The 3,400 billion VND intersection in Ho Chi Minh City has been under construction for 9 years but is still stuck with site clearance

MINH QUÂN |

HCMC - After nearly 9 years of construction, the My Thuy intersection project worth more than VND3,400 billion is still sluggish due to land clearance problems, with 61 households not yet handed over.

The My Thuy intersection project is a strategic intersection at the gateway to Cat Lai, Thu Duc City - where the density of freight transport vehicles is the highest in Ho Chi Minh City.

The project officially started in 2016, including two component projects: Construction with a cost of 1,826 billion VND and compensation and site clearance with more than 1,623 billion VND.

However, after nearly a decade of construction, the entire project has only reached about 30% of the volume. Some completed items include: Ky Ha 3 bridge, overpass on Ring Road 2, left underpass from Ring Road 2 to Cat Lai and My Thuy 3 bridge.

However, most of the remaining packages are stalled or are being constructed slowly due to lack of land.

The construction package of branches on the left bank of My Thuy canal is currently suspended, only reaching 15% of the volume. The My Thuy canal right bank branch road package has been 50% completed but has been forced to stop because the site has not been handed over to the public.

The construction package for Ky Ha 4 bridge and the branch from Phu My bridge to Cat Lai has started since April 2024 but is still stopped after completing part of the bridge foundation, due to lack of land for the remaining part.

Cau Ky Ha 4 dang tam ngung thi cong vi thieu mat bang. Ảnh: Anh Tu
Ky Ha 4 Bridge is temporarily suspended due to lack of land. Photo: Anh Tu

Some packages starting construction in 2025, such as the left turn overpass from Cat Lai to Phu My bridge ( begun on January 18), Ky Ha 3 bridge (right branch) and the overpass on Ring Road 2 (right branch) both started construction on March 14, are under construction of bored piles and bridge foundations, but the progress is also threatened if site clearance continues to be delayed.

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board), the construction progress is currently heavily dependent on site clearance, which is the responsibility of the Thu Duc City People's Committee.

Component project 2 - compensation and site clearance has been implemented by Thu Duc City since 2016, with a total capital of about 1,190 billion VND.

By the end of April 2025, only 134/195 cases had their site handed over, accounting for about 69%.

Nhieu can nha chua ban giao thi cong nut giao My Thuy. Anh: Anh Tu
Many houses have not been handed over for construction at My Thuy intersection. Photo: Anh Tu

The Traffic Department recommends that Thu Duc City People's Committee urgently hand over the entire remaining site before May 30, 2025, to ensure the goal of completing the entire project by April 2026.

The Thu Duc City People's Committee said that the main reason for the delay was land disputes, border encroachments, complaints, administrative litigations or people had not agreed because they had not been arranged a suitable resettlement plot.

Thu Duc City said it is removing obstacles to complete compensation and site clearance in the second quarter of this year.

MINH QUÂN
TIN LIÊN QUAN

HCMC finalizes the opening of the 341 billion VND underpass at An Phu intersection after many delays

|

HCMC - The 341 billion VND underpass at An Phu intersection (Thu Duc City) will be moved to June 30, 2025, after not being completed in time for the April 30 holiday.

HCMC widens road to 30m, relieves traffic jams in Thu Duc

|

HCMC - Nguyen Thi Dinh Street (from Giong Ong To Bridge to My Thuy Bridge) was expanded from 7 - 8m to 30m, with a total investment of about 2,075 billion VND.

HCMC is about to start construction of a 14,000 billion VND road, 6 lanes to rescue traffic jams in Thu Duc

|

HCMC - The two sections of Ring Road 2 through Thu Duc City are over 6km long, with 6 lanes, and phase 1 will have a total investment of nearly VND14,000 billion. The first package will start on April 19.

Verifying information on social networks "accusing" a system of distributing dirty meat tea

|

Soc Trang - Soc Trang Police are verifying information about the dirty meat distribution system, causing concerns about food safety.

Coastal ghost ship in Ninh Thuan will be demolished before being salvaged

|

Ninh Thuan - The Ninh Thuan coastal spaceship is currently planned to be demolished before being salvaged.

missing fisherman in Quang Binh leaves behind 3 fishermen in the coastal village

|

Quang Binh - Mr. Pham The Nhan, the main breadwinner of a family of 3 young children, went missing in the middle of the sea, leaving many people heartbroken and searching for him.

6 new points in the 2025 high school graduation exam

|

HCMC - According to the regulations for the 2025 high school graduation exam, this year's exam will have 6 new points.

Lao Dong Newspaper and Law Protection Newspaper sign a communication cooperation agreement

|

This morning (May 30), a signing ceremony for a communication cooperation agreement between Lao Dong Newspaper and Law Protection Newspaper took place in Hanoi.

HCMC finalizes the opening of the 341 billion VND underpass at An Phu intersection after many delays

MINH QUÂN |

HCMC - The 341 billion VND underpass at An Phu intersection (Thu Duc City) will be moved to June 30, 2025, after not being completed in time for the April 30 holiday.

HCMC widens road to 30m, relieves traffic jams in Thu Duc

MINH QUÂN |

HCMC - Nguyen Thi Dinh Street (from Giong Ong To Bridge to My Thuy Bridge) was expanded from 7 - 8m to 30m, with a total investment of about 2,075 billion VND.

HCMC is about to start construction of a 14,000 billion VND road, 6 lanes to rescue traffic jams in Thu Duc

MINH QUÂN |

HCMC - The two sections of Ring Road 2 through Thu Duc City are over 6km long, with 6 lanes, and phase 1 will have a total investment of nearly VND14,000 billion. The first package will start on April 19.