Inter-regional road connecting route with National Highway 32C after half a year of construction

Tô Công |

Phu Tho - Provincial road 315 connecting National Highway 32C with the inter-regional road in Van Xuan commune is being accelerated in construction progress.

The inter-regional road project connecting Ho Chi Minh Road with National Highway 70B, National Highway 32C from Phu Tho province to Yen Bai province (now Lao Cai province) - has a total adjusted investment of 2,120 billion VND.

The project started on December 14, 2021, building a main route more than 53.5km long through old districts of Phu Tho province such as: Tam Nong, Cam Khe, Ha Hoa - with a design according to the scale of a grade III mountain road, design speed of 60 km/h.

Along with the extended inter-regional road and the branch connecting Cam Khe industrial park, more than 2km of the main route (section Km0 - Km2+452) in Van Xuan commune has also been completed.

Đoạn đầu tuyến chính đường liên vùng (Km0 - Km2+452) vừa hoàn thành. Ảnh: Tô Công
The beginning of the main inter-regional road section (Km0 - Km2+452) has just been completed. Photo: To Cong

As Lao Dong newspaper has reported, Van Xuan commune has invested 120 billion VND for the project to renovate and upgrade provincial road 315 connecting National Highway 32C with the inter-regional road.

From the end of January 2026, Package No. 07: Construction of the project has completed the contractor selection and started construction (winning bid price of more than 94.6 billion VND).

Toàn cảnh tuyến đường tỉnh 315 qua xã Vạn Xuân. Ảnh: Tô Công
Overview of provincial road 315 through Van Xuan commune. Photo: To Cong

According to reporters of Lao Dong Newspaper in mid-August, after about half a year of construction, it can be initially seen that provincial road 315 will be significantly expanded.

Currently, the contractor is mobilizing a lot of manpower and vehicles to excavate and reclaim the roadbed, the horizontal/vertical drainage system, and gather raw materials...

Nhà thầu đang thi công nền đường và hệ thống thoát nước. Ảnh: Tô Công
The contractor is constructing the roadbed and drainage system. Photo: To Cong

It can be seen that the renovated and upgraded section passes through the fields and densely populated residential areas of Lam Son commune, former Tam Nong district, through the current Van Xuan Commune People's Committee headquarters.

With a large number of vehicles circulating, especially during the initial period when the main inter-regional road section was not completed, provincial road 315 previously had many locations that were degraded: Asphalt road surface peeling off, many potholes, craters, sidewalks deformed...

Các công nhân đang thi công một công trình thoát nước ngang đường. Ảnh: Tô Công
Workers are constructing a drainage project across the road. Photo: To Cong

According to project documents, the renovated and upgraded section has a total length of 4.63km, starting point at Km22+470 provincial road 315, My Van High School location; ending point at the Km27+100 intersection of provincial road 315 connecting to the inter-regional road at Km2+460.

The road being renovated and upgraded will have a roadbed width of 15m, of which the roadbed width is 11m, including 10.5m of road surface for vehicles (asphalt concrete paved), beltway width of 0.25m on each side, sidewalk width of 2m on each side... The design speed of the route section is 40km/h.

Tuyến đường dự án đi qua trụ sở UBND xã Vạn Xuân. Ảnh: Tô Công
The project route passes through the headquarters of Van Xuan Commune People's Committee. Photo: To Cong

In addition, the bidding package will also construct sidewalk systems, lighting, drainage, intersections, curbs; synchronous traffic safety systems according to usage requirements.

According to a leader of Van Xuan Commune Public Service Center (the investor), the contractor is focusing on excavating and filling the roadbed and drainage system on the route, and so far the actual volume has reached about 40%.

The project is being constructed on schedule. The contract implementation period is 360 days, but the contractor strives to complete the project before the Lunar New Year this year" - the leader of Van Xuan Commune Public Service Center informed.

Tô Công
RELATED NEWS

Phu Tho requests evacuation of people in river and stream areas to safe places

|

Phu Tho - The Provincial People's Committee has just requested units to proactively respond to heavy rain, floods, inundation, flash floods, and landslides.

Workers look forward to inter-regional road connecting industrial parks in Phu Tho

|

Phu Tho - The inter-regional branch road shortening the distance to Cam Khe industrial park is nearing completion, causing workers and people to look forward to it.

Completion of extended inter-regional road connecting near Phong Chau bridge in Phu Tho

|

Phu Tho - The extended inter-regional road connecting National Highway 32 near Phong Chau bridge, after more than 1 year of construction, has now completed construction items.

Miracle of survival after 4 days floating at sea thanks to foam

|

Ho Chi Minh City - Thanks to the determination to live for his children, a fishing boat crew member returned safely after 4 days of drifting at sea.

Real estate businesses crave capital under credit pressure

|

Ho Chi Minh City - The story of real estate lending interest rates that are difficult to reduce is a reality that businesses have to face.

More than 600 UAVs rushed towards Moscow at night

|

More than 600 UAVs are believed to have flown towards Moscow and the surrounding area, in the largest attack aimed at the Russian capital in the past 2 years.

Live press conference for Vietnam vs Malaysia team before the ASEAN Cup 2026 semi-final second leg

|

At 11:00 today, coach Tan Cheng Hoe (Malaysia team) and Kim Sang-sik (Vietnam team) will attend a press conference before the ASEAN Cup semi-final second leg.

Phu Tho requests evacuation of people in river and stream areas to safe places

Xuyên Đông |

Phu Tho - The Provincial People's Committee has just requested units to proactively respond to heavy rain, floods, inundation, flash floods, and landslides.

Workers look forward to inter-regional road connecting industrial parks in Phu Tho

Tô Công |

Phu Tho - The inter-regional branch road shortening the distance to Cam Khe industrial park is nearing completion, causing workers and people to look forward to it.

Completion of extended inter-regional road connecting near Phong Chau bridge in Phu Tho

Tô Công |

Phu Tho - The extended inter-regional road connecting National Highway 32 near Phong Chau bridge, after more than 1 year of construction, has now completed construction items.