Ho Chi Minh City technically opens 1.4 km of road along Xuyen Tam canal on the morning of September 2nd

MINH QUÂN |

Ho Chi Minh City - About 1.4 km of road along Xuyen Tam canal, from Luong Ngoc Quyen street to Vam Thuat river (An Nhon ward) will be technically opened to traffic on the morning of September 2.

On August 31st, even during the National Day holiday, dozens of workers along with excavators and rollers were still busy constructing on the road along Xuyen Tam canal, the section from Luong Ngoc Quyen street to Vam Thuat river, belonging to An Nhon ward.

Đoạn rạch Xuyên Tâm qua phường An Nhơn trước lúc cải tạo.  Ảnh: Anh Tú
Xuyen Tam canal section through An Nhon ward before renovation. Photo: Anh Tu
Rạch Xuyên Tâm được xây kè và đường ven rạch. Ảnh: Anh Tú
Xuyen Tam canal is built with embankments and roads along the canal. Photo: Anh Tu

At the section passing through Van Lang University, the road surface has been asphalted. At both ends of the route, the area near Vam Thuat River and Luong Ngoc Quyen road has been paved with stone to prepare for asphalt paving. Workers are also completing sidewalk curbs.

Đoạn đường ven rạch Xuyên Tâm qua Đại học Văn Lang đã trải nhựa.  Ảnh: Anh Tú
The road along Xuyen Tam canal through Van Lang University has been paved. Photo: Anh Tu
Người dân lưu thông trên đường ven rạch Xuyên Tâm, đoạn qua Trường Đại học Văn Lang.  Ảnh: Anh Tú
People traveling on the road along Xuyen Tam canal, passing through Van Lang University. Photo: Anh Tu

Ms. Phan Thi Hoang Yen (70 years old, An Nhon ward) said she is very happy that the new spacious road is about to be opened to traffic. According to Ms. Yen, this area used to be a dead end, with dense trees and many snakes and centipedes, so people did not dare to travel in the evening.

“Previously, this place was as dense as a wild forest. Now the canal has been renovated, the new road has been opened, people have spacious space to travel, and the elderly and children also have places to exercise” - Ms. Yen said.

Công nhân thi công bó vỉa hè.  Ảnh: Minh Quân
Workers constructing sidewalk curbs. Photo: Minh Quan
Đường ven rạch Xuyên Tâm, đoạn gần sông Vàm Thuật, đã lu nền, chờ thảm nhựa.  Ảnh: Anh Tú
The road along Xuyen Tam canal, near Vam Thuat river, has been paved, waiting for asphalt paving. Photo: Anh Tu

Mr. Huynh Sanh (77 years old, An Nhon ward) also highly appreciated the project's construction speed. According to him, this area was previously muddy, desolate, and traffic was difficult. After being renovated, the landscape has changed significantly.

Mr. Sanh said that construction units work day and night to ensure progress. When completed, the road will not only make travel more convenient but also create conditions for the area on both sides of the canal to develop.

Đường ven rạch Xuyên Tâm, đoạn gần đường Lương Ngọc Quyến, cũng đang chờ thảm nhựa. Ảnh: Anh Tú
The road along Xuyen Tam canal, the section near Luong Ngoc Quyen street, is also waiting for asphalt paving. Photo: Anh Tu

More than 1.4 km of road preparing to open to traffic is one of the items under package XL-03, the section from Luong Ngoc Quyen road to Vam Thuat river, started in May 2025.

The bidding package includes the construction of a dyke along both banks of the canal with a total length of about 2.7 km; dredging the canal bed 3.5 m deep, 20 m wide.

The project also builds more than 2.84 km of traffic roads along both banks of the canal. In which, the left bank is newly built more than 1.4 km; the right bank is upgraded, expanded and strengthened more than 1.4 km of existing roads. The road surface is 6 - 11 m wide.

Drainage, lighting, and technical trenches are also invested synchronously. The green area along Xuyen Tam canal is 3.5 - 21 m wide, including miniatures and park space, with a total area of about 2.88 ha.

Người dân lưu thông trên đoạn đường ven rạch Xuyên Tâm đã được thảm nhựa. Ảnh: Minh Quân
People traveling on the section of road along Xuyen Tam canal have been asphalted. Photo: Minh Quan

Mr. Phan Nhat Linh - Head of Project Management Board 3 (Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board, the investor) - said that on the morning of September 2nd, about 1.4 km of the left bank of Xuyen Tam canal (belonging to An Nhon ward) will be technically opened to traffic, celebrating the 81st National Day.

