Lao Cai comprehensively reviews nearly 900 billion VND project reflected as ineffective

Nhóm PV |

Lao Cai - Provincial People's Committee requests comprehensive inspection, clarification of progress, efficiency and related responsibilities at a nearly 900 billion VND agricultural project in Bao Thang commune.

On April 16, information from the Lao Cai Provincial People's Committee, the Chairman of the Provincial People's Committee has just issued instructions related to the content reflected in the article "Nearly 900 billion VND project in Lao Cai is not effective, people lack arable land" published in Lao Dong Newspaper.

Accordingly, the Chairman of the Provincial People's Committee assigned the Department of Finance to preside over and coordinate with relevant agencies and Bao Thang Commune People's Committee to organize a review of the entire content reflected in the press.

Hơn 539ha đất được giao cho Công ty TNHH thương mại Hoàng Lan để phục vụ sản xuất nông nghiệp nhưng đến nay chưa hiệu quả. Ảnh: Đinh Đại
More than 539ha of land was allocated to Hoang Lan Trading Co., Ltd. to serve agricultural production, but so far it has not been effective. Photo: Dinh Dai

The review focuses on the project implementation progress, including the level of completion of investment items compared to the approved plan.

At the same time, assess socio-economic efficiency such as job creation capacity, income for local people, as well as contributions to the state budget.

Along with that, functional agencies will clarify the responsibilities of relevant organizations and individuals in the project implementation process.

Trong khi đó, người dân địa phương phải chật vật mưu sinh vì thiếu đất canh tác. Ảnh: Đinh Đại
Meanwhile, local people are struggling to make a living due to lack of arable land. Photo: Dinh Dai

The Department of Agriculture and Environment is assigned to preside over the inspection of the management and use of land at the high-tech agricultural and forestry project in Bao Thang commune.

The inspection content includes compliance with legal regulations on land, agriculture and forestry, environmental protection, construction and related regulations.

Notably, land use will be specifically assessed according to the approved plan, clarifying the area that has not been put into use or used for the wrong purpose (if any).

At the same time, the progress and effectiveness of the implementation of crop and livestock items are also under inspection.

Nhiều công trình, diện tích đất bị bỏ không. Ảnh: Đinh Đại
Many works and land areas are abandoned. Photo: Dinh Dai

Lao Cai Provincial People's Committee requests relevant departments, branches, localities and Hoang Lan Trading Co., Ltd. to closely coordinate and provide complete dossiers and documents to serve the review process.

Based on the inspection results, the Department of Finance will summarize and advise the Provincial People's Committee on measures to handle existing problems and limitations; request investors to rectify or handle violations according to regulations if violations are detected. At the same time, propose solutions to ensure the legitimate rights of affected people.

The summary report must be completed and sent to the Provincial People's Committee before April 25, 2026.

Người dân mong chính quyền sớm có giải pháp nhằm tránh lãng phí tài nguyên đất. Ảnh: Đinh Đại
People hope that the Bao Thang commune government, Lao Cai province will soon have solutions to avoid wasting land resources. Photo: Dinh Dai

On the morning of April 16, in an exchange with a reporter from Lao Dong Newspaper, a representative of Hoang Lan Trading Co., Ltd. in charge of the project said that up to now, the unit has not received directing documents from the Provincial People's Committee or official information from local authorities. According to this person, all activities are still taking place normally.

Nhóm PV
RELATED NEWS

Difficult land use problem at a 895 billion VND high-tech project in Lao Cai

|

Lao Cai - A large-scale agricultural and forestry project in Bao Thang commune has been implemented for many years but is effective, posing a difficult problem for land use and people's livelihoods.

Lao Cai removes site obstacles, accelerates the progress of Apatite projects

|

Lao Cai - Cam Duong Ward coordinates with Apatit Vietnam Co., Ltd. to dialogue and remove difficulties in site clearance for projects in the area.

92.5 trillion VND project in Hanoi: Hundreds of people come to hear information about land acquisition

|

Hanoi - The work of land acquisition and site clearance for the Olympic Sports Urban Area project, with an investment of 925 trillion VND, is being actively implemented by communes.

People excitedly attend the Buddha bathing ceremony during the Chol Chnam Thmay Tet holiday

|

Ho Chi Minh City - Chôl Chnăm Thmây Tet at Candaransi Pagoda attracts a large number of people, highlighted by the Buddha bathing ritual and imbued with the identity of the Khmer people.

Terminating the operation of the National Traffic Safety Committee from June 1, 2026

|

The Prime Minister decided to terminate operations and dissolve the National Traffic Safety Committee and the Traffic Safety Boards of localities from June 1, 2026.

Case of teacher punishing 5 students for self-injecting needles in their hands: Test results have been available

|

Ho Chi Minh City - 5 students who were punished by teachers by self-injecting needles into their hands have blood counts within normal limits and are continuing to be monitored for their health.

Government directs inspection of the arrangement and assignment of deputy-level leaders

|

The Government requests inspection and supervision of legal regulations on arranging and assigning the number of deputy-level leaders according to regulations.

Trusting Lao Dong Newspaper to maintain its No. 1 position in protecting workers

|

Hanoi - At a working session with Lao Dong Newspaper on the morning of April 16, Chairman of the Vietnam General Confederation of Labor Nguyen Anh Tuan expressed his belief that Lao Dong Newspaper will continue to maintain its number 1 position in protecting workers.

Difficult land use problem at a 895 billion VND high-tech project in Lao Cai

Nhóm PV |

Lao Cai - A large-scale agricultural and forestry project in Bao Thang commune has been implemented for many years but is effective, posing a difficult problem for land use and people's livelihoods.

Dự án gần 900 tỉ đồng ở Lào Cai không hiệu quả, dân thiếu đất canh tác

Nhóm PV |

Lào Cai - Quy mô lớn, vốn đầu tư cao nhưng Dự án Nông lâm nghiệp ứng dụng công nghệ cao tại xã Bảo Thắng chưa tạo chuyển biến rõ rệt về hiệu quả sử dụng đất.

Lao Cai removes site obstacles, accelerates the progress of Apatite projects

Đinh Đại |

Lao Cai - Cam Duong Ward coordinates with Apatit Vietnam Co., Ltd. to dialogue and remove difficulties in site clearance for projects in the area.