Ho Chi Minh City recovers land from 98 households to expand 30m road to reduce congestion in Go Vap area

MINH QUÂN |

Ho Chi Minh City will complete land acquisition from 98 households and 2 organizations before September 3 to expand D3 road (section from Phan Van Tri to Quang Trung) to 30m.

Ho Chi Minh City People's Committee has just issued a plan to implement compensation, support and resettlement work to serve the D3 road expansion project, the section from Phan Van Tri street to Quang Trung street (Go Vap ward).

According to the plan, site clearance work will be implemented in 20 steps and must be completed before September 3, 2026 to ensure project progress.

The D3 road expansion project was approved by the Ho Chi Minh City People's Committee in 2016. Initially, the road was planned to be expanded to 20m with a construction cost of about 27 billion VND. The compensation and site clearance part was separated into a separate project with a total capital of nearly 84 billion VND. However, for many years the project has not been able to be implemented.

By October 2024, the Ho Chi Minh City People's Council adjusted the investment policy, raising the total project capital to nearly 657 billion VND after merging two projects into one.

The road surface scale was adjusted from 20m to 30m, leading to a sharp increase in compensation, support and resettlement costs, from nearly 84 billion VND to more than 550 billion VND.

Road D3 has a direction coinciding with alley 312 Quang Trung, about 360m long. After completion, the road will be expanded to 30m, connected to existing road No. 3, forming a smooth traffic axis from Nguyen Van Luong to Quang Trung.

The project is expected to contribute to reducing traffic pressure on frequently congested roads in areas such as Phan Van Tri, Quang Trung and Thong Nhat.

Hướng tuyến mở rộng đường D3. Ảnh: Minh Quân
Route direction to expand road D3. Photo: Minh Quan

According to the plan, the total land area expected to be recovered is more than 10,720m2, affecting 100 cases, including 98 households and 2 military units.

Among these, there are 21 cases expected to be resettled, including 8 households being completely cleared and 13 households being partially cleared but the remaining area is less than 15m2, not meeting living conditions.

The project is expected to be completed and put into operation by the end of 2027 or early 2028.

MINH QUÂN
RELATED NEWS

National Highway 13 is about to expand to 12 - 14 lanes, Ho Chi Minh City completes clearance before July 31

|

Ho Chi Minh City - National Highway 13 (from Binh Trieu bridge to Vinh Binh bridge) will be expanded to 12 - 14 lanes, the city requires completing the clearance of more than 1,000 households before July 31.

Trillion-dollar road surface to ease traffic jams in Go Vap

|

HCMC - The Duong Quang Ham Street expansion project (Go Vap) is speeding up construction progress, with the goal of completing the expansion to 6 lanes in 2025.

The 2,300 billion VND project to relieve traffic jams in Go Vap is still in disarray

|

HCMC - The project to expand Duong Quang Ham Street (Go Vap) with a total capital of 2,300 billion VND is still in disarray and unfinished despite the goal of opening to traffic by the end of 2024.

Iran shoots down US $30 million UAV

|

The Iranian Islamic Revolutionary Guard Corps announced that it had shot down a US unmanned aerial vehicle (UAV).

Fate" of "Trong com" and a series of million-view songs but without authors

|

The digital music market is developing diversely and complexly with many genres of music. Among them, folk songs or folk rhymes have a special "fate".

Black" Tai bowed his head to ask the court to reduce the sentence for his subordinates in the bank robbery case

|

Gia Lai - Giving his final words, Tai "den" - the mastermind behind the gun robbery of more than 1.8 billion VND at a Vietcombank bank transaction office - has asked for a reduced sentence for his subordinates.

Tax Department informs about cases of temporary exit suspension due to tax debt

|

The measure of temporary suspension of exit does not apply to personal income tax debts from salaries and wages, except for cases of exit to settle abroad.

National Highway 13 is about to expand to 12 - 14 lanes, Ho Chi Minh City completes clearance before July 31

MINH QUÂN |

Ho Chi Minh City - National Highway 13 (from Binh Trieu bridge to Vinh Binh bridge) will be expanded to 12 - 14 lanes, the city requires completing the clearance of more than 1,000 households before July 31.

Trillion-dollar road surface to ease traffic jams in Go Vap

Anh Tú |

HCMC - The Duong Quang Ham Street expansion project (Go Vap) is speeding up construction progress, with the goal of completing the expansion to 6 lanes in 2025.

The 2,300 billion VND project to relieve traffic jams in Go Vap is still in disarray

TÚ QUÂN |

HCMC - The project to expand Duong Quang Ham Street (Go Vap) with a total capital of 2,300 billion VND is still in disarray and unfinished despite the goal of opening to traffic by the end of 2024.