127.5 billion VND road opens the way to Ban Lien organic tea area in Lao Cai

Đinh Đại |

Lao Cai - The contractor is increasing manpower and equipment to accelerate the construction progress of provincial road 153, the section from Bac Ha commune to the center of Ban Lien commune.

Provincial road 153 section from Bac Ha commune to the center of Ban Lien commune (phase 2) is one of the key traffic projects in the 2025 - 2026 period.

The project is about 13km long, with a total investment of more than 127.5 billion VND. The road is designed to meet the standards of level V mountain roads, the roadbed and surface are 6.5m wide, and the road surface is asphalt concrete.

Đường vào từ xã Bắc Hà vào xã Bản Liền đang dần hình thành. Ảnh: Đinh Đại
The road from Bac Ha commune to Ban Lien commune is gradually taking shape. Photo: Dinh Dai

Along with that is the drainage ditch system, retaining walls, works to ensure traffic safety and handle many complex taluy positions.

Recorded at the construction site on March 10, many construction fronts are being deployed simultaneously.

The contractor has mobilized excavators, rollers, material transport vehicles and many workers to work continuously to speed up the progress of roadbed items and concrete and taluy components.

Các máy móc đang triển khai thi công mặt bằng và nền đường. Ảnh: Đinh Đại
Machinery is deploying construction of the ground and roadbed. Photo: Dinh Dai

Talking to reporters, Mr. Luong Van Kien - official of the Bac Ha Regional Construction Investment Project Management Board said that so far localities have handed over about 6.5 km of land to construction units.

On the handed-over area, the contractor is focusing on constructing the roadbed, embankments, drainage culverts and precast concrete components.
The remaining part strives to complete site clearance before March 31, 2026.

According to Mr. Kien, a part of the project passes through the protection forest area. The Bac Ha Regional Construction Investment Project Management Board has coordinated with the Lao Cai Provincial Forest Protection Department to develop a plan to recover the forest and submit it to the Provincial People's Council for consideration.

We are completing complete legal documents so that forest recovery and land allocation are carried out in accordance with regulations, avoiding affecting the overall progress of the project," Mr. Kien said.

Công nhân thi công cấu kiện bê tông. Ảnh: Đinh Đại
Workers constructing concrete components. Photo: Dinh Dai

According to the contract, the construction package will be implemented in about 600 days, from August 2025 and is expected to be completed in March 2027.

Mr. Le Hai Quang - Site Commander, Hoang Nguyen Construction Investment Co., Ltd. - said that the unit has arranged manpower and equipment ready to be reinforced as soon as the site is handed over more.

As soon as we receive the new site, we will organize more parallel construction teams, mobilize more machinery and manpower to ensure progress. This is an important project of the locality, so the unit determines to focus maximum resources to complete the commitment with the investor," Mr. Quang informed.

Song song với công tác thi công, việc giải phóng mặt bằng cũng là yếu tố quan trọng giúp đẩy nhanh tiến độ. Ảnh: Đinh Đại
In parallel with construction work, site clearance is also an important factor to accelerate progress. Photo: Dinh Dai

Also according to Mr. Quang, in the initial phase, the construction site mainly deployed weathering, excavation and embankment of the roadbed, construction of box culverts, longitudinal ditches and embankment wall positions. When the roadbed is stable, the unit will switch to asphalt concrete paving and complete the traffic safety system.

Provincial road 153 passes through many villages where the Tay, Dao, and Mong ethnic people have lived for a long time. Over the past time, commune authorities have organized people's meetings and propagated the meaning of the project to create consensus in site clearance work.

Công trình hoàn thành sẽ giúp kết nối các xã trên cao nguyên trắng Bắc Hà. Ảnh: Đinh Đại
The completed project will help connect communes on the white plateau of Bac Ha. Photo: Dinh Dai

Thanks to that, most households in the project area supported and were ready to hand over land and dismantle auxiliary works to serve construction.

When completed, the road will form an important connecting axis between Bac Ha, Ban Lien, and Ta Cu Ty communes, contributing to promoting tourism, agriculture and trade in goods, especially with the Ban Lien organic tea region.

Đinh Đại
RELATED NEWS

Sewer covers disappear en masse on a road in Hue

|

HUE - About 40 manhole covers on a road in An Cuu ward disappeared without a trace, leaving many dangerous deep holes on the road.

Lao Cai proposes a tens of trillions of VND road connecting the expressway with Y Ty

|

Lao Cai - March 3rd, Lao Cai Provincial People's Committee held a conference to consider the investment plan for the connecting road from Noi Bai - Lao Cai expressway to Y Ty Tourist Area.

Russian shadow oil fleet may be eased by US sanctions

|

As the US considers easing some restrictions on Russian oil, the Russian oil-carrying shadow fleet may be revealed.

Rice exports to the Chinese market increase sharply

|

Rice exports to the Chinese market increased 5.8 times compared to the same period last year.

Paying some collections proposed by teachers after the reflection of Lao Dong Newspaper

|

Khanh Hoa - After Lao Dong Newspaper reflected the teacher's petition to clarify some revenues and expenditures, Phuong Sai Kindergarten has paid some amounts of money.

Patients in the kidney dialysis village eagerly await the election day on March 15

|

Hanoi - Patients being treated in the "kidney dialysis hamlet" in Bach Mai ward have been propagated the Election Law and expressed their excitement to wait for the March 15th election day.

Verifying a car stopping in the middle of the road, moving abnormally causing traffic obstruction

|

Quang Tri - Functional agencies are verifying cars stopping in the middle of the road, unusually moving backwards in Dong Hoi ward.

Sewer covers disappear en masse on a road in Hue

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE - About 40 manhole covers on a road in An Cuu ward disappeared without a trace, leaving many dangerous deep holes on the road.

Lao Cai proposes a tens of trillions of VND road connecting the expressway with Y Ty

Bảo Nguyên |

Lao Cai - March 3rd, Lao Cai Provincial People's Committee held a conference to consider the investment plan for the connecting road from Noi Bai - Lao Cai expressway to Y Ty Tourist Area.

Hiện trạng tuyến đường thi công cầm chừng khiến nhà thầu bị phạt ở Lào Cai

Đinh Đại |

Lào Cai - Sau nhiều lần gia hạn, hiện trạng dự án đường vào trung tâm xã Phìn Ngan cũ vẫn chậm tiến độ, khối lượng thực hiện thấp.