Entangled" with 2 households, nearly 1,500 billion VND project to expand the southern gateway cannot reach the finish line

BẢO TÚ |

Ho Chi Minh City - With a total capital of nearly 1,500 billion VND, the National Highway 50 expansion project is currently 95% on schedule. The investor is focusing efforts on removing site obstacles to open traffic.

The project to upgrade and expand National Highway 50 has a total investment of 1,498 billion VND. The project includes the construction of a parallel route more than 4 km long and the expansion of the existing National Highway 50 nearly 3 km long. When completed, the entire route will have a width of 34m with 6 lanes, forming a spacious arterial axis at the southern gateway of Ho Chi Minh City.

Although it was expected to be completed by the end of 2025, due to problems in site clearance, the project currently reaches about 95% of the volume.

 Dự án Quốc lộ 50 đạt mốc 95% tiến độ, các hạng mục chính đã thành hình, Ảnh: Anh Tú
National Highway 50 project reaches 95% progress, main items have taken shape. Photo: Anh Tu
Tuyến đường song hành quốc lộ 50 có 6 làn xe, mặt đường rộng, bằng phẳng, phương tiện lưu thông thuận lợi. Ảnh: Anh Tú
The parallel road of National Highway 50 has 6 lanes, the road surface is wide, flat, and vehicle traffic is convenient. Photo: Anh Tu

According to actual observations, the parallel section stretching 4.4 km connecting from Nguyen Van Linh street to old National Highway 50 has now been completely completed. Assessing the effectiveness of the new road axis, many people living around the area said that the congestion situation on old National Highway 50 has clearly decreased. Especially during rush hour or holidays, Tet, when the number of vehicles from the Mekong Delta provinces pouring in increases sharply, vehicles traveling on the new route are very easy, people no longer have to endure the scene of moving little by little like in previous years.

In the project to upgrade 2.6 km of existing National Highway 50 (calculated from the intersection with the parallel road to the Long An border), the working atmosphere is currently very urgent. The contractor is diligently handling the final parts such as paving the road surface, installing traffic signs and medians.

  Đơn vị thi công đang tập trung hoàn thiện. Ảnh: Anh Tú
The construction unit is focusing on completing. Photo: Anh Tu

Next to it, Ong Thin bridge across the Can Giuoc River - one of the key items of the project - has also completed the main span section. The team of workers is focusing on building access roads to both ends of the bridge, completing the road surface and installing protective railings.

Đối với cầu Ông Thìn - hạng mục quan trọng bắc qua sông Cần Giuộc hiện đã cơ bản hoàn thành phần cầu chính
For Ong Thin bridge, the important item has basically completed the main bridge section. Photo: Anh Tu

However, a major obstacle on the entire route is the "bottleneck" section extending about 500m right at the connection point with the Ben Luc - Long Thanh expressway access road. This section is suddenly narrowed due to lack of synchronous construction. The Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) informed that this scope belongs to another independent project. The Board has developed an investment policy and is waiting for approval from the City People's Committee to soon deploy it to ensure continuity.

Nút thắt “cổ chai” dài 500m tại khu vực kết nối cao tốc Bến Lức - Long Thành chưa được thi công đồng bộ.
The 500m long "bottleneck" at the Ben Luc - Long Thanh expressway connection area has not been synchronously constructed. Photo: Anh Tu

In addition, inter-regional connectivity infrastructure is still not truly synchronized when the connecting section of National Highway 50 located in Tay Ninh province is still quite narrow. The road surface in many sections is only 2 lanes in scale, limiting the overall traffic capacity.

Điểm giao quốc lộ 50 giữa TPHCM (trái) và Tây Ninh (Ảnh: An Huy).
National Highway 50 intersection between Ho Chi Minh City (left) and Tay Ninh. Photo: Anh Tu

Explaining why the entire project cannot be completed, the investor representative pointed out that the biggest barrier lies in the site clearance stage, because there are still 2 households that do not agree with the complaint resolution results. In the upcoming plan, the Traffic Board said that it will focus on coordinating with relevant parties to remove site difficulties, setting a goal to technically open the entire road axis before June 30 and accept the project completion in 2026.

