Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

MINH QUÂN |

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Recorded on March 9, the Tan Van intersection construction site under the Ho Chi Minh City Ring Road 3 project is being deployed simultaneously with many important items.

Concrete bridge pillars of the main route have been basically completed. Many sections have been paved with girders and concrete pavement has been poured, preparing to cross National Highway 1.

Đoạn trên cao Vành đai 3 TPHCM sắp được nối thông qua nút giao Tân Vạn.  Ảnh: Minh Quân
The elevated section of Ring Road 3 HCMC is about to be connected through Tan Van intersection. Photo: Minh Quan
Đoạn Vành đai 3 hướng về đường Mỹ Phước - Tân Vạn.  Ảnh: Minh Quân
Ring Road 3 section towards My Phuoc - Tan Van road. Photo: Minh Quan
Đoạn Vành đai 3 hướng về cao tốc TPHCM - Long Thành - Dầu Giây.  Ảnh: Minh Quân
Ring Road 3 section towards the Ho Chi Minh City - Long Thanh - Dau Giay expressway. Photo: Minh Quan

In some other locations, construction units are still installing bridge pillars, scaffolding and formwork to prepare girders for the approach bridge spans up and down the intersection.

Underneath the project, materials and equipment are gathered to serve the construction of the parallel road.

Các nhà thầu đã huy động gần 260 nhân sự cùng khoảng 90 máy móc, thiết bị để thi công nút giao Tân Vạn.  Ảnh: Minh Quân
Contractors have mobilized nearly 260 personnel and about 90 machines and equipment to construct the Tan Van intersection. Photo: Minh Quan

Tan Van intersection has a total length of about 2.4 km, with a total investment of more than 1,831 billion VND, directly connected to many important traffic routes in the East such as National Highway 1, Metro Line No. 1 (extended to Binh Duong and Dong Nai), Ring Road 3, provincial road 743 and My Phuoc - Tan Van Avenue.

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board (the investor), there are currently nearly 260 personnel and about 90 machines and equipment mobilized for construction at the construction site.

Contractors are deploying 17 simultaneous construction fronts, with the actual volume reaching about 50% of the total contract value.

Thi công trụ và kết cấu cầu vượt của tuyến Vành đai 3 bắc qua Quốc lộ 1 tại nút giao Tân Vạn. Ảnh: Minh Quân
Construction of pillars and overpass structures of Ring Road 3 across National Highway 1 at Tan Van intersection. Photo: Minh Quan

Ho Chi Minh City strives to complete and open Tan Van intersection to traffic on June 30, and put it into operation along with the entire Ring Road 3 of Ho Chi Minh City.

Previously, at the end of December 2025, the 14.7 km long elevated Ring Road 3 East section, from Tan Van intersection to Ho Chi Minh City - Long Thanh - Dau Giay expressway intersection, was technically opened to traffic and is expected to be officially put into operation on April 30, 2026.

When Tan Van intersection is completed on June 30, this area will open a new traffic direction from Ho Chi Minh City to Dong Nai. People can move from Tan Van intersection to the elevated Ring Road 3, through Nhon Trach bridge to connect with the Ben Luc - Long Thanh expressway.

This connection route is expected to contribute to reducing traffic pressure for the Ho Chi Minh City - Long Thanh - Dau Giay expressway, which is often overloaded.

Nút giao Tân Vạn vừa thi công vừa phải tổ chức phân luồng trong điều kiện lưu lượng xe qua lại dày đặc mỗi ngày, đặc biệt là xe tải và container. Ảnh: Minh Quân
Tan Van intersection is both under construction and has to organize traffic diversion in conditions of dense traffic flow every day, especially trucks and containers. Photo: Minh Quan

However, the Ho Chi Minh City Traffic Construction Investment Project Management Board said that the Tan Van intersection project still faces some difficulties.

In the main high-voltage bridge abutment area, there is still a high-voltage power pole and a medium-voltage underground power system at pier P8A that have not been relocated, affecting the construction progress.

In addition, the organization of traffic diversion also faces many obstacles because this area has a large volume of vehicles entering and leaving warehouses and ports, and congestion often occurs.

The scarcity of materials has caused prices of stone, crushed stone, cement concrete and transportation costs to increase.

