Prime Minister directs progress milestones for Lao Cai - Hanoi - Hai Phong railway project

PHẠM ĐÔNG |

The Prime Minister requested the development of a master plan for progress gas routes, site clearance, and component projects of the Lao Cai - Hanoi - Hai Phong railway line.

On September 29, in Hanoi, Politburo member and Prime Minister Pham Minh Chinh chaired a meeting of the Government Standing Committee to listen to the report on the results of the First Session of the Vietnam - China Railway Cooperation Joint Committee and reviewed the situation and progress of the implementation of work, continuing to promote the implementation of the Lao Cai - Hanoi - Hai Phong railway project according to the set requirements.

According to the Resolution of the National Assembly, the Lao Cai - Hanoi - Hai Phong railway project is about 419 km long with a total capital of VND 203,231 billion, equivalent to USD 8.37 billion, starting in 2025 and striving to complete in 2030.

The Prime Minister has requested the groundbreaking of some construction items of the Lao Cai - Hanoi - Hai Phong Railway Project on December 19, 2025.

Concluding the meeting, the Prime Minister requested the Ministry of Science and Technology and the Ministry of Construction to urgently implement, appraise, and announce standards and regulations for high-speed railways and the Lao Cai - Hanoi - Hai Phong railway in accordance with the procedures, authority and regulations of law and international regulations, to be completed in October 2025.

The Ministry of Finance shall preside over and work with relevant agencies to review and calculate capital arrangement plans, including proactively developing Vietnam's capital sources and studying and proposing the most effective loan option.

At the same time, continue to work specifically with the Asian Infrastructure Investment Bank on the possibility of borrowing capital for the project; urgently report to the Government Standing Committee on specific plans in October.

The Prime Minister requested to urgently increase human resources and perfect the management boards of railway projects of the Ministry of Construction.

The Lao Cai - Hanoi - Hai Phong Railway Project Management Board continues to promote project implementation as soon as possible with the spirit of both doing and learning, drawing experience, and being proactive in implementing work, especially things that can be done by yourself.

The Prime Minister directs the Ministry of Construction and relevant agencies to develop a comprehensive plan for progress road, site clearance, and component projects.

In particular, for component project 1 (investing in infrastructure connecting stations on the route and station square, using domestic capital), the Prime Minister requested to complete the preparation and approval of the feasibility study report in October 2025; complete the technical design of the items to start construction before November 8; complete the selection of construction contractors and supervision consultants before December 5, complete site clearance and mine clearance within the construction area before December 19.

For component project 2 (investing in railway construction, using domestic capital and loans), the Prime Minister requested to urgently prepare a feasibility study report, to be completed by June 2026 at the latest, in the spirit of putting quality first and foremost; the appraisal and approval of the report must also be carried out urgently.

Regarding cooperation in railway industry development, the Prime Minister emphasized the viewpoint of implementing from low to high, from small to large, from simple to complex, to be as solid as possible.

The Prime Minister requested that together with the Lao Cai - Hanoi - Hai Phong railway project, it is necessary to continue promoting the Dong Dang - Hanoi and Mong Cai - Ha Long - Hai Phong railway projects connecting Vietnam - China.

PHẠM ĐÔNG
RELATED NEWS

Set to start construction of 2 major railway projects in the North on December 19

|

The Prime Minister requested consideration of selecting investment forms and investors for high-speed railway projects in accordance with procedures and authority in October.

Hanoi's intra-regional metro railway may extend to Ninh Binh

|

Deputy Prime Minister Tran Hong Ha has directed the proposal to allow the extension of the intra-regional metro line from Hanoi to Ninh Binh province.

Prime Minister requests to strengthen railway traffic order and safety

|

There have been 65 railway traffic accidents nationwide, killing 45 people and injuring 16 people in the first 7 months of 2025.

China lifts ban on strategic metal exports to the US

|

China has lifted a ban on exports of some key strategic metals to the US, effective from November 9.

On the day of completion, a chemical company in Lam Dong had a big explosion, killing 2 people

|

Lam Dong - The explosion that occurred at HC Bao Lam Joint Stock Company, in Bao Lam 1 commune, killed two workers on the day of completion.

From the Song Lo bridge case, the issue of project quality control is raised

|

The Lo River Bridge was designed to be built with a life of 100 years, but after only 10 years of operation, there have been signs of deterioration.

EU faces serious shortage due to Ukraine aid

|

The EU risks a sharp increase in deficits and public debt if it does not use Russian assets as collateral for Ukraine's aid, while Belgium opposes it due to legal risks.

Storm swept away roads, more than 1,000 people in Gia Lai isolated

|

Gia Lai - After the storm, heavy rain and strong water flowed a section of the road leading to Hratch village, So commune, leaving more than 1,000 people isolated.

Set to start construction of 2 major railway projects in the North on December 19

PHẠM ĐÔNG |

The Prime Minister requested consideration of selecting investment forms and investors for high-speed railway projects in accordance with procedures and authority in October.

Hanoi's intra-regional metro railway may extend to Ninh Binh

PHẠM ĐÔNG |

Deputy Prime Minister Tran Hong Ha has directed the proposal to allow the extension of the intra-regional metro line from Hanoi to Ninh Binh province.

Prime Minister requests to strengthen railway traffic order and safety

PHẠM ĐÔNG |

There have been 65 railway traffic accidents nationwide, killing 45 people and injuring 16 people in the first 7 months of 2025.