To date, at package XL-03, the foundation treatment item using CDM technology has been completed; embankment has reached about 90%, wastewater collection 97%, traffic roads 70% and technical trenches 75%.

Sau khi thông xe kỹ thuật, tuyến đường ven kênh sẽ tiếp tục được thi công hệ thống chiếu sáng và mảng xanh. Ảnh: Anh Tú
After technical traffic opening, the canal-side road will continue to have lighting systems and green spaces constructed. Photo: Anh Tu

The remaining items, including dredging the canal bed, green trees, lighting, technical trenches, railings and right bank traffic roads, are expected to be completed in November 2026. The entire XL-03 package is expected to be completed and put into use in 2026.

The project to dredge and renovate Xuyen Tam canal (from Nhieu Loc - Thi Nghe canal to Vam Thuat river) is nearly 9 km long, including the main route of more than 6.6 km and 3 branch routes Cau Son, Binh Loi, Binh Trieu of more than 2.2 km long.

The project has a total investment of more than 17,200 billion VND from the Ho Chi Minh City budget.

In addition to XL-03, the Xuyen Tam canal renovation project also has two bidding packages underway.

Package XL-02, the section from Bui Dinh Tuy bridge to Luong Ngoc Quyen street, including Binh Loi canal and Binh Trieu canal (Binh Thanh and Binh Loi Trung wards), started construction at the end of 2025. Currently, 13 construction fronts are being deployed, with a volume of about 10%.

Package XL-01, the section from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy bridge, including Cau Son canal (Gia Dinh and Binh Thanh wards), started construction at the end of 2025. The package is being constructed at 4 locations, with a volume of about 5%.

According to the direction of the Chairman of Ho Chi Minh City People's Committee, the Urban Infrastructure Project Management Board is developing a plan to shorten the completion time of the entire Xuyen Tam canal project to December 2027.

MINH QUÂN
RELATED NEWS

Thousands of houses in Ho Chi Minh City lose a part of their area, homeowners still say "more happy than winning the lottery

|

Ho Chi Minh City - The Xuyen Tam canal renovation project not only revives the polluted canal but also helps thousands of houses in alleys become front houses.

Ho Chi Minh City's most polluted canal renovation project completes land recovery for 2,190 households

|

Ho Chi Minh City - Xuyen Tam canal renovation project completes land recovery for 2,190 households. Chairman of Ho Chi Minh City People's Committee requests acceleration of construction, completing the project by the end of 2027.

New shape of Xuyen Tam canal after many years of pollution

|

Ho Chi Minh City - After decades of pollution, people are excited to see Xuyen Tam canal being renovated, embankments and infrastructure gradually forming.

Voters propose to merge National Unity Day with Vietnam Culture Day

|

The Ministry of Culture, Sports and Tourism has a document responding to the recommendations of voters in some localities sent after the first session of the 16th National Assembly.

Forecast of the time to end widespread intense heat

|

Forecast from September 3rd, Northern Vietnam will only have localized hot weather with the highest temperature in some places above 35 degrees Celsius. In Central Vietnam, hot weather will continue until around September 4th.

Victim of passenger car overturning in Gia Lai paralyzed in both legs, emergency surgery

|

On September 1st, Cho Ray Hospital in Ho Chi Minh City reported to the Ministry of Health and the Department of Medical Examination and Treatment Management on emergency surgery for a two-legged paralyzed patient in the passenger car overturning incident in Gia Lai.

Many strong whirlpools appear, possibility of new storms in the next 2 weeks

|

On September 1, low pressure Pilandok officially strengthened into a tropical storm, warning of 4 more monsoon zones likely to form in the next 2 weeks.

Thousands of houses in Ho Chi Minh City lose a part of their area, homeowners still say "more happy than winning the lottery

MINH QUÂN |

Ho Chi Minh City - The Xuyen Tam canal renovation project not only revives the polluted canal but also helps thousands of houses in alleys become front houses.

Ho Chi Minh City's most polluted canal renovation project completes land recovery for 2,190 households

MINH QUÂN |

Ho Chi Minh City - Xuyen Tam canal renovation project completes land recovery for 2,190 households. Chairman of Ho Chi Minh City People's Committee requests acceleration of construction, completing the project by the end of 2027.

New shape of Xuyen Tam canal after many years of pollution

NHƯ QUỲNH |

Ho Chi Minh City - After decades of pollution, people are excited to see Xuyen Tam canal being renovated, embankments and infrastructure gradually forming.