Trai bo sua nghin ti cham tien do, Thanh tra Chinh phu chi ra loat van de

Việt Bắc - Phùng Minh |

Tuyen Quang - The dairy farm project with a total investment of more than 2.2 trillion VND is currently behind schedule, with an unclear official operating date.

The project to invest in dairy cow farming and high-tech milk processing of Ha Giang High-Tech Dairy Farm Co., Ltd. has a total investment of more than 2.2 trillion VND. The project with a scale of about 10,000 heads, on an area of 80ha in Ha Giang 2 ward, Tuyen Quang province.

Started in 2017, according to the plan, in phase 1, this dairy farm will be completed and put into operation in the fourth quarter of 2024. However, to date, the project is behind schedule, no barns have been put into operation, and many construction items are unfinished.

Du an
The project to invest in dairy farming and high-tech milk processing of Ha Giang High-Tech Dairy Farm Co., Ltd. is being delayed. Photo: Viet Bac

Recorded by PV in the last days of December 2025, after many years of construction, 7 rows of barns have been built. Internal roads, feed processing centers for cows, wastewater treatment systems and other auxiliary items are being constructed.

Part of the road leading to the factory is also a people's road used by local people to transport materials and construction equipment. The flow of large tonnage trucks entering and leaving causes the road surface to be plowed, making travel difficult.

The project has been under construction for many years but has not been completed, the concrete road is already narrow, now all large trucks serving construction are entering very dangerously. People here hope the cow farm will soon operate, have more work and income," Ms. Ly Thi P (Ha Giang 2 ward) said.

Besides expectations for job creation and economic development, local people also expressed concern about the problem of treating odors and wastewater of the 10,000-head farm when it went into operation, because this area does not have rivers and streams flowing through, and water sources are scarce.

Mr. Ban Van T (Ha Giang 2 ward) shared: "We have heard about the air and water pollution situation in places with cattle farms. Although the farm here is not yet operating, we are also worried, people use groundwater and water flowing down from mountains for daily life and agricultural production, later if they are polluted, they will lose all livelihoods.

Regarding the project, recently, the Government Inspectorate also issued a conclusion pointing out a series of shortcomings in the approval of investment policies, adjustment of investment policies and slow progress.

According to the inspection conclusion, the survey process for detailed planning and project proposals was not rigorous, and the project area was based on the investor's proposal, leading to inconsistency and unity in data.

Especially, the lack of thorough geological surveys leads to the inability to use drilled wells to take water to serve the project (the water source for the cow farm currently depends on the Suu stream clean water project). To date, this trillion-VND cow farm project is behind schedule according to the investment policy approval decision.

The inspection conclusion also clearly stated that the responsibility for this limitation and shortcoming lies with the Chairman, Vice Chairman of the Provincial People's Committee, the investor, leaders of departments and branches, and the People's Committee of Vi Xuyen district (old) in charge of the relevant fields during the period.

The Government Inspectorate proposed that the Prime Minister direct the People's Committee of Tuyen Quang province to organize self-criticism, clarify responsibilities and handle them according to its authority or report and propose to competent authorities for handling.

Tuyen Quang Provincial People's Committee urgently organizes the implementation of conclusions and inspection recommendations, and takes measures to definitively handle difficulties and obstacles of the project.

Some images recorded at the project:

Con duong chinh dan vao du an cung la duong dan sinh cua hang tram ho dan luon trong tinh trang day bun dat, xe tai lon luu thong, nguy co mat an toan. Anh: Viet Bac.
The main road leading to the project is also a people's road for hundreds of households, always in a state of mud and soil, large trucks circulating, risk of unsafety. Photo: Viet Bac
Cac cong nhan van dang thi cong hang muc duong giao thong, mat bang. Anh: Viet Bac
Workers are constructing the outdoor items of the rows of barns. Photo: Viet Bac
Khong the khai thac nguon nuoc tai cho anh huong den tien do du an. Anh: Viet Bac
Many items and auxiliary works are unfinished. Photo: Viet Bac
Du an cham tien do gay lang phi nguon luc dat dai. Anh: Viet Bac
This land fund was previously mainly agricultural land and forest land of dozens of households, and has now been recovered to implement the project. Photo: Viet Bac
Cac trang trai chua the van hanh theo ke hoach. Anh: Viet Bac
People whose land is acquired for projects expect the cow farm to create more jobs and stable income. Photo: Viet Bac
Việt Bắc - Phùng Minh
RELATED NEWS

Morning news 20.9: Owner of illegally built cow farm fined 4 million VND

|

Morning news on September 20: Owner of illegally built cow farm fined 4 million VND; Gia Lai speeds up construction of inter-level boarding schools in 7 border communes;...

Fine 4 million VND for owner of illegally built cow farm

|

Thanh Hoa - Before the incident of the cow farm being reported by people causing pollution, the local government inspected and punished the illegal construction.

How to handle cow ranks accused of pollution by people

|

Thanh Hoa - The local government has stepped in to inspect and requested the cow farm owner to dismantle the illegal construction and restore it to its original state.

Hanoi Ring Road 3 congested for 10km on the first day of the 2026 New Year holiday

|

Hanoi - Ring Road 3 expressway is seriously congested on the first day of the 2026 New Year holiday, making people's journey back to their hometowns even more difficult.

Russia advances troops rapidly, controls 700km2 of territory from Ukraine

|

Russia announced that it would push back Ukrainian troops from the border, expand the buffer zone in Sumy and Kharkov, and control dozens of residential areas in December 2025 alone.

Stocks aim for the 2,000-point mark in 2026

|

2025 marks the most vibrant growth year in history, making Vietnam one of the most efficient stock markets in the world.

President Putin, Zelensky and world leaders congratulate New Year

|

In the moment of transition to the new year, many world leaders, including President Putin and Zelensky, sent congratulatory messages to the people.

Night literacy class for people in Vietnam - Laos border areas

|

Quang Tri - In the border area of Lia commune, literacy classes at night open up opportunities to change the lives of ethnic minorities.

Morning news 20.9: Owner of illegally built cow farm fined 4 million VND

HUYỀN TRANG - DUY HƯNG |

Morning news on September 20: Owner of illegally built cow farm fined 4 million VND; Gia Lai speeds up construction of inter-level boarding schools in 7 border communes;...

Fine 4 million VND for owner of illegally built cow farm

QUÁCH DU |

Thanh Hoa - Before the incident of the cow farm being reported by people causing pollution, the local government inspected and punished the illegal construction.

How to handle cow ranks accused of pollution by people

QUÁCH DU |

Thanh Hoa - The local government has stepped in to inspect and requested the cow farm owner to dismantle the illegal construction and restore it to its original state.