With a construction permit, the project must still meet the conditions for commencement

Như hạ |

The 2025 Construction Law clearly stipulates the conditions for starting construction from July 1, 2026.

The 2025 Construction Law (effective from July 1, 2026) stipulates many new points on construction works. Based on Article 48 of the 2025 Construction Law stipulating conditions for starting construction works. Specifically:

Article 48. Conditions for starting construction of works

1. The commencement of construction of works, except for cases specified in Clauses 2 and 3 of this Article, must ensure the following conditions:

a) Having a construction site for complete or partial handover;

b) Having a construction permit as prescribed in Article 43 of this Law;

c) Having the construction drawing design of the project part, project item, and commencement project that has been approved;

d) The investor has concluded a construction contract with the contractor to carry out construction activities related to the project started according to the construction progress;

e) The investor has sent a construction commencement notice in writing or online (except for individual houses of households and individuals) to the state management agency for construction in the locality.

2. The commencement of construction of the following works only needs to meet the conditions specified in point a, clause 1 of this Article:

a) Emergency, urgent works and works under special public investment projects;

b) The project needs to start soon according to the direction of competent authorities decided by the Prime Minister.

3. The commencement of construction of individual houses of households and individuals only needs to meet the conditions specified in point b, clause 1 of this Article and is built on legal residential land according to the provisions of land law.

Như hạ
RELATED NEWS

Ministry of Construction answers cases where construction permits are not exempted

|

The Ministry of Construction said that individual houses in construction areas identified in the commune's general plan are not eligible for exemption from construction permits.

Dossier requesting a permit for repair, renovation, and relocation of works from July 1, 2026

|

Decree 217/2026/ND-CP clearly stipulates the components of the dossier requesting a permit for repair, renovation, and relocation of works.

Conditions for issuing construction permits with a term from July 1, 2026

|

Decree 217/2026/ND-CP details the conditions for projects to be granted a term construction permit.

Suspected digestive disorders after semi-boarding meal, many parents still haven't sent their children to school

|

Although the school has welcomed children back, many parents of Hoa Sen Kindergarten have not sent their children to school because there are no food sample test results for semi-boarding meals.

Promoting digital transformation, creating new growth momentum for tourism

|

The Ministry of Culture, Sports and Tourism identifies the development of the cultural industry, digital transformation and institutional improvement as key tasks in the second half of the year.

Unfinished rural roads, people petition to clarify project implementation

|

Lao Cai - The Na Sam - Ban No rural road project in Van Ban commune has been delayed for nearly 3 years, causing people to be upset and continuously petition.

Passersby recount the moment they were chased and smashed cars by a group of thugs

|

Thanh Hoa - Passersby are still in shock when recounting the time when they were chased by a group of motorcyclists, blocked and thrown hard objects to damage the car.

Experts propose building a marine industry exhibition house in Duy Nghia sedimentary area

|

Da Nang - To make the Trung Phuong sedimentary area (Duy Nghia commune) a resource for tourism development, experts propose forming a marine occupation exhibition house.