Many shortcomings exposed in urban planning of 8,800 hectares

ĐÌNH TRỌNG |

Binh Duong Provincial Inspectorate has pointed out many shortcomings and problems of agencies when planning an urban area of ​​more than 8,800 hectares.

Binh Duong Provincial Inspectorate has conducted an inspection and issued a notice of inspection conclusion on planning and implementation of construction planning in the period 2015-2022 at Binh Duong Department of Construction. During this period, the Department of Construction advised the Provincial People's Committee to approve 20 new planning projects.

Binh Duong Provincial Inspectorate has selected 2 planning projects appraised by the Department of Construction, including the Lai Uyen Urban Master Plan until 2030, Bau Bang District, Binh Duong Province, with Bau Bang District People's Committee as the investor.

The previous planning site was mainly agricultural land, with a large land area of ​​up to 8,835 hectares. The target population by 2020 is 90,000 people.

Thanh tra do an
Inspector of Lai Uyen Urban Master Plan Project. Photo: Dinh Trong

Through inspection, Binh Duong Provincial Inspectorate discovered many shortcomings of related units when implementing this planning project.

Accordingly, the planning project documents did not clearly state whether the capital source used from the budget was public investment or career capital as prescribed. The People's Committee of Bau Bang City explained that the capital source for planning was career capital.

Bau Bang District People's Committee has not yet organized to collect full opinions from agencies, organizations, individuals and residential communities on planning tasks and planning projects as prescribed.

Bau Bang District People's Committee also did not have a document summarizing comments, explanations, acceptance, and reporting to competent authorities for consideration before deciding to approve according to regulations.

Thanh tra tinh phat hien nhieu diem bat cap khi lap do an. Anh: Dinh Trong
Provincial inspectors discovered many shortcomings in the project planning. Photo: Dinh Trong

Regarding the content of the planning project, the Binh Duong Provincial Inspectorate also pointed out that the basis for establishing the planning project did not specifically show the source of documents and data on the local socio-economic situation and related sectors, which is not in accordance with regulations.

The project also does not have data to calculate traffic volume, vehicle density, determine road characteristics and right-of-way, plan the traffic network for the area, and public transport.

The district People's Committee has not yet updated and explained some issues raised by the industry. Notably, the explanation of the scientific basis for population growth has not been shown in the planning project.

Regarding the organization of planning implementation, Bau Bang District People's Committee has not yet prepared, approved the documents and organized the implementation of marking in the field according to regulations. Bau Bang District People's Committee explained that due to insufficient capital allocation, it has not been implemented.

Cac thieu sot co trach nhiem cua So Xay dung trong cong tac tham dinh. Anh: Dinh Trong
Responsible shortcomings of the Department of Construction in appraisal work. Photo: Dinh Trong

Regarding the responsibility of the Binh Duong Department of Construction, the Provincial Inspectorate pointed out that the Department organized the appraisal and submission for approval at the same time of the task and the Lai Uyen Urban Master Plan project, which was not in accordance with the prescribed procedures.

The Provincial Inspectorate requested the Provincial People's Committee to request the Department of Construction to organize a review of relevant collectives and individuals, and rectify and overcome a number of shortcomings in the appraisal and approval of construction planning.

De nghi UBND huyen Bau Bang tien hanh cam moc quy hoach. Anh: Dinh Trong
Proposing the People's Committee of Bau Bang district to proceed with setting up planning markers. Photo: Dinh Trong

At the same time, direct the People's Committee of Bau Bang district to review and learn from the collectives and individuals who have committed the above shortcomings. Organize the preparation of records and set up boundary markers in the field. Ensure that lower-level planning complies with higher-level planning as a basis for implementing synchronous traffic infrastructure projects...

ĐÌNH TRỌNG
RELATED NEWS

20h News: Areas in Hanoi are about to ban gasoline vehicles from 2026

|

20h News: Where is Hanoi's Ring Road 1 about to ban gasoline vehicles, including which streets; The problem of printing shops in Lao Cai is worth billions of dong, some units have paid off debts...

1 year of the failed assassination of Mr. Trump, exposing the errors of the US Secret Service

|

A year after the failed assassination attempt on Mr Trump in Pennsylvania, the federal investigation report has just revealed a series of serious errors by the US Secret Service.

Dramatic moment to rescue 2 tourists who fell off a motorbike into a ravine in Hanoi

|

Hanoi - 2 tourists who fell onto a cliff on a motorbike in Ba Vi have just been rescued by authorities.

Current status of Hanoi Ring Road 1 will ban gasoline vehicles from July 2026

|

Hanoi is about to ban gasoline motorbikes from traveling on Ring Road 1, including the Hoang Cau - Voi Phuc section, the road considered "the most expensive on the planet".

Bất cập làm nhà trái phép trong vùng quy hoạch treo

Hoàng Bin |

Trong vùng quy hoạch treo hơn 20 năm của dự án khu hành chính cảng Kỳ Hà, Núi Thành, Quảng Nam, nhiều ngôi nhà kiên cố mọc lên, dù không được cấp phép.

Dự án 700 tỉ đồng chậm tiến độ, nhếch nhác gây nguy hiểm

ĐÌNH TRỌNG |

Bình Dương - Dự án đường ĐX02 nối dài, chỉ 3km nhưng thực hiện từ năm 2020 đến nay vẫn chưa xong. Nhiều điểm nhếch nhác, gây nguy hiểm cho người dân.

Lý do đơn vị tư vấn đấu thầu làm sai nhưng không bị xử phạt

ĐÌNH TRỌNG |

Tại Bình Dương, có những công ty tư vấn đấu thầu các dự án đầu tư công làm sai, nhưng không bị xử phạt do hành vi vi phạm đã quá thời hiệu xử lý.