Ring Road 3 HCMC elevated section asphalt paved seamlessly, racing for traffic opening progress 30. 4

Anh Tú |

Many elevated sections of Ring Road 3 in Ho Chi Minh City have been beautifully asphalted, and contractors are focusing their efforts on completing the final part to meet the traffic opening milestone on April 30th.

To ensure the traffic opening milestone of Ring Road 3, the elevated road section in the East of Ho Chi Minh City on the occasion of April 30th, contractors at the construction site are continuously constructing day and night to complete the remaining items.

The Ring Road 3 project through Ho Chi Minh City, the section through Thu Duc City (formerly) has a length of nearly 15 km (from Ho Chi Minh City - Long Thanh expressway to Tan Van intersection), designed as an elevated road with 4 lanes. Currently, the road and bridge deck items are basically completed, and the construction site is moving to the asphalt paving phase.

Toàn cảnh đoạn tuyến Vành đai 3 kết nối với cao tốc TPHCM - Long Thành - Dầu Giây đang được tập trung thi công lớp áo đường.
Overview of the Ring Road 3 section connecting to the Ho Chi Minh City - Long Thanh - Dau Giay expressway, which is being focused on constructing the road layer. Photo: Anh Tu

To closely follow the April 30 traffic opening milestone, contractors maintain about 500 engineers, workers and machinery and equipment working continuously in 3 shifts of 4 crews.

 Các xe chuyên dụng được huy động tối đa, làm việc liên tục trên công trường để đảm bảo mốc thông xe kỹ thuật 30.4. Ảnh: Anh Tú
Specialized vehicles are mobilized to the maximum, working continuously on the construction site to ensure the technical traffic opening milestone 30. 4. Photo: Anh T

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board, to date, the entire Ring Road 3 HCMC project has reached nearly 80% of the construction volume, basically meeting the progress requirements. At the elevated Ring Road 3 section, the progress has exceeded the 80% mark, and the asphalt paving volume of the main route has basically been completed on many key sections.

  Tuyến chính Vành đai 3 đoạn đi qua khu đô thị Vinhomes Grand Park đã hoàn tất công tác thảm nhựa mặt đường. Ảnh: Anh Tú
The main road of Ring Road 3, the section passing through Vinhomes Grand Park urban area, has completed the asphalt paving of the road surface. Photo: Anh Tu
[Ảnh 4] Đoạn cầu cạn dài hàng km xuyên qua các tòa nhà cao tầng đã thảm nhựa xong, hiện công nhân đang tiến hành lắp đặt hệ thống lan can thép.
The kilometers long viaduct section through high-rise buildings has been asphalted, and workers are currently installing a steel railing system. Photo: Anh Tu
Khu vực cầu cạn đường Vành đai 3 giao với các tuyến đường trong khu đô thị Vinhomes. Ảnh: Anh Tú
The viaduct area of Ring Road 3 intersecting with roads in Vinhomes urban area. Photo: Anh Tu
 Đoạn Vành đai 3 trên cao từ chùa Bửu Long đến khu đô thị Vinhomes Grand Park đã hiện rõ toàn bộ hình hài với mặt đường được thảm nhựa kéo dài khoảng 4 km. Ảnh: Anh Tú
The elevated Ring Road 3 section from Buu Long Pagoda to Vinhomes Grand Park urban area has clearly shown its entire shape with the road surface paved with asphalt stretching about 4 km. Photo: Anh Tu
Hiện tại, chỉ còn khoảng 2 km đoạn từ cầu Đồng Tròn hướng về chùa Bửu Long đang thi công bản mặt cầu, lan can và chờ thảm nhựa.
Tan Van intersection is being accelerated in construction progress to synchronize with the opening of the entire Ring Road 3 in June. Photo: Anh Tu

Representatives of the investor said that the asphalt paving work in the past time was directly affected by erratic rainy and windy weather. In addition, the shortage of aggregate materials (stone, sand filling) due to delays in the licensing stage of mining has disrupted the roadbed construction line.

The completion of asphalt paving and opening of 14.7 km of the main elevated bridge section before April 30 is a prerequisite for the project to continue construction and complete the last 2 km section and Tan Van intersection in June 2026, aiming to complete the entire Ring Road 3 project by the end of 2026.

 Việc đẩy nhanh hạng mục thảm nhựa giúp dự án Vành đai 3 sớm về đích, kết nối 5 tuyến cao tốc và giải quyết ùn tắc cho cửa ngõ phía Đông TPHCM. Ảnh: Anh Tú
Accelerating the asphalt paving item helps the Ring Road 3 project to reach the finish line soon, connecting 5 expressways and solving congestion for the eastern gateway of Ho Chi Minh City. Photo: Anh Tu
Anh Tú
RELATED NEWS

Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

|

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Ring Road 3 of Ho Chi Minh City section passing through Binh Duong is under construction for a parallel road

|

Ho Chi Minh City - Units begin construction of the parallel road with Ring Road 3 of Ho Chi Minh City section passing through Binh Duong previously.

My Phuoc - Tan Van road expanded from 6 to 12 lanes section passing Ring Road 3 HCMC

|

Ho Chi Minh City - After more than 2.5 years of construction, the Binh Chuan intersection of the Ho Chi Minh City Ring Road 3 project has gradually taken shape, a section of My Phuoc - Tan Van road has been expanded to 12 lanes.

Hoang Xuan Vinh - Olympic imprint from key investment strategy

|

Hoang Xuan Vinh's Olympic gold medal at Rio 2016 is a typical proof of the key investment efficiency of Vietnamese sports.

Ho Chi Minh City to start construction of 4 trillion-VND projects to rescue traffic jams in the South

|

Ho Chi Minh City - Thu Thiem 4 bridge, Binh Tien road bridge, Nguyen Tat Thanh road expansion, North-South axis upgrade, started this year to help reduce traffic jams in the South of Ho Chi Minh City.

List of National Assembly deputies of the 16th term under the Committee for Culture and Social Affairs

|

In the list of 500 people elected as National Assembly deputies of the 16th term just announced by the National Election Council, there are 15 people belonging to the Culture and Social Affairs Committee of the National Assembly.

Ring Road 3 HCMC elevated section asphalt paved seamlessly, racing for traffic opening progress 30. 4

|

Many elevated sections of Ring Road 3 in Ho Chi Minh City have been beautifully asphalted, and contractors are focusing their efforts on completing the final part to meet the traffic opening milestone on April 30th.

Forcing customers to take photos at Sam Son beach, one person fined 2 million VND

|

Thanh Hoa - For soliciting and forcing customers to take photos at Sam Son beach, a woman was fined 2 million VND.

Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

MINH QUÂN |

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Ring Road 3 of Ho Chi Minh City section passing through Binh Duong is under construction for a parallel road

ĐÌNH TRỌNG |

Ho Chi Minh City - Units begin construction of the parallel road with Ring Road 3 of Ho Chi Minh City section passing through Binh Duong previously.

My Phuoc - Tan Van road expanded from 6 to 12 lanes section passing Ring Road 3 HCMC

TRỌNG QUỲNH |

Ho Chi Minh City - After more than 2.5 years of construction, the Binh Chuan intersection of the Ho Chi Minh City Ring Road 3 project has gradually taken shape, a section of My Phuoc - Tan Van road has been expanded to 12 lanes.