HCMC - The Chairman of the HCMC People's Committee directed the establishment of an investigation team for the crane collapse incident at the My Thuy intersection project (Thu Duc City).

The Ho Chi Minh City People's Committee has just issued an urgent document, directing the Department of Construction and the Ho Chi Minh City Traffic Construction Investment Project Management Board regarding the crane collapse incident that occurred at the My Thuy intersection construction site, Cat Lai - Thach My Loi ward, Thu Duc city.

Previously, at around 1:00 p.m. on May 31, while workers were using a chain-wheeled crane to lift concrete blocks to serve the pilling pressing work behind the M2 abutment - part of the overpass construction package on Ring Road 2 (right branch, phase 3 of the My Thuy intersection project) - a concrete block suddenly tilted and slid from its position. The incident caused the cable to be pulled off, leading to imbalance and the crane overturned.

The crane cranes cross the existing left overpass, hitting the cabin of a container truck and a 7-seat car traveling below. The collision caused the container truck's cabin to be distorted, the 7-seat car to be slightly damaged, and a section of the overpass railing to be warped. Fortunately, no one was injured in the incident.

Hai oto hu hong sau su co sap can cau ngay 31.5. Anh: Giang Anh
Two cars were damaged after the crane collapse on May 31. Photo: Giang Anh

The Chairman of the Ho Chi Minh City People's Committee requested the Department of Construction to preside over and coordinate with relevant units to establish an Incident Investigation Team including representatives of specialized construction agencies, relevant agencies and appropriate technical experts. If necessary, the Investigation Team can invite a consultation organization to determine the cause and propose solutions according to regulations.

The investigation of incidents related to machinery and equipment will be conducted according to the provisions of Clause 3, Article 50 of Decree No. 06/2021/ND-CP of the Government, with the contents to be implemented including:

Check the site, check the declaration, and resolve the incident of the investor and construction contractors in accordance with regulations.

Consider and decide on stopping or temporarily suspending the use of machinery and equipment; stopping or temporarily suspending construction of items, parts or the entire project depending on the level of impact of the incident.

Consider deciding to demolish and clear the scene, ensuring safety for people, property and neighboring structures. Before clearing, the relevant parties must be responsible for filming, taking photos and collecting sufficient evidence of the scene to prepare documents.

Advised the Ho Chi Minh City People's Committee to issue a Notice of Investigation Results on the Causes of the Incident to the Investor and related parties. Relevant units are responsible for organizing the remediation of consequences in accordance with regulations.

Handling the responsibilities of relevant parties according to the law. In cases beyond their authority, it is necessary to advise the Ho Chi Minh City People's Committee on a handling plan in accordance with regulations.

In addition, the Ho Chi Minh City People's Committee assigned the Traffic Construction Investment Project Management Board to urgently declare and resolve the incident according to regulations.

The Traffic Department is also required to proactively coordinate and fully implement the requests of the Investigation Team to serve the determination of causes and propose remedies, ensuring project implementation progress according to plan.

The My Thuy intersection project started construction in 2016, including two component projects: Construction and installation with a cost of VND 1,826 billion and compensation and site clearance with more than VND 1,623 billion.

After nearly a decade of construction, the entire project has only reached about 30% of the volume, and has completed a number of bridges and underpasses. The entire project is expected to be completed in April 2026.

MINH QUÂN
RELATED NEWS

Reasons for the crane crashing into a car at My Thuy intersection in Ho Chi Minh City

|

HCMC - On the evening of May 31, the Traffic Construction Investment Project Management Board reported on the incident of a crane collapsing at My Thuy intersection, crushing 2 cars.

Construction crane collapsed, crushing a moving vehicle in Thu Duc City

|

HCMC - A crane in a construction project suddenly collapsed in the My Thuy bridge area, hitting a container truck and a car in circulation, causing traffic congestion.

The 3,400 billion VND intersection in Ho Chi Minh City has been under construction for 9 years but is still stuck with site clearance

|

HCMC - After nearly 9 years of construction, the My Thuy intersection project worth more than VND3,400 billion is still sluggish due to land clearance problems, with 61 households not yet handed over.

Live volleyball VTV Binh Dien Long An vs Hoa Chat Duc Giang Lao Cai

|

Live match between VTV Binh Dien Long An and Hoa Chat Duc Giang Lao Cai at the 2026 National Volleyball Championship, taking place at 12:00 PM today (April 13).

Recall of grade 3 textbooks containing unsafe links in Hue

|

HUE - Hue University Publishing House recalls "Informatics Worksheet 3" containing unsafe links, stops issuing, refunds and coordinates with functional agencies for handling.

There is no "safe zone" for the leader if leadership is relaxed

|

Head of the Central Propaganda and Mass Mobilization Commission Trinh Van Quyet clearly stated that there is no "safe zone" for the head if leadership is relaxed.

Piloting the delegation of power from higher levels to the Party Committee of grassroots Party committees directly under communes and wards

|

Regulation No. 20-QD/TW has supplemented the regulation on piloting the delegation of powers from higher levels to the Party committees of grassroots Party committees directly under the Party committees of communes, wards, and special zones.

Hanoi police inform about a house fire at night, many people trapped

|

Hanoi - A 6-story house fire in Hong Ha late at night, 5 trapped people were promptly rescued safely by the Fire and Rescue Force.

Reasons for the crane crashing into a car at My Thuy intersection in Ho Chi Minh City

Anh Tú |

HCMC - On the evening of May 31, the Traffic Construction Investment Project Management Board reported on the incident of a crane collapsing at My Thuy intersection, crushing 2 cars.

Construction crane collapsed, crushing a moving vehicle in Thu Duc City

Anh Tú |

HCMC - A crane in a construction project suddenly collapsed in the My Thuy bridge area, hitting a container truck and a car in circulation, causing traffic congestion.

The 3,400 billion VND intersection in Ho Chi Minh City has been under construction for 9 years but is still stuck with site clearance

MINH QUÂN |

HCMC - After nearly 9 years of construction, the My Thuy intersection project worth more than VND3,400 billion is still sluggish due to land clearance problems, with 61 households not yet handed over.