One unit in the contractor consortium has not met the construction progress of the parallel road, causing a lack of land to deploy the existing National Highway 1 overpass.

Nút giao Tân Vạn sẽ thông xe ngày 30.6.  Ảnh: Minh Quân
Tan Van intersection will open to traffic on June 30. Photo: Minh Quan
Phối cảnh nút giao Tân Vạn khi hoàn thành.  Ảnh: Ban Giao thông TPHCM
Perspective of Tan Van intersection when completed. Photo: Ho Chi Minh City Traffic Department

On March 9, Minister of Construction Tran Hong Minh directly inspected the construction progress at Tan Van intersection.

Bộ trưởng Bộ Xây dựng Trần Hồng Minh (bìa phải) kiểm tra nút giao Tân Vạn.  Ảnh: Minh Quân
Minister of Construction Tran Hong Minh (right cover) inspects Tan Van intersection. Photo: Minh Quan

Mr. Tran Hong Minh requested units to continue to focus maximum manpower, equipment and resources, organize scientific construction to accelerate the progress of the remaining items, strive to close and complete the entire intersection by June 30 to ensure synchronous connection.

The Minister of Construction also rectified some contractors whose implementation is still slow, requesting urgent remediation, strengthening human resources and machinery to avoid affecting the overall progress of the project.

MINH QUÂN
RELATED NEWS

Ring Road 3 through Ho Chi Minh City, Dong Nai, Tay Ninh proposed to be expanded to 8 expressway lanes

|

Ho Chi Minh City - Ring Road 3 of Ho Chi Minh City connecting Ho Chi Minh City, Dong Nai and Tay Ninh, proposed to be expanded from 4 to 8 expressway lanes, with a total capital of about 60,000 billion VND.

Workers are busy constructing Tan Van intersection, speeding up the progress of Ring Road 3

|

HCMC - The largest scale of the Tan Van intersection of the Ho Chi Minh City Ring Road 3 project is under urgent construction, striving to complete by 2026.

Tan Van intersection is seriously congested, Ho Chi Minh City offers urgent solutions

|

HCMC - The closure of Provincial Road 743 to construct Tan Van intersection under the Ring Road 3 project caused serious congestion, forcing HCMC to adjust the plan to reduce traffic congestion.

16th National Assembly deputies candidates meet with voters in Bac Ninh

|

Candidates for National Assembly Deputies of the 16th term meet with voters at constituency No. 3, Bac Ninh province.

Prime Minister directs the planning and investment attraction of Lai Chau airport

|

The Prime Minister requested to review and study adjusting the planning of Lai Chau airport to suit the general development of the country.

Thanh Hoa Department of Education and Training concludes the case of teachers of To Hien Thanh High School correcting scores

|

Thanh Hoa - The Department of Education and Training (GDĐT) of the province has the results of inspection and verification of the case of amending semester exam scores that occurred at To Hien Thanh High School.

Stormy sea, voters in island communes in Gia Lai send petitions through screens

|

Gia Lai - Stormy sea, voter meeting at Nhon Chau island commune must be organized online. Through the screen, voters raised recommendations on infrastructure, environment, and livelihoods.

Ukraine loses 1,255 soldiers in 1 day

|

Ukrainian forces have lost about 1,255 soldiers in the special military operation area on March 8.

Ring Road 3 through Ho Chi Minh City, Dong Nai, Tay Ninh proposed to be expanded to 8 expressway lanes

MINH QUÂN |

Ho Chi Minh City - Ring Road 3 of Ho Chi Minh City connecting Ho Chi Minh City, Dong Nai and Tay Ninh, proposed to be expanded from 4 to 8 expressway lanes, with a total capital of about 60,000 billion VND.

Workers are busy constructing Tan Van intersection, speeding up the progress of Ring Road 3

NHƯ QUỲNH - ANH TÚ |

HCMC - The largest scale of the Tan Van intersection of the Ho Chi Minh City Ring Road 3 project is under urgent construction, striving to complete by 2026.

Tan Van intersection is seriously congested, Ho Chi Minh City offers urgent solutions

MINH QUÂN |

HCMC - The closure of Provincial Road 743 to construct Tan Van intersection under the Ring Road 3 project caused serious congestion, forcing HCMC to adjust the plan to reduce traffic congestion.