Encountering site clearance, many projects in the highlands of Lao Cai cannot "open the way

Đinh Đại |

Lao Cai - Local authorities are mobilizing people to gradually remove site bottlenecks to ensure project progress.

According to records at the end of August, Bao Nhai commune is implementing many infrastructure, transportation and people's livelihood projects.

New roads, residential areas, and schools are expected to improve travel and living conditions and create more development momentum for the highland area.

However, in some projects, site clearance (GPMB) has not been completed, affecting the progress of implementation.

Dự án Hạ tầng kỹ thuật khu dân cư thôn Nậm Đét đang được triển khai, song còn 4 hộ chưa hoàn tất bàn giao mặt bằng. Ảnh: Đinh Đại
The Nam Det residential area technical infrastructure project is being implemented, but 4 households have not yet completed the handover of land. Photo: Dinh Dai

At the Nam Det residential area technical infrastructure project, 45 households were affected with an area of more than 31,700m2. The project has a total investment of 16 billion VND, and the approved site clearance cost is more than 5.29 billion VND.

By July 2026, 41 households had handed over the land, and 4 households had not completed it. Among them, 2 households did not agree to receive compensation and support money because they believed the unit price was low; 2 households had not coordinated to declare and count 6 graves.

Moving graves is also related to the customs of the Dao people. Some households do not agree because they believe that the deceased are only buried once and not moved to another location.

Tuyến liên xã Bảo Nhai - Cốc Ly được đầu tư hơn 46 tỉ đồng nhưng còn vướng mặt bằng tại một số vị trí. Ảnh: Đinh Đại
Bao Nhai - Coc Ly inter-communal road (Lao Cai) is still facing site clearance issues in some locations. Photo: Dinh Dai

The locality has coordinated with the Bac Ha Regional Project Management Board to organize 4 working sessions, dialogues, and propaganda to mobilize households to remove obstacles.

The Bao Nhai - Coc Ly inter-communal route is also facing difficulties in terms of land. The project has a total investment of 46.1 billion VND, and is expected to recover about 14ha from 169 households and 2 organizations.

Some areas have been used stably by people to live, but land use right certificates show that it is production forest land. When applying compensation prices, the large difference makes some households disagree.

In Nam Khap Ngoai village residential area, the project is expected to recover about 19.17ha of 110 households and 2 organizations.

Địa phương tăng cường tuyên truyền, vận động người dân nhằm tháo gỡ các điểm nghẽn trong giải phóng mặt bằng. Ảnh: Đinh Đại
Localities strengthen propaganda and mobilize people to remove bottlenecks in site clearance. Photo: Dinh Dai

Currently, 54 households are still facing problems because the land clearance map identifies some areas as unused flat land managed by the Commune People's Committee, while people believe they have used it stably before.

The project to renovate and upgrade provincial road 154, Ta Thang - Coc Ly intersection, has a total investment of 60 billion VND, and site clearance costs of more than 8.8 billion VND.

Phase 1 is expected to recover about 7.6ha from 61 households; currently counting trees, crops and assets on land.

According to Bao Nhai Commune People's Committee, the obstacle of land use right certificates not being consistent with the current situation is one of the reasons why site clearance work is prolonged.

The locality proposed solutions for certificates issued from 2005 based on aviation photos, because the data at that time was not highly accurate.

Những tuyến đường, trường học mới được kỳ vọng cải thiện hạ tầng, tạo thêm động lực phát triển cho vùng cao Bảo Nhai khi hoàn thành. Ảnh: Đinh Đại
New roads and schools are expected to improve infrastructure, creating more development momentum for the Bao Nhai highlands when completed. Photo: Dinh Dai

Talking to reporters, Mr. Tran Manh Cuong - Head of the Economic Department of Bao Nhai commune said that the biggest difficulty in site clearance work today is the issue of compensation unit prices. Some people believe that the price is still low, so high consensus has not been reached.

According to Mr. Cuong, in the coming time, the commune will coordinate with departments, branches, and mass organizations to strengthen propaganda and mobilize people, and at the same time clearly explain the mechanisms, policies and compensation unit prices approved by the province.

For cases that still have problems, the commune continues to coordinate with relevant units to organize dialogues and mobilize each household, thereby creating consensus in the implementation process.

Đinh Đại
RELATED NEWS

The 235 billion VND project will eliminate traffic bottlenecks at the beginning of Phong Chau bridge

|

Phu Tho - National Highway 32 section from Phong Chau bridge to inter-regional road (Km76+150 - Km81+380) through Van Xuan commune is preparing to be upgraded and expanded.

Lao Cai establishes Research Committee to find solutions to bottlenecks

|

Lao Cai - The establishment of the Research Board aims to provide in-depth advice on mechanisms, policies, strategic issues and development bottlenecks of the province.

Lao Cai reviews mineral projects, thoroughly resolves bottlenecks

|

Lao Cai - Faced with the risk of many factories lacking raw materials and operating at a standstill, the Provincial People's Committee requests departments and sectors to focus on removing obstacles.

25 officials of the old Song Hong School recognized as civil servants

|

Phu Tho - The Principal of Phu Tho Vocational College has just signed a decision recognizing 25 people of the old Song Hong School who passed the civil servant recruitment exam after the merger.

Hanoi, Ho Chi Minh City and 8 tourist destinations weather forecast from now until September 2nd

|

Northern tourist destinations need to be wary of thunderstorms from the night of August 30 to August 31; from September 1 - 2, good weather, sunny days.

The 235 billion VND project will eliminate traffic bottlenecks at the beginning of Phong Chau bridge

Tô Công |

Phu Tho - National Highway 32 section from Phong Chau bridge to inter-regional road (Km76+150 - Km81+380) through Van Xuan commune is preparing to be upgraded and expanded.

Lao Cai establishes Research Committee to find solutions to bottlenecks

Theo cổng thông tin Lào Cai |

Lao Cai - The establishment of the Research Board aims to provide in-depth advice on mechanisms, policies, strategic issues and development bottlenecks of the province.

Lao Cai reviews mineral projects, thoroughly resolves bottlenecks

Thanh Thủy |

Lao Cai - Faced with the risk of many factories lacking raw materials and operating at a standstill, the Provincial People's Committee requests departments and sectors to focus on removing obstacles.