Compensation, support and resettlement for high-speed railway projects from 2026

Bình Quý |

Khanh Hoa - From 2026 and 2028, the locality will implement compensation, support and resettlement for the North-South high-speed railway project through the area.

On October 1, the Khanh Hoa Department of Construction reported on the North-South High-Speed Railway Project through the province with a total length of about 191.8km. The route passes through 25 communes and 4 wards, starting at Dai Lanh commune (adjacent to Dak Lak province), ending at Phuoc Ha commune (adjacent to Lam Dong province).

In the province, there will be 3 stations (2 passenger stations, 1 cargo station) and 4 maintenance stations located in Tu Bong, Cam An, Xuan Hai and Phuoc Ha communes.

According to preliminary calculations, the project affects 5,467 households and 36 organizations, of which 1,829 households need to be resettled. The province plans to arrange 31 resettlement areas, including 13 existing areas and 18 newly built and expanded areas with a total cost of more than 1,744 billion VND.

Implementation progress, from now until December 2026: construction of resettlement areas. March to December 2026: counting, making compensation, support, and resettlement plans.

June 2026 to June: implement compensation, support, and resettlement.

The provincial leaders requested relevant departments, branches and localities to urgently review the plan, separate the project into sub-projects for easy implementation, and unify the application of compensation and resettlement policies.

At the same time, the Department of Construction coordinated with project management boards to review the location and scale of resettlement areas, survey construction materials to include in the list of national key projects.

Units and localities are also required to increase propaganda on policies, compensation and support mechanisms to create high consensus in the process of site clearance.

Bình Quý
RELATED NEWS

Prime Minister directs progress milestones for Lao Cai - Hanoi - Hai Phong railway project

|

The Prime Minister requested the development of a master plan for progress gas routes, site clearance, and component projects of the Lao Cai - Hanoi - Hai Phong railway line.

HCMC proposes to establish an Urban Railway Corporation to be able to operate a series of metro lines

|

Ho Chi Minh City - Urban Railway Corporation will have 4 main functions: capital mobilization; construction investment management; operation and maintenance; multi-industry business.

Hanoi flooded through the lens of an Australian filmmaker

|

An Australian tourist recorded footage of the spirit of Hanoians when facing storms.

Nearly 400 earthquakes, more than 170 casualties after 6.9 earthquake in the Philippines

|

Hundreds of aftershocks shook after the 6.9 earthquake in the Philippines, causing heavy damage to people and property.

Order to close the bottom spillway of Tuyen Quang hydroelectric reservoir, 3 provinces and cities must ensure safety

|

The bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 11am this afternoon.

List of flooded spots in Hanoi on the morning of October 1

|

Hanoi - As of this morning, the inner city area still has more than 20 flooded spots causing traffic difficulties such as in Vo Chi Cong, Thang Long Avenue, Duong Dinh Nghe...

No tax-free shopping center of 35,000m2 in Da Nang

|

Da Nang - VV Mall Shopping Center ( Vo Nguyen Giap Street, Da Nang City) has recently closed, with few buyers.

Prime Minister directs progress milestones for Lao Cai - Hanoi - Hai Phong railway project

PHẠM ĐÔNG |

The Prime Minister requested the development of a master plan for progress gas routes, site clearance, and component projects of the Lao Cai - Hanoi - Hai Phong railway line.

HCMC proposes to establish an Urban Railway Corporation to be able to operate a series of metro lines

MINH QUÂN |

Ho Chi Minh City - Urban Railway Corporation will have 4 main functions: capital mobilization; construction investment management; operation and maintenance; multi-industry business.

200 hộ dân phía Đông TPHCM di dời, nhường đất xây đường sắt tốc độ cao Bắc - Nam

MINH QUÂN |

TPHCM đẩy nhanh thu hồi đất khoảng 200 hộ dân làm đường sắt tốc độ cao Bắc - Nam, tổng kinh phí bồi thường, hỗ trợ, tái định cư gần 2.600 tỉ đồng.