Bac Ha White Plateau is about to have a 200 billion VND hospital

|

Lao Cai - After the subsidence incident, the project to build the Bac Ha District General Hospital (BVDK) with an investment capital of 200 billion VND is being accelerated again.

In early March 2025, at the construction project of the Bac Ha district general hospital located in Bac Ha town, according to the reporter of Lao Dong Newspaper, after 3 years of construction, the project has completed many items and is in the process of accelerating construction.

At the time of recording, some items such as the 6-storey apartment building were in the process of completing the rough construction, the 3-storey administrative building and pharmacy warehouse were basically completed.

In addition, a series of other auxiliary items, traffic roads, internal roads, and electricity and water systems are being actively implemented by units to complete the progress on time.

Nhieu hang muc tai BVDK huyen Bac Ha (Lao Cai) dang trong qua trinh hoan thien sau 1 nam dung thi cong. Anh: Dinh Dai
Many items at Bac Ha District General Hospital (Lao Cai) are in the process of completion after 1 year of stopping construction. Photo: Dinh Dai

Ms. Thao Thi Din (Bac Ha town) said that this hospital had to stop construction for a while due to cracked walls, but has now resumed construction since the beginning of 2025.

"The state's attention to investing in a new modern hospital in the district has made everyone excited. Hopefully, after the construction is completed, our people will be examined and treated right in the white plateau without having to go far as before," Ms. Din shared.

Tong muc dau tu cua du an la 200 ti dong nham nang cao nang luc kham chua benh cua cac co so y te trong tinh Lao Cai. Anh: Dinh Dai
The total investment of the project is 200 billion VND to improve the capacity of medical examination and treatment facilities in mountainous areas. Photo: Dinh Dai

Through research, the project is invested by the People's Committee of Bac Ha district, approved with the goal of building a new hospital with a scale of 250 beds, on a total area of 50,755m2.

The total investment is 200 billion VND, with investment capital from the central budget for the period 2021 - 2025.

The Bac Ha District General Hospital project has been under construction since 2022, expected to be completed by the end of 2024.

The representatives of the construction contractor are the Joint Venture of Truong Son One Member Co., Ltd. - Duc Tuan Construction Investment Co., Ltd. - Lao Cai Construction Co., Ltd. - Sang Son Co., Ltd. - 19-8 Construction Co., Ltd. and Dements - Dists.

Sau khi khac phuc sut lun do dia chat, du an da thi cong tro lai. Anh: Dinh Dai
After overcoming the subsidence due to geology, the project has resumed construction. Photo: Dinh Dai

However, in the mid- to late 2023 period, during the construction process, on the main house area (in the case of a 6-storey block), there was a phenomenon of subsidence and many cracks appeared on the wall surfaces of the project.

According to the report of the People's Committee of Bac Ha district, during the construction of items under the District General Hospital Project, there was prolonged heavy rain in the area. By the end of August 2023, there was a phenomenon of subsidence of the floor of the main house area (6-storey apartment building).

After the discovery, the District People's Committee requested the construction unit to dig additional drainage ditches to prevent water from flowing into the subsided ground. At the same time, the design consultant unit is required to conduct a geophysical survey of the construction area of the project's main house.

Mot so hang muc nha da xay xong phan tho. Anh: Dinh Dai
Some items of the house have completed the rough construction. Photo: Dinh Dai

It is known that up to now, after finding the cause and having a solution, the project has resumed construction.

On March 3, speaking with a reporter from Lao Dong Newspaper, Mr. Ha Duc Thanh - Director of the Bac Ha District Construction Investment Project Management Board - said: "The Bac Ha District General Hospital construction project had to stop construction for about a year due to subsidence. Therefore, the unit has requested an extension of the completion time. Currently, the contractor is speeding up construction again and is expected to hand over the hospital by October".

TIN LIÊN QUAN

Dead pigs enter slaughter area, Quang Tri requests to tighten quarantine

|

Quang Tri - The discovery of dead pigs with signs of disease being transported to the concentrated slaughter area raises concerns about the risk of dirty food entering the market.

The possibility of a storm or tropical depression appearing in the East Sea

|

According to the meteorological agency, there is a high probability that there will be a tropical cyclone (storm/tropical depression) in the East Sea in the middle of this week.

Round 11 of the 2025 National Futsal Championship: Thai Son Nam HCMC reclaims the top spot

|

The big win in the late match of round 11 helped Thai Son Nam HCMC reclaim the leading position in the HDBank national futsal championship 2025 rankings.

Mr. Trump delays the bill to impose 500% tax on Russian partners

|

Mr Trump's stance has prevented US Senators from pushing for a bill to sanction Russia.

Plane crashes in the US, many victims hospitalized

|

The plane crashed shortly after takeoff from the Tullahoma regional airport in Tennessee (USA) at around 0:45 on June 9, Hanoi time.

5 new points on health insurance take effect from 1.7.2025

|

From July 1, 2025, many new regulations on health insurance will take effect, directly affecting people's rights to medical examination and treatment.

International visitors impressed by the spirit of Vietnam at the CAND Glory event

|

HCMC - Many international tourists were impressed and admired the patriotism and silent sacrifice of the Vietnamese army and people through the event of the Glory of the People's Public Security.

Bac Ha has a new Vice Chairman of the district

Đinh Đại |

Lao Cai - On the afternoon of February 27, the People's Council of Bac Ha district held its 25th session to elect the position of Vice Chairman of the District People's Committee.

Admiring plum blossoms in full bloom on the white plateau of Bac Ha in early spring

Đinh Đại |

Lao Cai - After Tet, the fields of the Bac Ha white plateau were covered in white plum blossoms.

Chủ tịch huyện Bắc Hà nói về đường 300 tỉ đồng chậm tiến độ

Đinh Đại |

Lào Cai - Chủ tịch UBND huyện Bắc Hà đã đưa ra những lý giải về việc nhiều hộ dân phải dựng lều bạt sống tạm bợ sau khi thi công đường vành đai 2.