has a contract value of more than VND 2,880 billion.

On July 8, information from Vietnam Airports Corporation (ACV) said about the implementation of component project 3 - part of Long Thanh International Airport project phase 1 (abbreviated as Long Thanh airport).

In particular, for package 4.9, construction of the fuel supply system, up to now, the consortium of contractors has mobilized nearly 465 personnel and more than 80 construction machinery and equipment to speed up the progress.

To ensure the timely handover of the underground pipeline in the bean sprout area according to the plan, the contractor has organized 13/14 simultaneous construction teams, distributed throughout the bean sprout area.

At the same time, other items are also being actively implemented, including: construction of valve holes, excavation of pipeline soil, construction of fuel tank foundations, construction of fuel tank installation, construction of houses and auxiliary works, rainwater drainage systems and landscape roads. The total value of the volume to date has reached about 1,016 billion VND.

Package 4.9, the fuel supply system for the construction contractor is a consortium of Vietnam Oil and Gas Technical Services Corporation - BCA - Thang Long One Member Co., Ltd. (abbreviated as: PTSC - BCA TL consortium); Contract value is over VND 2,880 billion.

The Long Thanh airport component project 3 has a total investment of more than VND 99,000 billion, including 14 packages. Up to now, 3 packages have been completed, 9 packages are under construction, the remaining 2 packages are about to select contractors. At the current construction site, the units are still maintaining the construction progress with hundreds of deployment teams, mobilizing nearly 13,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment to speed up the progress with the goal of basically completing the project by the end of 2025, putting it into operation and commercial exploitation in the first half of 2026 in accordance with the Prime Minister's request.

HÀ ANH CHIẾN
RELATED NEWS

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

|

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Urgently expand the Ho Chi Minh City - Long Thanh expressway to shorten travel time to Long Thanh airport

|

The Government Office has just issued a document notifying the opinion of Deputy Prime Minister Tran Hong Ha on the implementation of the Ho Chi Minh City - Long Thanh Expressway expansion project.

Developing a $16 billion free trade zone project near Long Thanh airport

|

Dong Nai - The estimated cost to build a free trade zone near Long Thanh airport is about 16 billion USD with an area of nearly 8,300 hectares.

Digital transformation helps trade unions receive workers' thoughts faster

|

Ms. Ho Nhu Cat Tuong hopes that in the coming time there will be more solutions and digital utilities to strengthen the connection between union members and workers with the trade union organization.

Many expectations placed at the 14th Vietnam Trade Union Congress

|

On June 3, the 14th Vietnam Trade Union Congress entered its first working session, bringing expectations of practical innovations for union members and workers.

Continue to build a strong Trade Union organization in terms of ideology, politics and organization

|

On the morning of June 3, Mr. Nguyen Xuan Hung - Vice President of the Vietnam General Confederation of Labor reported on the amendment and supplementation of the Charter of the 13th Vietnam Trade Union.

Distinguished Delegate of An Giang sends expectations at the 14th Congress of the Vietnam Trade Union

|

As one of 780 outstanding delegates, representing the will, aspirations and intelligence of nearly 10 million trade union members nationwide attending the 14th Congress of the Vietnam Trade Union for the term 2026 - 2031, Mr. Do Tran Thinh - Chairman of the An Giang Provincial Labor Federation brought the thoughts, aspirations and expectations of union members and workers to the Congress.

The 14th Vietnam Trade Union Congress takes place from June 3-5, 2026

|

The 14th Vietnam Trade Union Congress, term 2026-2031, takes place from June 3-5 at the National Convention Center, Hanoi City.

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Urgently expand the Ho Chi Minh City - Long Thanh expressway to shorten travel time to Long Thanh airport

Lê Thanh Phong |

The Government Office has just issued a document notifying the opinion of Deputy Prime Minister Tran Hong Ha on the implementation of the Ho Chi Minh City - Long Thanh Expressway expansion project.

Developing a $16 billion free trade zone project near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The estimated cost to build a free trade zone near Long Thanh airport is about 16 billion USD with an area of nearly 8,300 hectares.