HCMC disburses VND34,529 billion, people only receive VND7,069 billion

MINH QUÂN |

HCMC - Although VND34,529 billion in compensation capital has been disbursed in 2024, the actual amount of money paid to the people has only reached VND7,069 billion (20,57%).

This information is stated in the report of the Department of Natural Resources and Environment of Ho Chi Minh City sent to the People's Committee of Ho Chi Minh City on the progress of compensation payment and site handover for projects in 2024 in districts, towns and Thu Duc City.

As of January 31, 2025, the total compensation capital disbursed to 161 projects in 17 districts, towns and Thu Duc City is VND34,529 billion (reaching 98.44%) over VND35,076 billion in compensation capital in 2024.

Of which, District 11 and Binh Thanh District achieved a disbursement rate of 100%. Many other localities also have a high rate of over 98%, such as District 8 (99.98%), Go Vap District (99.79%), District 10 (99.56%), Nha Be District (99.36%), Binh Tan District (99%), Cu Chi District (98.96%), Thu Duc City (98.97%) and Hoc Mon District (98.19%).

However, despite the high disbursement rate, the actual payment progress for the people is still very slow. As of February 26, 2025, the total amount paid has only reached VND 7,069 billion, accounting for 20.47% of the total plan.

In particular, some districts and towns have very low payment rates, such as District 3 has not yet paid (00%)), Can Gio district has only reached 1.78%, District 8 has reached 2.84%, District 4 has reached 3.41% and Binh Thanh district has reached 7.06%.

According to the Department of Natural Resources and Environment, the amount of VND34,529 billion disbursed is actually the capital issued from the State Treasury.

According to the process, after the People's Committees of localities complete the approval of compensation, support and resettlement policies and plans for each project, the Investors and the State Treasury of Ho Chi Minh City will base on this decision to transfer money to the Compensation and Site Clearance Boards in districts, towns and Thu Duc City. These boards are responsible for making payments to the people.

Therefore, in terms of procedures, when the amount is disbursed from the State Treasury, the compensation capital is considered to have been disbursed.

According to the Department of Natural Resources and Environment of Ho Chi Minh City, one of the main reasons for the slow progress of compensation disbursement is the inaccurate budget making.

Due to the lack of a legal basis to inventory the current situation, local authorities can only estimate based on cadastral records. This leads to the temporary calculation of the entire recovered land as legal. When implemented in practice, the payment amount is often lower than the estimate, reducing the disbursement rate.

On the contrary, some projects have incurred higher compensation costs than expected, forcing them to adjust investment policies, prolonging implementation time. The delay also leads to "priced inflation", causing total investment to increase, making it more difficult to disburse.

Many projects do not follow the planning, and are forced to adjust after approval. Some cases of land recovery are not in accordance with the boundary or are not in sync with related projects, causing people to be affected many times, making it difficult to stabilize their lives and not agreeing with compensation policies. This causes difficulties in handing over the site and raising capital when land prices increase.

The People's Committees of localities have not closely coordinated with the Department of Construction in forecasting demand, leading to a shortage of resettlement housing funds. The delay in approving the land price adjustment coefficient has caused disagreement among people, prolonging the disbursement time.

There is a shortage of personnel participating in compensation work, leading to delays in handling documents. Some local leaders hesitate to verify the origin of the land, causing the compensation plan to be delayed in approval.

MINH QUÂN
RELATED NEWS

HCMC builds 2 more bridges to relieve traffic jams in Thu Duc City

|

HCMC - The My Thuy Intersection Project (Thu Duc City) is implementing phase 3 with the construction of an overpass on Ring Road 2 and Ky Ha 3 Bridge, with a total capital of 312 billion VND.

The most polluted canal in Ho Chi Minh City is about to be renovated with 17,000 billion VND

|

HCMC - After many years of waiting, the Xuyen Tam canal renovation project, the most polluted canal in the city, with a total capital of more than VND17,000 billion, will start construction in April 2025.

Compensation capital "blocked" at major projects in Ho Chi Minh City

|

In 2024, Ho Chi Minh City was assigned to disburse more than VND79,200 billion in public investment capital. However, as of November 29, the city had only disbursed more than VND19,700 billion, reaching 24.9% of the plan.

US wants to take over Greenland, pushing Europe into a difficult situation

|

Mr. Medvedev said that the US ambition to control Greenland is creating a major rift within the West, putting Europe in a dilemma.

Gold price update at the end of the session on February 2: Domestic gold prices plummet

|

Gold price update at the end of the session on February 2: The market plunged sharply after a period of hot increase, under increasing selling pressure as margin requirements increased.

Suspected gas cylinder explosion while cooking, father dies, son injured

|

Hà Tĩnh - Cơ quan Công an đang làm rõ thông tin tại xã Cẩm Trung xảy ra vụ nổ bình ga khiến hai cha con thương vong.

Female teacher suspended for impacting student's face right on the podium

|

Thai Nguyen - Teacher N.T.T.N was suspended for 15 days to verify and clarify the incident related to the video spread on social networks.

Lao Dong Newspaper presents Binh Ngo Tet Newspaper to forces tasked with protecting borders and islands

|

Hà Nội - Chiều 2.2, Báo Lao Động đã trao tặng 13.000 cuốn báo Tết cho các chiến sĩ Bộ đội biên phòng, Quân chủng Hải quân và Cảnh sát biển Việt Nam.

HCMC builds 2 more bridges to relieve traffic jams in Thu Duc City

MINH QUÂN |

HCMC - The My Thuy Intersection Project (Thu Duc City) is implementing phase 3 with the construction of an overpass on Ring Road 2 and Ky Ha 3 Bridge, with a total capital of 312 billion VND.

The most polluted canal in Ho Chi Minh City is about to be renovated with 17,000 billion VND

MINH QUÂN |

HCMC - After many years of waiting, the Xuyen Tam canal renovation project, the most polluted canal in the city, with a total capital of more than VND17,000 billion, will start construction in April 2025.

Compensation capital "blocked" at major projects in Ho Chi Minh City

MINH QUÂN |

In 2024, Ho Chi Minh City was assigned to disburse more than VND79,200 billion in public investment capital. However, as of November 29, the city had only disbursed more than VND19,700 billion, reaching 24.9% of the plan.