On March 4, units are making efforts to accelerate the construction progress of the Ring Road 3 HCMC project section passing through Binh Duong province previously.
According to the Binh Duong Traffic Works Project Management Board, Ring Road 3 of Ho Chi Minh City passing through the Binh Duong area was previously about 26.6 km long. Currently, 4 construction packages are under construction with a total length of 11.6 km, the remaining 15km section coincides with My Phuoc - Tan Van road.
In which, the progress of construction package No. 3 (section from Binh Chuan intersection to Saigon River nearly 9 km long) is being accelerated to strive to reach the finish line early. This section, phase 1, builds a scale of 4 expressway lanes and parallel roads on both sides.

This construction package has an approach section and an overpass about 2 km long across 3 routes including Nguyen Thi Minh Khai, National Highway 13 and Cach Mang Thang 8. Currently, the overpasses have taken shape, the overpass beams have been built across intersection routes, and the contractor is gradually completing the overpasses.
Notably, units are currently starting to prepare the ground for the parallel road construction with the Ring Road 3 overpass in Ho Chi Minh City. The entire ground of about 2 km of the parallel road section through the expressway overpass has been cleared. Units are leveling, making drainage culverts and excavating and filling the road surface.
The remaining section is nearly 7 km long, the contractors are embanking, compacting the roadbed, and proceeding with paving. According to the Binh Duong Traffic Works Project Management Board, construction package No. 3 started in February 2024, the construction time according to the contract is 960 days. It is expected that the overpass and road section will be completed in September 2026.