Close-up of the headquarters of state management agencies at Long Thanh airport racing for progress

HÀ ANH CHIẾN |

Dong Nai - The projects of port headquarters, customs, immigration, police... are gradually emerging to prepare for Long Thanh airport to be put into operation in 2026.

On July 10, Lao Dong Newspaper reporters recorded the reality of the Long Thanh airport project site (Long Thanh commune, Dong Nai province), component projects and packages are being simultaneously implemented, taking advantage of the weather during the sunny days (Dong Nai is currently in the rainy season) to speed up progress.

According to the representative of Vietnam Airports Corporation (ACV), despite facing many challenges, at the current construction site, the units are still maintaining the construction progress with hundreds of deployment teams, mobilizing nearly 13,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment to speed up the progress with the goal of basically completing the project by the end of 2025, putting it into operation and commercial exploitation in the first half of 2026 in accordance with the Prime Minister's request.

The Long Thanh airport project consists of 4 component projects. In particular, for component project 1 (headquarters of state management agencies), the construction of airports headquarters, customs headquarters, immigration management headquarters and local police headquarters have all been started.

Some actual images at component project 1 - Long Thanh airport:

h1
The Long Thanh International Airport Project Phase 1 (abbreviated as the Long Thanh Airport Project) includes 4 component projects. In particular, component project 1 (headquarters of state management agencies), currently the works of airport headquarters, customs headquarters, immigration management headquarters and local police headquarters have all been started. Photo: HAC
h2
For the Southern Airports Representative Office headquarters, the rough construction has been basically completed and is under construction. Photo: HAC
h3
The Southern Aviation Authority logo appeared at Long Thanh airport. Photo: HAC
h4
The immigration management headquarters and local police headquarters are also in the completion stage. Photo: HAC
h5
The customs headquarters at Long Thanh airport is completing the roof. Photo: HAC
h6
Many workers are urgently completing the painting at state management works at Long Thanh airport. At the working session of Minister of Construction Tran Hong Minh and the working delegation at the Long Thanh airport project on May 21, the Department of Economics - Construction Investment Management (Ministry of Construction) said: Component project 1 - Long Thanh airport has basically reached progress, many items are expected to be completed in the fourth quarter of 2025. Photo: HAC
h7
In addition to the gradually completed projects, it is noted that some of the projects that started construction later are also racing to promptly operate synchronously when Long Thanh airport is put into operation. Photo: HAC
h8
The project sign of the Long Thanh International Airport Animal Quarantine Station construction project (inspected by the investor of the Veterinary Department of Region VI), behind which is the project under construction. Photo: HAC
h9
Similarly, the project to build a plant quarantine station at Long Thanh airport is also under construction. Photo: HAC
h10
Overview of the passenger terminal of component project 3 - Long Thanh airport. Photo: HAC

On June 18, the Government Office announced the Conclusion of Deputy Prime Minister Tran Hong Ha at the meeting to deploy the investment project to build Long Thanh International Airport Phase 1. Accordingly, for component project 1, the Ministers of the Ministries are the projects' investment management agencies and the Chairman of the Dong Nai Provincial People's Committee is responsible for implementing the headquarters of state management agencies to ensure completion progress before December 31, 2025. The Ministry of Construction coordinates with the Ministries and People's Committees of Dong Nai province to review the implementation of bidding packages to ensure completion progress ( note that the headquarters works of animal and plant quarantine stations have started construction slowly).

HÀ ANH CHIẾN
TIN LIÊN QUAN

Hundreds of personnel and machinery constructing the Long Thanh airport fuel supply package

|

Dong Nai - Package 4.9, construction of the fuel supply system for Long Thanh airport, has a contract value of more than VND 2,880 billion.

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

|

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Starting construction of 2 aviation service projects at Long Thanh airport, investing nearly 1,800 billion VND

|

Dong Nai - Vietnam Airlines has started two projects on food supply and aircraft maintenance at Long Thanh airport.

Requesting 3 units to report the 208,000 VND bread case at Noi Bai airport before July 11

|

The Civil Aviation Authority of Vietnam has just requested units to report the 208,000 VND banh mi case at Noi Bai airport before July 11.

Continue to reorganize mass organizations assigned by the Party and the State

|

The Party Committee of the Vietnam Fatherland Front and Central organizations will lead and direct the continued reorganization of mass associations assigned by the Party and State to operate under the Vietnam Fatherland Front, in the direction of reducing the number, streamlining the internal apparatus, and operating practically and effectively.

Buying Vietlott lottery on the day of giving birth, a worker won more than 16 billion VND

|

A man has just received the Vietlott Jackpot 2 lottery draw Power 6/55 QSMT No. 01210 with a value of more than 16 billion VND.

Mr. Thaksin declares belief in the integrity of Paetongtarn's daughter

|

Former Thai Prime Minister Thaksin Shinawatra shared his views on the situation in Thailand and the suspension of his daughter, Ms. Paetongtarn, from the position of Prime Minister.

There have been conclusions about the person who shot down the MH17 passenger plane

|

The Malaysia MH17 plane crash due to shelling in 2014, with 298 passengers on board, has been determined.

Hundreds of personnel and machinery constructing the Long Thanh airport fuel supply package

HÀ ANH CHIẾN |

Dong Nai - Package 4.9, construction of the fuel supply system for Long Thanh airport, has a contract value of more than VND 2,880 billion.

Nearly 13,000 experts, engineers, and workers race to progress the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - At the Long Thanh airport project, nearly 13,000 experts, engineers, workers and nearly 3,000 construction equipment are being mobilized to speed up the progress.

Starting construction of 2 aviation service projects at Long Thanh airport, investing nearly 1,800 billion VND

HÀ ANH CHIẾN |

Dong Nai - Vietnam Airlines has started two projects on food supply and aircraft maintenance at Long Thanh airport.