Building a fence for Long Thanh airport with a scope of 5,000 hectares

HÀ ANH CHIẾN |

Dong Nai - On November 3, Vietnam Airports Corporation (ACV) announced that it had started construction of the 5,000-hectare fence of Long Thanh airport (package 2.10).

ACV said it started construction of the fence project on October 25, 2024, with a construction period of 360 days to complete on October 25, 2025.

Currently, construction units are urgently deploying the work of gathering materials, equipment and camps to carry out construction according to the contract schedule.

Previously, the fence within the 1,810 ha area of ​​phase 1 of Long Thanh airport (package 2.4) was 100% completed with a length of 7,856 m.

Up to now, in clearing the 5,000-hectare fence of Long Thanh airport, ACV has received 21.78/21.89 km (99.5%), the remaining 100 m (0.05%) has not been handed over.

UBND huyen Long Thanh canh bao nghiem cam hanh vi lan chiem khu vuc san bay Long Thanh. Anh: HAC
Long Thanh District People's Committee warns against encroachment on Long Thanh airport area. Photo: HAC

Dong Nai Provincial People's Committee has proposed to soon complete the construction of protective fences for the entire 5,000-hectare area of ​​Long Thanh airport project.

The solution is to build a fence around the Long Thanh airport project to prevent re-encroachment after clearing the land.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Survey of North-South high-speed railway at Long Thanh airport

|

Dong Nai - The National Assembly's Economic Committee surveyed the investment location for the construction of a high-speed railway on the North-South axis at the Long Thanh airport project site.

Investing 1,400 billion VND in road connecting the North of Long Thanh airport

|

Dong Nai Provincial People's Committee is completing procedures to invest in a road worth more than VND1,400 billion connecting the northern area of ​​Long Thanh airport.

6,200 billion VND road expansion next to Long Thanh airport

|

Dong Nai – DT 769 road, 30km long, located next to Long Thanh airport and passing through Long Thanh - Thong Nhat districts, will be upgraded and expanded.

Construction of 119 billion VND project to supply electricity to Long Thanh airport

|

Dong Nai Power Company Limited is implementing the Long Thanh airport 110kV station project and connecting line, which will be accepted and energized in November 2024.

Image of Truong My Lan at the first phase of the appeal trial

|

HCMC - Truong My Lan and other defendants appeared in court for the appeal trial (phase 1) at the HCMC High People's Court on the morning of November 4.

Forecast of when typhoon Marce in the Philippines will reach hurricane strength

|

Typhoon Marce, the first storm to hit the Philippines in November, is forecast to soon reach severe tropical storm and typhoon strength.

Hanoi reclaims more than 320,000m2 of land to build 40-60.5m wide roads

|

Hanoi - Dan Phuong District plans to reclaim about 326,000m2 of land to build the 5.8km long Tay Thang Long road, with a cross-section of 40-60.5m, with a capital of nearly 1,300 billion VND.

4 national treasures at the Vietnam Military History Museum

|

2 fighter planes, tank 843... are National Treasures on display at the Vietnam Military History Museum.

Survey of North-South high-speed railway at Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The National Assembly's Economic Committee surveyed the investment location for the construction of a high-speed railway on the North-South axis at the Long Thanh airport project site.

Investing 1,400 billion VND in road connecting the North of Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai Provincial People's Committee is completing procedures to invest in a road worth more than VND1,400 billion connecting the northern area of ​​Long Thanh airport.

6,200 billion VND road expansion next to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai – DT 769 road, 30km long, located next to Long Thanh airport and passing through Long Thanh - Thong Nhat districts, will be upgraded and expanded.