Accordingly, the unit price for selling social housing before adjusting the positioning coefficient is 24,818,000 VND/m2 (including value-added tax, excluding maintenance costs).
The Department of Construction of Quang Ninh province requests that within 180 days from the date of acceptance of the completed construction project and putting it into use, the investor is responsible for carrying out the State Audit or independent audit, finalizing construction investment costs in accordance with the provisions of housing law, construction law and other relevant legal regulations.
In case the selling price of social housing according to the audit, finalization and inspection results of the Department of Construction is higher than the selling price signed by the investor, the investor is not allowed to collect additional differences from social housing buyers; in case it is lower, the investor must return the difference to social housing buyers.
The investor is not allowed to collect money exceeding 95% of the contract value until the home buyer is granted a Certificate of land use rights, ownership of assets attached to land and completes the return of the difference (if any).
The Social Housing Area project at Da Giac 3, Hung Thang Service Urban Area, Bai Chay ward was started on December 19, 2025. According to the plan, the project will be completed in 2029.
The project has a total land use area of 29,758.66 m2; the expected population scale is about 5,000 people.
The project includes 2 social housing apartment buildings and 1 commercial housing apartment building.
The total number of apartments is 2,645, including 2,093 social housing units; 542 commercial housing units; 10 commercial service units.
Apartment area from 45 m2 to 69.9 m2.