Building a 22km pipeline to supply fuel to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai – The underground pipeline supplying Jet A-1 fuel from the upstream warehouse of Go Dau port to Long Thanh airport is about 22 km long.

On November 7, Dong Nai Provincial People's Committee held a working session on planning the underground pipeline supplying fuel from the upstream warehouse of Go Dau port to Long Thanh airport (Long Thanh district).

According to the planning, the Jet A-1 underground pipeline is about 22km long, consisting of 9 sections with 2 steel pipes placed in parallel, 0.5m apart.

The depth of buried pipe is 2m from the existing cross-section.

Of the total length of the underground pipeline, 16km runs outside the boundary of Long Thanh airport and 6km runs within the airport construction area.

Ong Vo Tan Duc - Chu tich UBND tinh Dong Nai phat bieu tai buoi lam viec. Anh: HAC
Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee spoke at the meeting. Photo: HAC

Speaking at the meeting, Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee said that Long Thanh Airport Phase 1 is expected to be put into operation in September 2026. Therefore, the construction of an underground pipeline to supply fuel for airport operations is very urgent.

Currently, comparing the underground pipeline construction planning with the land use planning of Long Thanh district until 2030, there are some locations on the route that are being planned for rural residential land and commercial service land.

Therefore, Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee requested Long Thanh District People's Committee and Department of Natural Resources and Environment to guide the consulting unit and the project proposal unit, PetroVietnam Oil Joint Stock Corporation (PVOil), to adjust the land use planning to ensure strictness and conformity with all types of planning to facilitate land recovery and site clearance.

The Department of Construction presides over and coordinates with the People's Committee of Long Thanh district to guide the consulting unit to review and adjust the pipeline construction plan to match the general planning of Long An commune, Tan Hiep commune, Long Phuoc commune, Phuoc Thai commune in Long Thanh district and the detailed planning of Go Dau Industrial Park.

After the route plan is adjusted to suit the planning, the Department of Construction will synthesize and advise the Dong Nai Provincial People's Committee to consult with specialized units of the Ministry of Transport and Airports Corporation of Vietnam (ACV) on the implementation policy.

This content needs to be completed soon in November 2024, to be submitted to the Provincial People's Council for consideration and approval at the end of 2024 session.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Training high quality human resources for Long Thanh airport

|

Dong Nai – Head of the Central Propaganda Department Nguyen Trong Nghia proposed focusing on training high-quality human resources to serve the Long Thanh airport project.

Construction of 119 billion VND project to supply electricity to Long Thanh airport

|

Dong Nai Power Company Limited is implementing the Long Thanh airport 110kV station project and connecting line, which will be accepted and energized in November 2024.

Building a fence for Long Thanh airport with a scope of 5,000 hectares

|

Dong Nai - On November 3, Vietnam Airports Corporation (ACV) announced that it had started construction of the 5,000-hectare fence of Long Thanh airport (package 2.10).

Seminar "Improving the operational efficiency of state-owned enterprises commensurate with resources"

|

Seminar "Improving the operational efficiency of state-owned enterprises commensurate with resources" organized by Lao Dong Newspaper in collaboration with the State Audit.

Continued shocking drop, gold ring price plummets to bottom

|

Along with the downward trend of the world market, domestic gold is falling sharply. The price of plain gold rings has lost the 84 million VND/tael mark.

Clarifying the responsibility of the Da Nang Dam Management Board for causing flooding in people's houses

|

The management board of the Nam My Dam (Da Nang City) did not communicate or inform the authorities to evacuate neighboring households when floodwaters came.

Forecasting the development of wars when Mr. Trump takes power

|

Donald Trump's return to power could profoundly change the course of wars in the Middle East and Europe.

Building a 22km pipeline to supply fuel to Long Thanh airport

|

Dong Nai – The underground pipeline supplying Jet A-1 fuel from the upstream warehouse of Go Dau port to Long Thanh airport is about 22 km long.

Training high quality human resources for Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai – Head of the Central Propaganda Department Nguyen Trong Nghia proposed focusing on training high-quality human resources to serve the Long Thanh airport project.

Construction of 119 billion VND project to supply electricity to Long Thanh airport

NHƯ QUỲNH - HÀ ANH CHIẾN |

Dong Nai Power Company Limited is implementing the Long Thanh airport 110kV station project and connecting line, which will be accepted and energized in November 2024.

Building a fence for Long Thanh airport with a scope of 5,000 hectares

HÀ ANH CHIẾN |

Dong Nai - On November 3, Vietnam Airports Corporation (ACV) announced that it had started construction of the 5,000-hectare fence of Long Thanh airport (package 2.10).