The comprehensive clearing of the arterial route National Highway 50 is not simply to eliminate traffic jams and shorten travel time. This is also an important lever to exploit urban development potential, promote logistics networks and economic trade for the entire southern gateway area of Ho Chi Minh City.

BẢO TÚ
RELATED NEWS

HCMC expands Nguyen Tat Thanh Street to rescue traffic jams at the southern gateway

|

HCMC - Nguyen Tat Thanh Street, a vital traffic axis connecting the South and the center of HCMC, will be expanded towards Khanh Hoi Port to reduce traffic congestion.

HCMC builds 5 major intersections to remove traffic congestion at the southern gateway

|

Ho Chi Minh City is about to build Binh Thuan, Kinh Duong Vuong - National Highway 1 intersections, Nguyen Van Linh - Nguyen Huu Tho and three intersections connecting to Ben Luc - Long Thanh Expressway.

HCMC last week: The southern gateway is about to build a series of overpasses and underpasses to reduce congestion

|

HCMC - The southern gateway of HCMC is about to build a series of overpasses and underpasses; The HCMC Department of Construction has a new director after 3 months of merger,...

After nearly 3 years of construction, the 1,500 billion VND project to expand the southern gateway of Ho Chi Minh City is gradually reaching the finish line

|

HCMC - After nearly 3 years of construction, the National Highway 50 expansion project with a total capital of VND1,498 billion has reached 70% of the volume, expected to open to traffic the entire route by the end of this year.

Midfielder Hoang Hen: Vegetarian diet helps me recover my physical condition

|

Midfielder Hoang Hen shared that he did not encounter any obstacles in the training and competition process when maintaining a vegetarian diet.

Handling the pollution situation on the Nhat Le River after the reflection of Lao Dong Newspaper

|

Quang Tri - The situation of garbage accumulation along the Nhat Le River, causing a messy landscape and affecting the environment, has been handled after the reflection of Lao Dong Newspaper.

Developing electric vehicle charging station infrastructure in apartment buildings, towards green transformation

|

To meet the trend of green transportation, it is necessary to soon complete technical standards and develop electric vehicle charging station infrastructure in apartment buildings.

Ho Chi Minh City to deploy 5 major projects to rescue traffic jams in the East

|

Ho Chi Minh City is about to expand National Highway 13, the road connecting Hanoi Highway - Ring Road 3, Cat Lai - Phu Huu inter-port road, expand Nguyen Thi Dinh road, and upgrade Hanoi Highway.

HCMC expands Nguyen Tat Thanh Street to rescue traffic jams at the southern gateway

MINH QUÂN |

HCMC - Nguyen Tat Thanh Street, a vital traffic axis connecting the South and the center of HCMC, will be expanded towards Khanh Hoi Port to reduce traffic congestion.

HCMC builds 5 major intersections to remove traffic congestion at the southern gateway

MINH QUÂN |

Ho Chi Minh City is about to build Binh Thuan, Kinh Duong Vuong - National Highway 1 intersections, Nguyen Van Linh - Nguyen Huu Tho and three intersections connecting to Ben Luc - Long Thanh Expressway.

HCMC last week: The southern gateway is about to build a series of overpasses and underpasses to reduce congestion

Nguyên Chân |

HCMC - The southern gateway of HCMC is about to build a series of overpasses and underpasses; The HCMC Department of Construction has a new director after 3 months of merger,...

After nearly 3 years of construction, the 1,500 billion VND project to expand the southern gateway of Ho Chi Minh City is gradually reaching the finish line

Anh Tú |

HCMC - After nearly 3 years of construction, the National Highway 50 expansion project with a total capital of VND1,498 billion has reached 70% of the volume, expected to open to traffic the entire route by the end of this year.